First Street Project Schedule <br />Item <br />EXHIBIT 3 <br />Date <br />Plan Check Complete - Building Permit Ready <br />01/16/18 <br />Partnership Closing <br />02/28/18 <br />Construction Start <br />03/01/18 <br />50% Complete <br />12/01/18 <br />Construction Completion (18 months) <br />09/01/19 <br />Final Certificate of Occupancy <br />09/01/19 <br />Complete Move In Tenants <br />12/31/19 <br />3 -months stabilized occupancy <br />03/31/20 <br />Close on Permanent Financing/Conversion <br />03/31/20 <br />Receive 8609 Certificate from TCAC <br />09/30/20 <br />3-107 <br />