								        			The total cost of Change Order Number 006, Item B is twenty-three thousand, three hundred
<br />    			seventy-one  and  40/100  dollars  ($23,371.40).  This  sum  constitutes  full  and  complete
<br />    			compensation for furnishing all labor, materials, equipment, tools, and incidentals including all
<br />    			markups by reason of this Change Order 006, Item B. No additional working days are added as
<br />    			part of this Change Order 006, Item B.
<br />     									CHANGE ORDER NUMBER 006, ITEM B COST: $23,371.40
<br />       		3.  This Change Order Number 006, Item C provides additional compensation to transport and install
<br />    			bus shelter with ad signage as described in COR#14 at bus stop located near Main St and Buffalo
<br />    			Ave. (approximately eastern side of road at 2129 Main St, Santa Ana, CA 92706 with delivery of
<br />    			shelter to adjacent parking lot). All labor, materials, and equipment necessary to transport and
<br />    			install the bus shelter are included in this Change Order Number 006, Item C.
<br />    			Work to be paid at agreed price in accordance with Section 7-3.7-"Agreed Price" of the Standard
<br />    			Specifications for Public Works Construction. The total cost of Change Order Number 006, Item
<br />    			C is eighteen thousand, eighty and 59/100 dollars ($18,080.59). This sum constitutes full and
<br />    			complete compensation for furnishing  all  labor,  materials,  equipment, tools, transport,  and
<br />    			incidentals including all markups by reason of this Change Order 006, Item C. Two (2) additional
<br />    			working days are added as part of this Change Order 006, Item C.
<br />    									CHANGE ORDER NUMBER 006, ITEM C COST: $18,080.59
<br />       		4.  This Change Order Number 006, Item D provides additional compensation to adapt proposed
<br />    			vault to existing vault as described in COR #12 and CRB No. 04. All labor, materials, and
<br />    			equipment necessary to furnish, construct, and install COR#12 and CRB No. 04 are included in
<br />    			this Change Order Number 006, Item D.
<br />    			Work to be paid at agreed price in accordance with Section 7-3.7-"Agreed Price" of the Standard
<br />    			Specifications for Public Works Construction. The total cost of Change Order Number 006, Item
<br />    			D  is forty-seven thousand,  two hundred thirty and  09/100 dollars  ($47,230.09). This sum
<br />    			constitutes full and complete compensation for furnishing all labor, materials, equipment, tools,
<br />   			transport, and incidentals including all markups by reason of this Change Order 006, Item D.
<br />   			Three (3) additional working days are added as part of this Change Order 006, Item D.
<br />    									CHANGE ORDER NUMBER 006, ITEM D COST: $47,230.09
<br />       		5.  This Change Order Number 006, Item E provides additional compensation to procure and install
<br />   			SCE pull box, upsize PVC conduit, and substitute slab box lid. All labor, materials, and equipment
<br />   			necessary to furnish and install items described in COR #2 are included in this Change Order
<br />   			Number 006, Item E.
<br />   			Work to be paid at agreed price in accordance with Section 7-3.7-"Agreed Price" of the Standard
<br />   			Specifications for Public Works Construction. The total cost of Change Order Number 006, Item
<br />   			E is twenty-three thousand, six hundred forty-eight and 50/100 dollars ($23,648.50). This sum
<br />   			constitutes full and complete compensation for furnishing all labor, materials, equipment, tools,