6. To compensate the contractor for investigating and relocating an existing water service in <br /> conflict with the proposed sound wall foundation. Reference correspondence regarding <br /> COR#11 dated July 15, 2025. <br /> AGREED PRICE =$1,825.83 <br /> 7. To compensate the contractor for extra work to install jog outs of the sound wall at the SCE <br /> poles located on the East side of Bristol between Warner Ave. and St. Gertrude PI. Reference <br /> correspondence regarding COR#12 dated July 16, 2025. <br /> AGREED PRICE = $35,647.75 <br /> 8. To compensate the contractor for extra work to regrade and re-compact sound wall footing <br /> at the northwest. Reference correspondence regarding COR#15.1 dated July 30, 2025. <br /> AGREED PRICE =$2,133.50 <br /> 9. To compensate the contractor additional sound wall premiums on the west side between St. <br /> Gertrude Pl. to St. Anne Pl. Reference correspondence regarding COR#22 dated July 25, <br /> 2025. <br /> AGREED PRICE = $7,980.10 <br /> 10. To compensate the contractor for installing the sound wall foundations up to the jog outs for <br /> all SCE pole locations. Reference correspondence regarding COR#23 dated August 4, 2025. <br /> AGREED PRICE = $11,381.34 <br /> WORK PERFORMED UNDER DISPUTE AT CITY-APPROVED PRICE <br /> 11.To compensate the contractor for remove the existing traffic signal pull box at St. Andrew, <br /> and install additional conduit and wiring to Pole No. 8. Reference correspondence regarding <br /> COR#4.2 dated July 3, 2025. <br /> APPROVED PRICE.= $5,519.57 <br /> 12.To compensate the contractor for re-staking of the east sound wall from STA 23+54 to STA <br /> 26+06. Reference correspondence regarding COR#17 dated August 13, 2025. <br /> APPROVED PRICE =$813.05 <br /> 13.To compensate the contractor installing jog outs at the SCE poles on the west side on Bristol. <br /> Reference correspondence regarding COR#25 dated September 18, 2025. <br /> APPROVED PRICE =$59,254.30 <br /> TOTAL CHANGE ORDER COST= $155,731.47 <br /> TOTAL CONTRACT INCREASE COST = $72,949.47 <br /> *Execution of this Change Order constitutes agreement only as to the specific scope of work and <br /> cost described herein. Additional non-compensable working days will be added following a time <br /> impact analysis demonstrating the work, delay event, or other excusable causes that affected the <br /> project critical path in regards to the items noted above in this Change Order. <br /> Page 2 of 3 <br />