Laserfiche WebLink
FY2025-26 CIP <br />Project Status Update <br />Construction <br />Estimated <br />Project Type <br />Project Name <br />Project Balance <br />Status <br />Contract Award <br />Completion or <br />(As of 01/12/26) <br />Date <br />Construction <br />Duration <br />Streets <br />First St Rehab Grand To Tustin <br />2,779,186 <br />Expected to advertise February 2027 <br />Design Phase <br />3-6 months <br />Streets <br />First St Rehab: Grand To Tustin <br />822,004 <br />Expected to advertise February 2027 <br />Design Phase <br />3-6 months <br />Streets <br />First St Traffic Safety Corridor <br />- <br />Expected to advertise October 2026 <br />Design Phase <br />3-6 months <br />Streets <br />Grand Av Rehab: Edinger -McFadden <br />2,274,838 <br />Expected to award March 2026 <br />Design Complete <br />7/31/2026 <br />Streets <br />Grand Ave Rehab First St -Santa Ana <br />2,972,300 <br />Expected to advertise June 2026 <br />Design Phase <br />3-6 months <br />Streets <br />Industrial St Repair FY23/24 <br />2,197,906 <br />Expected to advertise February 2026 <br />Design Complete <br />3-6 months <br />Streets <br />Industrial St Repair Pro 24/25 <br />2,479,361 <br />Expected to advertise February 2026 <br />Design Complete <br />3-6 months <br />Streets <br />Industrial St Repair Program <br />2,857,801 <br />Expected to advertise February 2026 <br />Design Complete <br />3-6 months <br />Streets <br />Local St Preventative Maintenance <br />277,687 <br />Expected to advertise April 2026 <br />Design Phase <br />6-9 months <br />Streets <br />Macarthur Rehab Harbor -Fairview <br />- <br />Expected to advertise August 2027 <br />Design Phase <br />3-6 months <br />Streets <br />MacArthur Rehab: Fairview-Raitt <br />818,135 <br />Expected to advertise August 2026 <br />Design Phase <br />12/31/2027 <br />Streets <br />Main Rehab Edgewood-Memory Ln <br />269,586 <br />Design phase funding only; Design 20% <br />Design Phase <br />3-6 months <br />complete. <br />Streets <br />McFadden Rehab Fairview - Raitt <br />847,005 <br />In construction <br />9/17/2024 <br />6/31/26 <br />Streets <br />McFadden Rehab Harbor -Fairview <br />756,716 <br />In construction <br />9/17/2024 <br />6/31/26 <br />Streets <br />McFadden Rehab Raitt To Grand <br />835,201 <br />In construction <br />9/17/2024 <br />6/31/26 <br />Streets <br />Memory Ln & Mainplace Dr <br />690,000 <br />Expected to advertise August 2027 <br />Design Phase <br />3-6 months <br />Streets <br />Raitt St Rehab Cc -Washington <br />2,609,580 <br />Expected to advertise February 2026 <br />Design Phase <br />6-9 months <br />Streets <br />Raitt St Rehab: McFadden -First <br />4,388,228 <br />Expected to advertise February 2026 <br />Design Phase <br />6-9 months <br />Streets <br />Santa Ana Grade Separation <br />75,000 <br />Expected to advertise March 2028 <br />Design Phase <br />18-24 months <br />Streets <br />Standard Avenue Widening <br />969,043 <br />Design phase funding only; Design 5% <br />Design Phase <br />9-12 months <br />complete. <br />Streets Warner Ave Improvements Phase 2-Oak-Grand <br />Streets <br />Warner Ave Widening: Main -Oak Phase I <br />Traffic Safety <br />Bristol Corridor Regional Traffic <br />Traffic Safety <br />Bristol St Bike Lanes: First to Civic Center <br />Traffic Safety <br />Flower & Macarthur Left Turn Signal <br />Traffic Safety <br />Grand Ave Traffic Signal Synchronization <br />Traffic Safety <br />High Visibility Marked Crosswalk Improvements <br />Traffic Safety <br />McFadden Ave Transit Signal <br />Traffic Safety <br />McFadden Protected Bike Lane Harbor -Grand <br />Traffic Safety <br />Raitt St Protected & Buff Bikeway <br />Traffic Safety <br />Seger/Raitt Traffic Signal <br />Traffic Safety <br />Segerstrom/Spruce Traffic Signal <br />Traffic Safety <br />Signal Installation Segerstrom & Rosewood <br />Traffic Safety <br />Standard Ave Prot Bk Ln: 3-War <br />Traffic Safety <br />Traffic Calming FY 23/24 <br />Traffic Safety <br />Traffic Calming: Memory & Flower <br />Traffic Safety <br />Warner Protected Bike Lane: Oak -Grand <br />Utility <br />Bristol Water Main Improvements -Phase 4 <br />Utility <br />10Th & Flower Stormwater Capture <br />Utility <br />Bristol Phase 3A Water <br />Utility <br />Bristol -Tolliver St Urban Greening <br />Utility <br />Citywide Facilities PFAS Improvements <br />20,690,659 <br />Expected to advertise February 2026 <br />Design Complete <br />12-18 months <br />4,875,238 <br />In construction <br />3/16/2021 <br />6/30/2026 <br />3,574,926 <br />Expected to advertise February 2026 <br />Design Complete <br />3-6 months <br />1,265,718 <br />Expected to advertise November 2026 <br />Design Phase <br />3-6 months <br />250,000 <br />Expected to advertise February 2026 <br />Design Complete <br />1-3 months <br />5,710,514 <br />Construction to begin June 2026 <br />9/16/2025 <br />6-9 months <br />- <br />Expected to advertise May 2026 <br />Design Phase <br />6-9 months <br />2,179,222 <br />In construction <br />7/1/2025 <br />2/6/2026 <br />6,507,633 <br />In construction <br />9/17/2024 <br />6/26/2026 <br />85,403 <br />Expected to advertise February 2026 <br />Design Phase <br />6-9 months <br />1,279,311 <br />In construction <br />11/4/2025 <br />6/9/2026 <br />613,464 <br />In construction <br />10/1/2024 <br />2/20/2026 <br />1,114,409 <br />In construction <br />1/21/2025 <br />4/17/2026 <br />539,901 <br />In construction <br />9/17/2024 <br />6/26/2026 <br />288,181 <br />In construction <br />9/23/2024 <br />2/28/2027 <br />896,438 <br />Expected to advertise March 2026 <br />Design Phase <br />6-9 months <br />1,129,991 <br />Expected to advertise February 2026 <br />Design Complete <br />12-18 months <br />3,146,154 <br />In construction <br />2/24/2025 <br />12/31/2026 <br />600,000 <br />In award phase. Anticipated award in March <br />Design Complete <br />6-9 months <br />2026. <br />1,300,143 <br />In construction <br />2/24/2025 <br />6/30/2026 <br />1,290,861 <br />In construction <br />3/18/2025 <br />4/1/2026 <br />6,000,000 <br />In construction <br />11/4/2025 <br />12/30/2033 <br />