<br /> <br /> <br /> CI OF SANTA ANA <br /> <br /> PUBLIC WORKS AGENCY <br /> CONTRACT CHANGE ORDER <br /> V-1 <br /> <br /> Project Number PROJECT NO. 06-1500; BRISTOL STREET WIDENING Change Order Number 3 <br /> <br /> FROM MCFADDEN AVE. TO PINE ST. <br /> To ALL American Asphalt Contractor <br /> <br /> You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and <br /> specifications on this contract. <br /> NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. <br /> <br /> Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br /> Change requested by PUBLIC WORKS AGENCY <br /> <br /> f <br /> The compensation both time and cost set forth in this final change order comprises the total <br /> Y compensation due the Contractor, all Subcontractors, and all Suppliers for all work perf ormed per <br /> 4 <br /> this change order, including impact on unchanged work. By signing this final change order, the <br /> x Contractor acknowledges and agrees on behalf of himself, all Subcontractors, and all Suppliers, <br /> that the stipulated compensation includes payment for all work contained in this final change order, <br /> plus all payment for interruption of schedules, extended field overhead, home office overhead, <br /> profit, delay, and all impact, ripple effect or cumulative impact on all other work under this Contract. <br /> The signing of this final change order constitutes full mutual accord and satisfaction for all changes <br /> and work performed on this project, and that the time and cost paid per this final change order <br /> constitutes the total equitable adjustments owed the Contractor, all Subcontractors, and all <br /> Suppliers for all work performed on this project. The Contractor on behalf of himself, all <br /> F Subcontractors, and all Suppliers agrees to waive all rights, without exception or reservation of any <br /> whatsoever to file any further claim related to this project. <br /> TOTAL COST THIS CHANGE ORDER: DECREASE $ INCREASE $ 56,214.80 <br /> 3 <br /> <br /> s 4 By reason of this order the CONTRACT TIME completion will be adjusted as follows: Minus Eight-Seven Days. <br /> d <br /> k We the undersigned contractor have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all <br /> equipment, furnish all materials, except as may otherwise be noted above, and perform all service necessary for the work above specified, and will accept as full <br /> payme therefor the prices shown above. <br /> j <br /> f A epte ,Date 10 -4 - i0 Contractor ALL American Asphalt <br /> Title 3ANES M . M~- ,EF_~ P~p~ t•.f~~~ <br /> 4Approv I recommende Date <br /> PUBLIC KS AGENCY' EXECUTIVE DIRECTOR <br /> Approved bye <br /> F ` ? Date <br /> CITY MANAGER <br /> <br /> Page 2 of 2 <br />