- CITY OF SANTA ANA <br /> PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> T _ <br /> Project Number Project No. 22-1380 Main Library Renovation Project Change Order Number 7 <br /> To PCL Construction Services, Inc. Contractor <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE:THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> Unless otherwise stated,rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> EXTRA WORK AT AGREED PRICE <br /> 1. Existing Elevator Upgrade (Additional Scope Covered in Allowance) per ASI-004 & CRX- <br /> 0008. <br /> TOTAL AGREED PRICE = 88,686.49 <br /> 2. Landscape 8' High Fence Attachment Detail per RFI-0083 & CRX-0076. <br /> TOTAL AGREED PRICE=$7,892.34 <br /> 3. Basement Janitor's Room 023 Map Sink Install per RFI-0173.2 & CRX-0077.1. <br /> 1 TOTAL AGREED PRICE =$10,628.48 <br /> 4. Door Access Control per ASI-003 & CRX-0078. <br /> TOTAL AGREED PRICE= $128,830.72 <br /> 5. South Facade Window 114 Switch to Door per ASI-0022, RFI-0261, & CRX-0082. <br /> TOTAL AGREED PRICE = $15,531.33 <br /> 6. Basement Condensate & Cable Tray Conflict per RFI-0159.1 & CRX-0101. <br /> TOTAL AGREED PRICE=$13,241.56 <br /> 7. Sanitary Sewage Ejector Tank Install Conflict per RFI-0264 & CRX-0127. <br /> TOTAL AGREED PRICE=$13,718.73 <br /> 8. Level-1 Mechanical Diffusers Conflict w/Existing Opening per RFI-0251.2 & CRX-0128.1. <br /> TOTAL AGREED PRICE =$23,594.15 <br /> Page 1 of 6 <br />