Laserfiche WebLink
FY24-25 CIP Project Status Update <br />Grand Ave Rehab: Warner-Edinger Streets 116,875 - - 116,875 Construction Complete, pending project closeout (retention release, <br />receipt of warranty bonds, final grant billing, etc.)Complete <br />Main St Rehab: Warner-Edinger Streets 90,264 - - 90,264 Construction Complete, pending project closeout (retention release, <br />receipt of warranty bonds, final grant billing, etc.)Complete <br />Civic Center Drive Bike Blvd Streets 61,320 - - 61,320 Complete Complete <br />North East Annexation Improvements Streets 711,814 - - 711,814 Construction Phase, 95% complete 12/2024 <br />Safe Routes to Schools: Kennedy & Villa Streets 1,144,810 -130,000 1,014,810 Construction phase, 90% complete 12/2024 <br />Safe Routes to Schools: Fremont & Spurgeon Streets 5,510,295 - - 5,510,295 Construction phase, 91% complete 12/2024 <br />Sidewalk Improvement Streets 75,049 - - 75,049 Design Phase, 25% complete 12/2024 <br />Legacy Square Transportation Improvements Project Streets 1,804,580 - - 1,804,580 Construction Phase, 0% complete 02/2025 <br />Raitt St Rehab: McFadden to 1st Streets 1,616,000 - - 1,616,000 Design Phase, 10% complete 03/2025 <br />Traffic Calming: Memory & Flower Bikeway Streets 1,300,743 -850,743 450,000 Design Phase, 30% complete 04/2025 <br />Grand Ave Rehab: McFadden-1st Streets 2,242,951 - - 2,242,951 Construction Phase, 0% complete 04/2025 <br />Pedestrian & Mobility Improvements Phase II Streets 2,827,250 2,827,250 - - Construction phase, 95% Complete 05/2025 <br />Neighborhood Safety Streetlights Phase I Streets 834,630 834,630 - - Construction 80% Complete 05/2025 <br />First St Slope Stabilization Streets 3,311,350 3,311,350 - - Construction, 95% complete 05/2025 <br />Pedestrian & Mobility Improvements Phase I Streets 202,500 202,500 - - Construction phase 99% complete 05/2025 <br />Pedestrian & Mobility Improvements Phase III Streets 322,120 322,120 - - Construction phase 90% complete 05/2025 <br />Safe Routes to Schools: Kennedy & Villa Streets 1,144,810 -130,000 1,014,810 Construction Phase, 90% complete 05/2025 <br />Project W Bus Shelter Streets 391,015 -166,034 224,981 Construction phase, 98% complete 05/2025 <br />Warner Ave Widening: Main to Oak Phase I Streets 7,676,656 -1,200,000 6,476,656 Construction Phase, 80% complete 06/2025 <br />Warner Ave Traffic Signal Synchronization Streets 100,000 - - 100,000 Construction complete; O&M 30% complete, OCTA led Project 06/2025 <br />MacArthur Blvd Traffic Signal Synchronization Streets 100,000 - - 100,000 Construction phase, 95% complete, OCTA led Project 06/2025 <br />Traffic Signal Install Chestnut/Zoo Streets 834,051 - - 834,051 Construction phase 30% complete 06/2025 <br />Bike Racks Throughout City Streets 136,405 - - 136,405 Design phase, 100% complete; working on construction advertisement 06/2025 <br />Flower & 3rd St Traffic Safety Streets 500,000 -500,000 -Design Phase; 95% Complete 06/2025 <br />Westminster Rehab: Clinton To Fairview Streets 102,720 - - 102,720 Design Phase, 50% complete 06/2025 <br />Hazard Ave Protected Bike Lane Streets 111,868 - - 111,868 Design Phase, 50% complete 06/2025 <br />Bus Stop Improvements Streets 396,955 - - 396,955 Construction Phase, 75% complete 06/2025 <br />Bristol Corridor Improvement - Warner & 17th Streets 6,228,834 - - 6,228,834 Design Phase, 99% complete 06/2025 <br />Active Transportation Safety Improvements-Warner Streets 506,072 - - 506,072 Design Phase, 25% complete 06/2025 <br />Euclid St Rehab: 1St To Hazard Streets 226,236 - - 226,236 Design Phase, 90% complete 06/2025 <br />Raitt St Rehab: McFadden To Civic Center Streets 903,228 - - 903,228 Design Phase, 25% complete 06/2025 <br />South Main Street Corridor Public Improvements Streets 875,678 -839,194 36,484 Construction Phase, 25% complete 06/2025 <br />Safe Routes to Schools: Davis Elementary Streets 1,910,565 65,920 - 1,844,645 Construction Phase 90% Complete 06/2025 <br />MacArthur Rehab: Fairview-Raitt Streets 820,408 - - 820,408 Design Phase, 25% complete 07/2025 <br />Warner Ave and Wright Street Traffic Signal Modification Streets 703,585 - - 703,585 Construction Phase, 5% complete 08/2025 <br />Neighborhood Safety Streetlights Phase II Streets 1,071,050 1,071,050 - - Construction 15% Complete 08/2025 <br />10th & Flower Street Improvements Streets 4,612,868 4,612,868 - - Construction phase, 0% complete 09/2025 <br />Traffic Calming Improvements Phase II: Cubbon & Birch St Streets 802,132 -802,132 -Construction phase, 5% Complete 09/2025 <br />First St Corridor Traffic Signal Synchronization Streets 339,849 - - 339,849 Construction complete; O&M 0% complete, OCTA led Project 09/2025 <br />Bristol St & Memory Lane Intersection Widening Streets 2,210,533 - - 2,210,533 Design Phase, 90% complete 09/2025 <br />Standard Ave Protected Bike Ln Streets 5,473,046 - - 5,473,046 Construction Phase, 0% complete 09/2025 <br />Bristol St Rehab: Santa Clara-Memory Streets 1,504,110 - - 1,504,110 Design Phase, 99% complete 09/2025 <br />Santiago Creek Pedestrian Bridge Impr Streets 740,000 - - 740,000 Design Phase, 25% complete 09/2025 <br />Segerstrom/Spruce Traffic Signal Streets 803,536 -671,402 132,134 Construction Phase; 15% Complete 09/2025 <br />Euclid St Corridor Traffic Signal Synchronization Streets 120,000 - - 120,000 Design 90% Complete; City of La Habra led project 09/2025 <br />1st St Rehab: Grand-Tustin Streets 843,041 - - 843,041 Design Phase, 90% complete 09/2025 <br />Standard Ave Rehab: 1st-Warner Streets 1,900,000 - - 1,900,000 Construction Phase, 0% complete 09/2025 <br />Raitt St Protected And Buffered Bikeway Streets 809,655 - - 809,655 Design Phase, 60% complete 09/2025 <br />Fairview A Rehab: City Limit-Seger Streets 6,247,602 - - 6,247,602 Design Phase, 90% complete 09/2025 <br />Main St Slurry Seal & Resurfacing Streets 833,824 - - 833,824 Design Phase, 60% complete 12/2025 <br />Bedford Rehab: Main Place to City Limit Streets 213,000 - - 213,000 Design Phase, 60% complete 12/2025 <br />OC Streetcar Streets 854,682 - - 854,682 Construction Phase, 80% complete, OCTA Led project 12/2025 <br />Civic Center Rehab: Minter to Santiago Streets 2,000,000 -714,000 1,286,000 Design Phase, 0% complete 12/2025 <br />Edinger Ave Traffic Signal Synchronization Streets 100,000 - - 100,000 Construction phase, 50% complete, OCTA led project 06/2026 <br />Segerstrom Ave & Dyer Rd Traffic Signal Synchronization Streets 245,768 - - 245,768 Construction phase, 95% complete, City of Irvine led Project 06/2026