Standard and McFadden Protected Bike Lanes <br />Public Works Agency <br />September 17, 2024 <br />Slide 16 <br />Strategic Construction Phasing <br />To minimize community impacts, strategic phasing was <br />incorporated for this project. <br />•Phase 1:Standard from 1st to McFadden <br />–Est. November 2024 to February 2025 <br />•Phase 2: Standard from McFadden to Warner <br />–Est. March 2025 to June 2025 <br />•Phase 3: McFadden from Harbor to Bristol <br />–Est. June 2025 to September 2025 <br />•Phase 4: McFadden from Bristol to Grand & Balance of <br />Traffic Signals <br />–Est. October 2025 to June 2026