HomeMy WebLinkAbout23A - FLOWER ST IMPROVEMENTSREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
MAY 15, 2018
TITLE:
AWARD CONTRACT TO ALL AMERICAN
ASPHALT FOR SLURRY SEAL
IMPROVEMENTS ON FLOWER STREET
FROM SUNFLOWER AVENUE TO
MACARTHUR BOULEVARD, AND ON
MACARTHUR BOULEVARD FROM RAITT
STREET TO BRISTOL STREET
(PROJECT NOS. 18-6916 & 18-6917)
{STRATEGIC PLAN NOS. 6, 1B, 1C & 1G}
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 1s' Reading
❑ Ordinance on 2n° Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Award a contract to All American Asphalt, the lowest responsible bidder, in accordance with
the base bid in the amount of $569,366, for the term beginning upon execution of the
contract and ending upon project completion, for construction of the Slurry Seal
Improvements on Flower Street from Sunflower Avenue to MacArthur Boulevard, and on
MacArthur Boulevard from Raitt Street to Bristol Street, and authorize the City Manager and
the Clerk of the Council to execute the contract subject to nonsubstantive changes approved
by the City Manager and the City Attorney.
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of $829,082
which includes the contract bid amount, administration, inspection and testing, and an
authorized contingency of $174,311.
DISCUSSION
The City's Pavement Management Program has identified the arterial street segments of Flower
Street from Sunflower Avenue to MacArthur Boulevard, and MacArthur Boulevard from Raitt
Street to Bristol Street, as high priority for slurry seal improvements (Exhibit 1). The
recommended work consists of preparing the roadway by performing minor preparatory
pavement repairs, localized replacement of asphalt concrete pavement, followed by crack sealing
treatment, and then slurry seal resurfacing, striping, and signage. The. improvements also
include replacement of damaged concrete curbs, gutters, sidewalks, and curb ramps. Once
completed, these improvements will enhance the ride quality and visual appearance of the street,
and comply with Americans with Disability Act standards.
23A-1
Award Contract to All American Asphalt for Slurry Seal Improvements
Flower Street and MacArthur Boulevard
May 15, 2018
Page 2
A Notice Inviting Bids was advertised on March 23 and 28, 2018, and bids were opened on April
16, 2018. The following is a summary of the bid invitations made and the bids received:
Contractor Participation Data
Santa Ana contractors receiving notices
12
Contractors requesting bidding documents
3
Bids received
4
Bids received from Santa Ana contractors
1
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
All American Asphalt
Corona
$569,366
2
Hardy & Harper
Santa Ana
$613,000
3
RJ Noble
Orange
$654,395
4
j Excel Paving Co
Long Beach
$654,994
A total of four bids were received and all bids were deemed responsive. All American Asphalt
submitted the lowest responsive bid in the amount of $569,366 (Exhibit 2). Based on the bid
analysis and a contractor's reference check, staff recommends awarding the construction
contract to All American Asphalt in the amount of $569,366 (Exhibit 3).
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 — Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe, and aesthetically pleasing for all users); Strategy C (invest
resources and technology to extend the service life of existing infrastructure to protect the City's
investment and support a high quality of life standard); and Strategy G (develop and implement
the City's Capital Improvement Program in coordination with the Community Investment Plan).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are
exempt from further review. Categorical Exemption Environmental Review No. ER -2018-41 and
ER -2018-42 were filed for the project 18-6916 and 18-6917.
23A-2
Award Contract to All American Asphalt for Slurry Seal Improvements
Flower Street and MacArthur Boulevard
May 15, 2018
Page 3
FISCAL IMPACT
As indicated in the Cost Analysis (Exhibit 4), the estimated total construction delivery cost of the
project is $829,082, which includes construction contract, administration, inspection, testing,
surveying, and an authorized contingency of $174,311. Funding is available in the Select Street
Construction Road Maintenance and Rehabilitation Account fund (Account No. 05917665-66220)
for projects 18-6916 and 18-6917 in the amounts of $218,082 and $611,000, respectively, for
expenditures in Fiscal Year 2017-18.
Acting Executive Director
Public Works Agency
EWG/TC/MO
Exhibits: 1. Location Map
2. Bid
3. Construction Contract
4. Cost Analysis
APPROVED AS TO FUNDS & ACCOUNTS:
Francisco Gutierrez(o� q�
Executive Director
Finance & Management Services Agency
23A-3
23A-4
Map Legend
1111111111 Flower Street Slurry from Sunflower Ave. to MacArthur Blvd.
1111111111 MacArthur Boulevard Slurry from Raitt St. to Bristol St.
�
SANTA ANA City Council Project Nos. 18-6916-&18-6917:
PWA Agenda Date: Flower Street and MacArthur Boulevard
PUBOCWUIIKSAGENCY May 15, 2018 Slurry Projects
23A-6
Exhibit 2
CITY OF SANTA ANA ADDENDUM No. One
PROPOSAL
PROJECT NO.: 18.6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAM ST. TO BRISTOL ST.
