<br />ATTACHMENT NO. 7 <br /> <br />SCHEDULE OF PERFORMANCE <br /> <br />FUNCTION <br /> <br />DEVELOPMENT <br /> <br />A. <br /> <br />Submission of Preliminary Plans DP <br />No. 2004-02 and CUP No. 2004-09. <br /> <br />I. Developer submits its <br />Preliminary Plan to Agency. <br /> <br />2. The Agency staff shall approve <br />or disapprove the Preliminary <br />Plan. <br /> <br />B. <br /> <br />Building Pennits for <br />Phase I - Parking structure including <br />construction drawings, <br />specifications, finish grading plans <br />and landscape plans. <br /> <br />c. <br /> <br />Demolition of improvements on <br />Parcel A. <br /> <br />D. <br /> <br />Building Permits for <br />Phase II - New showroom and office <br />area, including construction <br />drawings, specifications, finish <br />grading plans and landscape plans. <br /> <br />E. <br /> <br />Demolition of improvements on <br />Parcel B. <br /> <br />F. <br /> <br />Building Pennits for <br />Phase III - New sales, service, parts <br />and office addition to existing <br />Crevier building. <br /> <br />TIME OF PERFORMANCE <br /> <br />Completed <br /> <br />Completed <br /> <br />Submit evidence of building pennits and <br />proof of financing within 110 days after date <br />of Agency's execution of this Agreement. <br /> <br />Prior to start of construction on Phase I. <br /> <br />Submit evidence of building penn its and <br />proof of financing within 9 months after <br />commencement of construction of Phase I. <br /> <br />Prior to start of construction on Phase II. <br /> <br />Submit evidence of building permits and <br />proof of financing within 9 months after <br />commencement of construction of Phase II. <br />