<br />Bid Results Summary
<br />RANK BIDDER’S NAME LOCATION BASE BID
<br />1 Dominguez General Engineering Inc.Pomona, CA $2,133,362
<br />2 CEM Construction Corp Montebello, CA $2,166,879
<br />3 Big Ben Inc.Irvine, CA $2,490,807
<br />4 Vasilij Inc.Irwindale, CA $2,497,508
<br />5 Ramona Inc.Arcadia, CA $2,887,829
<br />6 Colich & Sons L.P.Gardena, CA $3,356,288
<br />7 Kordich Construction Inc.Cypress, CA $3,614,148
<br />8 Mike Bubalo Construction Co., Inc.Baldwin Park, CA $4,067,887
<br />9 Griffith Company Brea, CA $4,161,671
<br />10 Excel Paving Co.Long Beach, CA $4,254,341
<br />11 SRK Engineering Escondido, CA $4,691,667
<br />Dominguez General Engineering, Inc. submitted the lowest responsive base bid, in the
<br />amount of $2,133,362 (Exhibit 2). As specified in the bid documents, the lowest bid shall
<br />be determined on the basis of the Base Bid. Based on the bid analysis and a
<br />contractor’s reference check, staff recommends awarding the construction contract to
<br />Dominguez General Engineering, Inc., in the amount of the base bid totaling $2,133,362
<br />(Exhibit 3).
<br />Dominguez General Engineering, Inc. has not performed as a prime contractor in the
<br />City of Santa Ana within the past five years. A reference check was made and good
<br />reviews were received from other public agencies regarding quality of work performed
<br />by Dominguez General Engineering, Inc.
<br />Project Delivery
<br />To deliver a complete project, in addition to the construction contract bid amount, the
<br />estimated total project delivery cost includes construction administration, inspection,
<br />and testing, along with an allowance for contingencies to account for unexpected or
<br />unforeseen conditions. Construction administration and inspection includes
<br />construction management and materials testing. As indicated in the Cost Analysis
<br />(Exhibit 4) and as summarized in the table below, the estimated total construction
<br />delivery cost of the project is $2,986,706.
<br />
<br />
<br />City Council 25 – 3 11/7/2023
|