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation
230
CY
$120 -0 0
$ 2700-00
2
Cold Mill (2")
63,200
SF
$ ,201
$)9'32-U6
3
AC Pavement (Asphalt Concrete)
340
TN
$ V. U0
$ 2°1590.0 0
4
Asphalt Rubber Hot Mix (ARHM)
1,420
TN
$ 09.00
$ 141(090.00
5
Rubberized Emulsion Aggregate Slurry
(REAS)Type11��31p00
270
TN
$
000-00
$
00
6
Crack Sealing (Flower St.)
1
LS
$ $200.00
$ &,00.00
7
Crack Scaling (MacArthur 131vd.)
1
LS
$5106.00
$ S100.00
8
PCC Sidewalk
470
SF
$ 1sso
$ U;45;UO
9
PCC Curb 8a Gutter (Type A-2-8)
75
LF
$ 1Z1, or)
$ 01 Dj 5, 00
10
PCC Curb Ramps
1,200
SF
811,0U
$2'L$00' -OU
11
PCC Driveway (T=8")
400
SF
119,00
$ -1 uoo , 00
12
TtuncatedDome
3
EA
$50106.00
$11106.00
P-1 of P-17
23A-7
CITY OF SANTA ANA ADDENDUM No. One
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST, SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD,
PROJECT NO,: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
ItemPFInishGrade
ption
Qty
Unit
YTnitPrice
Amount
13ave
1
EA
$ 1100.00
$ 1100,06
14Metal
Pull Box Frame and Cover to
2
EA
$ (050 • UU
$ 13Uw DU
15Manhole
Frame &Cwar to -Finish
Grade
10
EA
$ arj�,UO
$�51U•UU
16
FnmishandInstallWaterValveFmmeand
Cover to Finish Grade
B
BA
$QQO.UU
$ (p�UO•UU
17
Furnish and Install New #6 Pull Box
4
EA
$ ( qo • U 0
$ Z� IRU _I00
18
Protection of Surface Utility Frames & Covers
(FlowerSt,)
1
IS
$Uj50•UU
$g50.UU
19
of Surface Utility Frames &Covers
Prote(MacArthur
(MaoArthur Blvvd.)
1
LS
$ q 0.00
$ q 50 0U 0
20
Temporary ConsnuctionSign
3
EA
$ IlUU.00
$ �30U • 00
21
Project advertisement sign
4
EA
$ �05U.00
T-42:0-0. UO
22
Fumish and Install Traffic Loops Type D fi
28
EA
23
Fumish and Install TrafScLoops Typo Et
67
EA
$ZUA•Dt7
$13y3ia,00
24
Signing and Striping (Flowerst,)
1
LS
$ g2oo.UU
$GJ 2,0,,0,
25
Signing and Striping(MacArthurBlvd,)
1
LS
$1j0oo.Od
$ 11U00.00
26
Labor Agreement Oversight
1
LS
$ 15,000
$ 15,000
P-2 of P-17
23A-8
CITY OF SANTA ANA ADDENDUM No. One
PROPOSAL
PROJECT NO.: I8-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
TOTAL BASE BID $ 5(o9, '%p (p. 0 0
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
f This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within forty-five (45) working days after the commencement date stated in the
Notice to Proceed. All work must be completed by August 31, 2018
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $2,500 per calendar day.
Nae of Firm AII American Asphalt
Signature of BIDDER
Title Edward J. Carlson Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasiicer,and Manager; thereof.)
