CITY OF SANTA ANA DOWNTOWN PARKING STRUCTURE
<br />IMPROVEMENTS RFP NO. 24-100A
<br />Staff Allocations per Discipline:Cost Estimate Consultants
<br />Role/Classifications:Hours Fees Principal Overall PM Senior
<br />Arch
<br />Job
<br />Captain CAD Principal Senior
<br />Arch
<br />Job
<br />Captain CAD Principal Senior
<br />Eng
<br />Proj.
<br />Eng CAD Principal Senior
<br />Eng
<br />Proj.
<br />Eng CAD Elevator
<br />Consultant
<br /> Hourly Rate:220$ 211$ 185$ 132$ 118$ Hrs Fees 220$ 185$ 132$ 118$ Hrs Fees 220$ 185$ 175$ 118$ Hrs Fees 220$ 185$ 175$ 118$ Hrs Fees
<br />Task 1: Design Development 259 $60,710
<br />Kick-off Meeting / Site Investigation 14 $2,764 2 4 2 8 $1,654 2 2 $370 2 2 $370 2 2 $370
<br />Pre-Design / Research 21 $4,128 8 2 10 $2,058 1 2 3 $590 4 4 $740 4 4 $740
<br />Site & Engineering Design 55 $8,289 4 4 8 16 $2,640 1 2 4 7 $921 2 8 4 14 $2,242 2 4 12 18 $2,486
<br />Site Plan Review 16 $3,064 4 2 6 $1,214 2 2 $370 4 4 $740 4 4 $740
<br />Outline Specifications 4 $792 2 2 $422 0 $0 1 1 $185 1 1 $185
<br />Preliminary ROM Cost Estimate 1 $211 1 1 $211 0 $0 0 $0 0 $0
<br />Design Development (60% plans)148 $41,462 2 8 16 24 16 66 $10,144 2 8 4 14 $1,898 8 16 8 32 $5,224 8 16 12 36 $5,696 $12,500 $6,000
<br />Task 2: Construction Documents 264 $69,944
<br />90% Construction Documents 137 $30,845 8 16 24 24 72 $10,648 1 4 4 9 $1,185 4 12 8 24 $3,784 4 12 16 32 $4,728 $10,500
<br />100% Construction Documents 73 $21,275 4 4 8 8 24 $3,584 1 2 4 7 $921 2 8 8 18 $2,714 4 8 12 24 $3,556 $10,500
<br />Construction Cost Estimate 2 $422 2 2 $422 0 $0 0 $0 0 $0
<br />Technical Specifications 6 $1,162 2 2 $422 0 $0 2 2 $370 2 2 $370
<br />Final Construction Documents Submission 46 $16,240 8 2 4 14 $2,586 2 2 4 $634 4 8 12 $2,140 8 8 16 $2,880 $8,000
<br />Task 3: Bid Advertisement, Construction
<br />Administration, and Record Drawings 145 $26,933
<br />Plan Check & Permits 14 $2,778 8 4 12 $2,428 0 $0 1 1 $175 1 1 $175
<br />Final Construction Cost Estimate 2 $422 2 2 $422 0 $0 0 $0 0 $0
<br />Bid Advertisement 4 $844 4 4 $844 0 $0 0 $0 0 $0
<br />Construction Administration 76 $13,046 8 16 12 36 $6,232 2 4 2 8 $1,134 4 12 16 $2,840 4 12 16 $2,840
<br />Record Drawings / As-built Plans 49 $9,843 2 4 4 8 18 $2,634 1 2 4 7 $921 4 8 12 $1,644 4 8 12 $1,644 $3,000
<br /> TOTAL - Hours 4 79 72 84 56 295 1 16 24 22 63 0 37 69 36 142 0 43 65 60 168
<br />Fee Proposal Total $157,587
<br />Subtotal
<br />TOTAL Landscape Arch Electrical Civil Architecture
<br />Subtotal Subtotal Subtotal
<br />668
<br />12/13/2024 1
<br />
<br />
<br />City Council 13 – 29 2/18/2025
|