EXHIBIT 4 <br /> SCHEDULE E <br /> CHANGES FROM APPLICATION <br /> Scope:No changes. <br /> Schedule: Planned Construction Substantial Completion and Open to Traffic Date was extended <br /> from January 1, 2030,to December 31, 2031, to provide additional schedule to complete right of <br /> way acquisitions and construction.The amended completion date factors in the contract timeline, <br /> and all necessary coordination and reviews,which were not the basis for the completion date <br /> calculation at the time of the original application. <br /> The table below compares the Project milestone dates. <br /> Milestone Application Schedule C <br /> Planned Right of Way Certification Date: 09/30/2026 12/31/2027 <br /> Planned Construction Substantial Completion and <br /> Open to Traffic Date: 1/l/2030 12/31/2031 <br /> Budget:No changes. <br /> Other:NIA. <br /> 7of1 <br />