ENVIRONMENTAL IMPACT REPORT ADDENDUM <br />Bristol Street Widening Project Warner Ave to Saint Andrew Place (Phase IV) <br />1.4.3 Changes as Compared to the Approved Project <br />It should be noted that project phasing has been revised from the original three phases identified in the1990 <br />Final EISIEIR. Construction phasing of the entire project segment has been further subdivided as follows: <br />• St. Andrew Place to McFadden Avenue (Constructed in 2002) <br />• Elrn Street to Memory Lane (Constructed in 2003) <br />• Pine Street to 3r4 Street (Constructed in 2009) <br />• Phase I: McFadden Avenue to Pine Street (Constructed in 2011)' <br />• Phase II: 3`d Street to Civic Center Drive (Construction to be completed in 2014) <br />• Phase IIIA: Civic Center Drive to Washington Avenue <br />• Phase IIIB: Washington Avenue to 17t" Street <br />• Phase IV: Warner Avenue to St. Andrew Place <br />• Phase V: 17t" Street to Elra Street <br />The proposed street widening design configuration for the current Phase IV segment differs from the <br />original configuration of the 1990 Final EISIEIR, as follows: <br />• The proposed Project increases the total right-of-way width from 120 feet to 128 feet. The proposed <br />Project right-of-way cross-section would maintain a curb -to -curb width of 100 feet, would <br />accommodate a 7-foot wide bike lane on each side of the roadway, and would not affect the number <br />or width of vehicular travel lanes as compared to the right-of-way cross-section addressed in the <br />1990 FEISIEIR. However, the proposed Project right-of-way cross section, as compared to the right- <br />of-way cross section addressed in the 1990 FEISIEIR, would reduce the width of the sidewalks from <br />10 to 8 feet and also accommodate a 6-foot wide parkway on each side of Bristol Street to separate <br />pedestrian and vehicular travel; a parkway was not included as part of the roadway cross section <br />addressed in the 1990 FEISIEIR. Acquisition of property resulting from the proposed Project right- <br />of-way is accounted for in this analysis. <br />• The centerline alignment has been shifted to the west starting at St. Gertrude instead of starting at <br />Glenwood Place with the addition of 4-feet to the original 20-foot shift. The street centerline then <br />shifted back 4-feet to the east at St. Andrew in order to match the existing centerline north of St. <br />Andrew. By shifting the centerline at St. Gertrude, the Phase IV Project saved eight parcels from full <br />take by reducing these parcels to partial acquisitions. <br />• A bus turnout would be located at the Warner Avenue. <br />• Change right-of-way requirement from full take to partial take of the following single-family <br />residential parcels: 015-215-10 (150 square feet), 015-215-11 (50 square feet), 015-214-10 (50 <br />square feet), 015=234-10 (50 square feet), 015-233-11 (50 square feet), 015-233-10 (50 square feet), <br />015-232-11 (50 square feet), and (015-232-10 (50 square feet). <br />1 Phase numbers were assigned to the Bristol Street Widening Project subsequent to cancelation of the CenterLine <br />Light Rail Transit Project and associated reallocation of funding from that canceled project to the Bristol Street <br />Widening Project. <br />ANA 305494 (PER 02) CSA (AUGUST 2014) 133867 YU 15 <br />75C-29 <br />