CITY OF SANTA ANA <br /> SPECIFICATIONS <br /> PROJECT NO.: 25-6030 <br /> TRAFFIC SIGNAL INSTALLATION AT SEGERSTROM AVENUE AND ROSEWOOD <br /> AVENUE <br /> SECTION 6 - PROSECUTIONAND PROGRESS OF THE WORK <br /> 6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK <br /> 6-1.1 Construction Schedule <br /> Add the following to this subsection: <br /> A working day shall be defined as outlined below, and the Contractor's activities shall be confined <br /> accordingly: <br /> 1. From 9:00 a.m. to 3:00 p.m., Monday through Friday, for work requiring temporary <br /> lane closures, i.e. those having less than a 24-hour duration, and for work at major <br /> intersections. As an alternative, construction at major intersections may be permitted <br /> on Fridays, at night or on weekends, at the discretion of the Engineer. <br /> 2. From 7:00 a.m. to 5:00 p.m.,Monday through Friday, within work areas having either <br /> no lane closures or having continuous lane closures, i.e. 24-hour closures lasting more <br /> than one day. For work in, or adjacent to, residential areas, work shall not commence <br /> prior to 8:00 a.m. <br /> Deviation from these hours/days shall not be permitted without the prior consent of the Engineer, <br /> except in emergencies involving immediate hazard to persons or property, or as specified <br /> otherwise. <br /> Holidays as herein referred to shall be deemed to be: <br /> • New Year's Day • Independence Day <br /> • Martin Luther King Day • Labor Day <br /> • President's Day • Veteran's Day <br /> • Cesar Chavez Day • Thanksgiving Day and the day after <br /> • Memorial Day • Christmas Eve through New Year's Day <br /> In addition to the holidays listed above, the City has a holiday moratorium; refer to City of Santa <br /> Ana Standard Plan No. 1160. <br /> The Contractor is required to submit a comprehensive baseline schedule to the Engineer for <br /> approval before commencing construction.This schedule must detail the sequence of construction <br /> activities, including major milestones and critical path tasks. Throughout the construction phase, <br /> the Contractor shall provide monthly updates to the baseline schedule, reflecting the current <br /> progress of the project, completed tasks,work planned for the upcoming month, and any schedule <br /> changes. <br /> In addition to the baseline schedule and monthly updates,the Contractor shall also provide a rolling <br /> 3-week look-ahead schedule. This schedule should offer a detailed outlook of planned activities <br /> for the upcoming three-week period, focusing on immediate work activities as well as work <br /> completed in the previous week. The rolling look-ahead schedule must be submitted to the <br /> 17 <br />