Laserfiche WebLink
First Street Slope Stabilization Project <br /> July 16, 2024 <br /> Page 2 <br /> southside slope, replace damaged curb and gutter, improve drainage around the <br /> stormwater lift station, install additional security fencing, and deal with unforeseen site <br /> conditions and unsuitable soil. <br /> The recommended action will increase the project contingency by $625,000, thereby <br /> increasing the total estimated construction delivery cost to $6,725,000, as indicated in <br /> the Cost Analysis (Exhibit 3) and as summarized in the table below: <br /> Project Item Current Total Additional New Total <br /> Funding <br /> Construction Contract Bid Amount $5,018,520 $0 $5,018,520 <br /> Construction Administration, $581,000 $0 $581,000 <br /> Inspection, and Testing <br /> Contract Contingencies $500,480 $625,000 $1 ,125,480 <br /> TOTAL ESTIMATED Fs ,100,0006 $625,000 $6,725,000 <br /> CONSTRUCTION DELIVERY COST <br /> FISCAL IMPACT <br /> As indicated in the Cost Analysis, the total estimated construction delivery cost of the <br /> project is $6,725,000, which includes the construction contract, contract administration, <br /> inspection, testing, and an authorized contingency. <br /> On December 20, 2022, City Council approved $5,600,000 of American Rescue Plan <br /> Act (ARPA) funding for this project. On April 15, 2024, under City Manager <br /> authorization, an additional $500,000 was allocated to this project. At this time, an <br /> additional $625,000 of ARPA funding will be allocated to the contingency and added to <br /> the FY 2024-25 CIP (Exhibit 4). <br /> The following table summarizes funds budgeted and available in current FY 2024-25 for <br /> expenditure to complete construction of this project. Any remaining balances not <br /> expended at the end of the fiscal year will be presented to City Council for approval of <br /> carryovers to FY 2025-26. <br /> Accounting Unit - Accounting Unit <br /> Fiscal Account No. Fund - Account No. Amount <br /> Year (Project No.) Description Description <br /> Original Project Budget <br /> American ARPA-PWA, <br /> 2024-25 18117013-66220 Rescue Plan Improvements $6,100,000 <br /> (22-1341) Act (ARPA) Other Than <br /> Buildings <br /> Additional Funding <br /> City Council 17 — 2 7/16/2024 <br />