Award a Construction Contract to R.J. Noble Company for the Construction of the Grand <br /> Avenue Rehabilitation from Edinger Avenue to McFadden Avenue Project <br /> March 3, 2026 <br /> Page 4 <br /> Milestone Estimated Notes <br /> Completion <br /> Contractor Mobilization Aril 2026 Start of construction activities <br /> Project Completion July 2026 Based on 45 working days <br /> Protect Phasing <br /> The contractor will be constructing this project in a singular phase, fulfilling the scope of <br /> work as outlined in the contract documents. The contractor is responsible for determining <br /> the scheduling and sequencing of activities based on their proposed means and methods. <br /> Public Outreach <br /> The project scope will impact nearby businesses and residences. To ensure timely and <br /> effective communication, the following notification measures will be implemented prior to <br /> the start of construction: <br /> • Electronic message signs will be installed two weeks in advance of construction <br /> activities to provide early notice of the project's start date, <br /> • A project information sign will be posted at the construction site, including contact <br /> information for public inquiries, <br /> • Residents and businesses within 1,000 feet of the project limits will receive door <br /> hanger or mailed notifications at least two weeks before construction begins, <br /> • A second round of notification will be issued 48 hours prior to the start of <br /> construction to residents and business adjacent to the limits of work, and <br /> • The City will also disseminate information through its official website and social <br /> media platforms to keep the public informed of construction activities, including <br /> any lane closures. <br /> The Contractor is required to issue construction notices to adjacent residents and <br /> businesses at least two weeks before construction begins. Additionally, the contractor is <br /> required to install signage at the project site indicating project details and contact <br /> information. <br /> ENVIRONMENTAL IMPACT <br /> Pursuant to the California Environmental Quality Act (CEQA), the recommended actions <br /> are exempt from further review pursuant to Section 15301(c) of the CEQA Guidelines <br /> for projects consisting of existing highways and streets, sidewalks, gutters, bicycle and <br /> pedestrian trails, and similar facilities. The proposed project continues to meet these <br /> parameters of the CEQA Guidelines, and Categorical Exemption Environmental Review <br /> No. ER-2023-91 will be filed for Project 23-6700 (Exhibit 4). <br /> FISCAL IMPACT <br /> As indicated in the Cost Analysis, the estimated total construction delivery cost of the <br /> project (No. 23-6700) is $1,243,213. All funds are available for expenditure in Fiscal Year <br /> 2025-26. Any remaining balances not expended at the end of the fiscal year will be <br /> City Council 18 — 4 3/3/2026 <br />