CITY OF SANTA ANA <br /> PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> Project Number Project No. 18-2681 —Centennial Lake Renovation Change Order Number 3 <br /> To CJW Construction Contractor <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE:THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actually used and no allowance will he made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> The compensation both time and cost set forth in this change order comprises the total compensation due the <br /> Contractor, all Subcontractors, and all Suppliers for all work performed per this change order, including impact <br /> on unchanged work. 13y signing this change order, the Contractor acknowledges and agrees on behalf of <br /> himself, all Subcontractors, and all Suppliers, that the stipulated compensation includes payment for all work <br /> contained in this change order, plus all payment for interruption of schedules, extended field overhead, home <br /> office overhead, profit, delay, and all impact, ripple effect or cumulative impact on all other work under this <br /> Contract. The signing of this change order constitutes full mutual accord and satisfaction for all changes and <br /> work performed on this project, and that the time and cost paid per this change order constitutes the total <br /> equitable adjustments owed the Contractor, all Subcontractors, and all Suppliers for all work performed on <br /> this project. The Contractor on behalf of himself, all Subcontractors, and all Suppliers agrees to waive all <br /> rights, without exception or reservation of any whatsoever to file any further claim related to this project. <br /> TOTAL COST THIS CHANGE ORDER: DECREASE $ _____________ INCREASE W 122,305.42 <br /> By reason of this order the CONTRACT TIME complefion will be adjusted as follows: Zero(0)Working Days <br /> We the undersigned contractor have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide <br /> all Equipment,fumish all materials,except as may otherwise be noted above,and perform all service necessary for the work above specified,and will accept <br /> as full payment therefor the prices shown above <br /> Accepted,Date Sept. 17, 2025 Contractor CJW Construction <br /> B Titte Daniel Duarte - President <br /> Approval recommended 1py Date ZQ L + <br /> WOR S A EXECUTWE iREC OR <br /> Approved by i Date ate <br /> - 7i <br /> Cl TY MANAGER <br /> Attest: Date <br /> CITYCLE K <br /> Page 2 of 2 <br />