PM/LA LA/QA SID SLD LCAD PME CQA PE ENG HYDENG CCORD ADM SVY EE GEO ENV SPOHN Total Reim.
<br />$185 $200 $155 $155 $125 $230 $225 $200 $180 $225 $130 $130 LS LS LS LS LS $$
<br />A Project Coordination 30 6 4 7,450$ 100$
<br />B Records Research 4 4 2 4 4 2 3,320$ 100$
<br />C.1 Conceptual Plan (30%), 3D Exhibit / Final Schedule 24 4 4 50 4 12 8,500$ 23,690$ 250$
<br />C.2 Preliminary Hydrology and Hydraulics Analysis 1 2 4 8 40 4 2 12,765$ 100$
<br />D Topographic Survey 1 2 11,500$ 12,145$ 200$
<br />E Preliminary WQMP 1 2 4 40 16 2 12,685$ 100$
<br />F Public Outreach and Project Meetings 16 12 24 8,360$ 500$
<br />G Utility Coordination 2 2 2 8 4 4 3,760$ 100$
<br />H Environmental (TBD)6 3 6 58,900$ 61,990$ 200$
<br />Final Construction Documents (90%-100%)
<br />I.1 Geotechnical Investigation and Report 1 2 2 20,275$ 21,180$ 500$
<br />I.2 Horizontal Control Plans 2 1 4 6 16 2 5,840$ 100$
<br />I.3 Grading and Drainage Plans 4 6 6 16 48 2 15,570$ 100$
<br />I.4 Composite Storm Drain, Sewer and Water Plan 2 2 4 16 40 2 12,390$ 100$
<br />I.5 Erosion Control Plan 2 1 1 1 8 2 2,725$ 100$
<br />I.6 Final Water Quality Management Plan 1 2 4 24 16 4 9,745$ 100$
<br />J.1 Site Construction Plan 40 8 90 2 20,510$ 100$
<br />J.2 Planting Plan 16 4 60 11,260$ 100$
<br />J.3 Irrigation Plan 4 120 2 19,600$ 100$
<br />J.4 Skate Park Plan 4 1 9,500$ 10,440$ 100$
<br />J.5 Landscape Construction Details 20 10 80 15,700$ 100$
<br />J.6 Final Color Rendering 4 1 32 4,940$ 100$
<br />K Electrical Plans 6 1 13,900$ 15,210$ 100$
<br />L.1 Final Construction Documents 8 4 8 8 16 8,680$ 100$
<br />L.2 Technical Specifications 16 6 12 8 4 4 6 10,060$ 100$
<br />L.3 Final Opinion of Probable Cost 12 2 8 1 2 8 5,980$ 100$
<br />L.4 Plan Submittals, Approval Process, and Permitting 16 12 40 4 4 8 2 2 13,760$ 300$
<br />Optional Tasks / Construction
<br />M.1 Bid Advertisement 8 8 3,320$ 150$
<br />M.2 Construction Administration 20 8 16 8 6 10,840$ 1,000$
<br />M.3 As Built Plans 4 16 2 4 8 5,540$ 250$
<br />Total (excluding optional tasks)272,855$ 3,950$
<br />Optional Task Environmental 58,900$
<br />Optional Task Skatepark 18,000$
<br />Optional Tasks (M.1 - M.3)19,700$ 1,400$
<br />Reimbursables included for budgetary purposes only.
<br />Colored areas are not included in the total but are shown as optional.
<br />Legend:
<br />PM/LA=Project Manager Landscape Architect, LA/QA - Senior Landscape
<br />Architect / Quality Assurance, SID=Senior Irrigation Designer, SLD=Senior
<br />Landscape Designer, LCAD=Landscape CAD, PME= Project Manager
<br />Engineering, CQA=Civil Quality Assurance, PE=Professional Engineer,
<br />ENG=Engineer, HYDENG=Hydrology Engineer, CCORD=Civil Coordinator,
<br />ADM=Administrative, SVY=Survey, GEO= Geotechnical Engineer, EE=Electrical
<br />Engineer, SPOHN=Skatepark Designer, ENV=Environmental
<br />Please note that scope and fee are negotiable.
<br />City of Santa Ana
<br />10th and Flower Park
<br /> Project Fee Schedule
<br />Task &
<br />Description
<br />
<br />
<br />City Council 17 – 75 5/2/2023
|