Laserfiche WebLink
6. To compensate the contractor for asbestos around piping per RFI-0042 and CRX-0018. <br /> TOTAL AGREED PRICE =$7,993.25 <br /> 7. To compensate the contractor for the demolition scope adjustment per CRX-0021. <br /> TOTAL AGREED PRICE=$115,660.88 <br /> 8. To compensate the contractor for the demolition of existing beams at the new elevator per <br /> RFI-0061 and CRX-0023. <br /> TOTAL AGREED PRICE = $26,879.27 <br /> TOTAL AGREED INCREASE=$190,559.32 <br /> TOTAL AGREED CONTRACT CHANGE ORDER COST=$104,085.29 <br /> Page 2 of 3 <br />