Laserfiche WebLink
15. To compensate the contractor for procuring and installing anti-graffiti protection coating for the <br /> north side soundwall per PCO #53 dated February 15, 2024. <br /> AGREED PRICE: $35,700.00 <br /> Schedule impact: Five (5) working days <br /> TOTAL AGREED AMOUNT: $577,267.62 <br /> EXTRA WORK AT AGREED UNIT PRICE <br /> 16. Delete bid items 7,8, and 9 per PCO #38, dated August 7, 2023. <br /> ITEM# DESCRIPTION ESTIMATED UNIT UNITESTIMATED AMOUNT <br /> QUANTITY PRICE <br /> 7 *COLD MILLING (3" MAX) 165,000* SF $0.50 ($82,500.00) <br /> 8 *ASPHALT CONCRETE(ARH M) 2,220* TN $92.00 ($204,240.00) <br /> 9 *ASPHALT CONCRETE (HMA) 6,050* TN $77.00 ($465,850.00) <br /> ESTIMATED TOTAL: ($752,590.00) <br /> 17. Add bid items 7,8, and 9 to compensate the contractor for cost escalations for Trucking, Asphalt <br /> Material, and ARHM Material per PCO #38 dated August 7, 2023. <br /> ITEM# DESCRIPTION ESTIMATED UNIT UNITESTIMATED AMOUNT <br /> QUANTITY PRICE <br /> 7 *COLD MILLING (3" MAX) 165,000* SF $0.875 $144,375.00 <br /> 8 *ASPHALT CONCRETE(ARH M) 2,220* TN $145.00 $321,900.00 <br /> 9 *ASPHALT CONCRETE(H MA) 6,050* TN $120.00 $726,000.00 <br /> ***The above quantity is an estimate; contractor will receive payment based on the actual quantity <br /> installed in each progress payment. These bid items shall not be subject to the "25%" limit as stated in <br /> Section 3-2 of the Standard Specifications and as included in the project bid proposal*** <br /> ESTIMATED TOTAL: $1,192,275.00 <br /> TOTAL AGREED CHANGE ORDER COST: $1,769,542.62 <br /> TOTAL AGREED CONTRACT INCREASE COST: $1,016,952.62 <br /> City Council Page 3 of41 — 15 5/21/2024 <br />