Fairview Street Rehabilitation from Southern City Limits to Alton Avenue
<br /> March 3, 2026
<br /> Page 3
<br /> advertised in PlanetBids from November 13, 2025 to December 11, 2025. Bids were
<br /> received electronically via PlanetBids on December 11, 2025.
<br /> A copy of construction plans, contracts, specifications, and all related reference
<br /> materials (such as The Greenbook) are available for public review at the City's Public
<br /> Works Agency, Central Files office located in City Hall.
<br /> Bid Results Summary
<br /> RANK BIDDER'S NAME LOCATION BASE BID +
<br /> ALTERNATES
<br /> 1 Onyx Paving Company, Inc. Yorba Linda, CA $2,728,000
<br /> 2 R.J. Noble Company Orange, CA $ 2,742,000
<br /> 3 Hardy & Harper, Inc. Lake Forest, CA $ 2,980,000
<br /> 4 Toro Enterprises, Inc. Oxnard, CA $ 3,207,010
<br /> 5 Vido Samarzich, Inc. Santa Ana, CA $ 3,241,720
<br /> 6 Excel Paving Co. Long Beach, CA $ 3,448,860
<br /> 7 All American Asphalt Corona, CA $ 3,461,115
<br /> NR RCCI Azusa, CA Non-Responsive
<br /> A total of eight (8) bids were received and seven (7) were deemed responsive. Staff
<br /> determined that RCCI's bid was non-responsive because it did not meet contract
<br /> specification requirements to self-perform more than 50% of the total contract value.
<br /> Onyx Paving Company, Inc. submitted the lowest responsive base bid in the amount of
<br /> $2,673,000 (Exhibit 3). As specified in the bid documents, the lowest bid shall be
<br /> determined on the basis of the Base Bid. The add-alternate scope of work in the bid
<br /> package is the installation of a traffic video detection system at Fairview Street and
<br /> Segerstrom Avenue to improve traffic control. The total bid including the add-alternate
<br /> scope of work is in the amount of $2,728,000 and still collectively lower than the other
<br /> bids including the alternative. Based on the bid analysis and a contractor's reference
<br /> check, staff recommends awarding the construction contract, including the add-alternate
<br /> scope, to Onyx Paving Company, Inc. (Exhibit 4).
<br /> Onyx Paving Company, Inc. has previously performed work as a prime contractor in the
<br /> City of Santa Ana within the past three (3) years, including two Local Street
<br /> Preventative Maintenance Projects and the Fremont Elementary and Spurgeon
<br /> Intermediate Safe Routes to School Projects. The Contractor satisfactorily completed
<br /> these projects and staff recommends awarding the construction contract to Onyx Paving
<br /> Company, Inc. for the construction of the Project.
<br /> Project Delivery
<br /> To deliver a complete project, in addition to the construction contract, the estimated total
<br /> project delivery cost includes a budget allocation for construction administration,
<br /> inspection, and testing. Construction administration and inspection may be performed
<br /> by either Staff or consultants and includes construction management, inspection of the
<br /> City Council 17 — 3 3/3/2026