2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
<br />$842,630, which includes $674,104 for the construction contract, $101,115 for
<br />contract administration, inspection, and testing, and $67,411 for unanticipated or
<br />unforeseen work.
<br />3. Award a construction contract to GEMS Environmental Management Services, Inc.,
<br />the lowest responsible bidder, in accordance with the base bid in the amount of
<br />$674,104, subject to change orders, for construction of the Fire Station 74 Fuel
<br />Station Replacement Project (Project No. 24-6053), for a term beginning January 20,
<br />2026 and authorize the City Manager to execute the contract.
<br />4. Determine that, pursuant to the California Environmental Quality Act, the
<br />recommended actions are exempt from further review. Categorical Exemption
<br />Environmental Review No. ER-2025-116 will be filed for Project No. 24-6053.
<br />23. Award of a Construction Contract to Golden Gate Steel, Inc., to Construct the Portola
<br />Splash Pad Project (Project No. 25-2401) (Non -General Fund)
<br />Department(s): Public Works Agency
<br />Recommended Action: 1. Approve an amendment to the Fiscal Year 2025-26
<br />Capital Improvement Program to include an additional $2,467,500 in construction
<br />funds for the Portola Splash Pad Project (Project No. 25-2401).
<br />2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
<br />$2,467,500, which includes $1,974,000 for the construction contract, $296,100 for
<br />contract administration, inspection, and testing, and $197,400 for unanticipated or
<br />unforeseen work.
<br />3. Award a construction contract to Golden Gate Steel, Inc., the lowest responsible
<br />bidder, in accordance with the base bid in the amount of $1,974,000, subject to
<br />change orders, for construction of the Portola Splash Pad Project (Project No. 25-
<br />2401), for a term beginning January 20, 2026 and authorize the City Manager to
<br />execute the contract.
<br />4. Determine that, pursuant to the California Environmental Quality Act, the
<br />recommended actions are exempt from further review. Categorical Exemption
<br />Environmental Review No. ER-2025-118 will be filed for Project No. 25-2401.
<br />24. First Amendment to the Agreement with Musco Sports Lighting, LLC to Install
<br />Additional LED Lighting at Centennial Park Playground (Project No. 26-6007)
<br />(General Fund & Non -General Fund)
<br />Department(s): Public Works Agency
<br />Recommended Action: 1. Approve an amendment to the Fiscal Year 2025-26
<br />Capital Improvement Program to include an additional $186,978 in construction funds
<br />for the Centennial Park Lighting Project (Project No. 26-6007).
<br />2. Authorize the City Manager to execute a First Amendment to the agreement with
<br />Musco Sports Lighting, LLC to add playground LED sports lighting at Centennial
<br />City Council 13 1/20/2026
<br />
|