All American Asphalt -Corporation
Mark Luer- President
Edward J. Carlson- Vice President
Michael Farkas- Secretary
P-3 of P-17
23A-9
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
BIDDER'S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the
Council with her signature and official seal noting hereon the action of approval of the Council,
signed by the Public Works Agency Executive Director or his/her duly authorized agent, and
signed by the City Attorney, denoting his approval of the form of this document, and its
execution, and when it or an exact copy of it has been either delivered to BIDDER or deposited
with the United States Postal Service properly addressed to the BIDDER with the correct postage
affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of
damages actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or
BIDDER'S bond substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation
under the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Firm
Signature of BIl
Title
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
All American Asphalt- Corporation
Mark Luer- President
Edward J. Carlson- Vice President
Michael Farkas- Secretary
P-4 of P-17
23A-10
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
CONTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she
and all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: All American Asphalt
Business Address: 400 E. Sixth Street Corona, CA 92879
Business E -Mail Address: publicworks(u)allamericanasphalt.com
Telephone: 951-736-7600
State Contractor's License No. and Class: 267073 A. C-12
License Expiration Date: 1-31-2022
State Dept. of Industrial Relations (DIR)
Registration No.: 1000001051
State Dept. of Industrial Relations (DIR)
Registration Expiration Date: 6-30-2018
LAIJ
Signed: F "44-71,41 .
Title: Edward J. Carlson, Vice President
P-5 of P-17
23A-11
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well
as California Code of Regulations, Title 8, Section 16,000, et seq., ("Prevailing Wage Laws"),
which require the payment of prevailing wage rates and the performance of other requirements
on "public works" and "maintenance" projects. Since the services are being performed as part of
an applicable "public works" or "maintenance" project, as defined by the Prevailing Wage Laws,
and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such
Prevailing Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at
the commencement of this Agreement. Contractor shall make copies of the prevailing rates of
per diem wages for each craft, classification or type of worker needed to execute the services
available to interested parties upon request, and shall post copies at the Contractor's principal
place of business and at the project site.
Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees
and agents free and harmless from any claim or liability arising out of any failure or alleged
failure to comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct.
Name of Firm All American Asphalt
Signature of BIDDER
Title Edward,
(if an individual, so
All American Asphalt- Corporation
Mark Luer- President
Edward J. Carlson- Vice President
Michael Farkas- Secretary
P-6 of P-17
23A-12
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
OWNERSHIP AFFIDAVIT
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS:
CITY OF SANTA ANA )
�du,o�fd) Gal Ibon being duly swom, deposes and says:
❑ INDIVIDUAL That he/she is the party making the foregoing proposal:
❑ PARTNERSHIP That he/she Is a member of the co -partnership firm designated as:
and %%lip has been and is duly vested with the authority to make and execute instruments
for the co -partnership by:
who constitute the other members ofthe co -partnership.
CORPORATION That Ire is of.
—_
All American Asphalt the Vice President
a corporation which is making the foregoing proposal:
❑ JOINT VENTURE That he is of:
one of the parties making the foregoing proposal as a joint venture, and the he/she has
been and is duly vested with the authority to execute instruments for an on behalf of the
parties making said bid who are:
that such a bid is genuine and not collusive or sham, and has not in any manner sought by
collusion to secure any advantage against the City of Santa Ana or any person interested in the
proposed contract, for himself or any other person.
Signature ofrBidder fdward J. Carlson, Vice President
Subscribed and sworn to before me this day of 20
*Please see attached California Jurat*
Signature of officer Administering Oath (Notary Public)
P-7 of P-17
23A-13
CALIFORNIA JURAT
GOV CODE1
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California
County of Riverside
COURTNEY CHAPAS
. ..... Notary Public - California
¢ :-,g , Riverside County
z Commission ✓f 2172984
M Comm. Ex iras Nov 20, 2020
Subscribed and sworn to (or affirmed) before
me on this 13th day of April . 2018 .
Date Month
By (1) Edward J. Carlson
Name of Signer
Proved to me on the basis of satisfactory evidence
be the person who appeared before me (.) (,)
(and
(2) Name of Signer
Proved to me on the basis of satisfactory evidence
be the person who appeared before me.)
Signature -b CNV
Place Notary Seal Abov Signatueof NotalPublic
OPTIONAL
Though the information below is not required by law, it may prove
valuable to person relying on the document and could prevent
fraudulent removal and reattachment of this form to another document.
Further Description of Any Attached Document
Title or Type of Document: Ownership Affidavit
Document Date: 4-13-2018 Number of Pages: 1
Signer(s) Other Than Named Above: None
23A-14
CITY OF SANTA ANA Bond 09597423
Bid Dalte:o:04/1612019
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
fflffl:• /
KNOW ALL PRESENT that,
All American Asphalt , as BIDDER, and
Fidelity and Deposit Company of Maryland , as SURETY
are held and firmly bound unto the CITY OF SANTA ANA, as AGENCY, in the penal sum of _
Ten Percent of Total Amount Bid--- Dollars ($10% of Bid ), which is ten percent (109/6)
of the total amount bid by BIDDER to AGENCY for the above -stated project, for the payment of
which sum, BIDDER and SURETY agree to be bound, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas BIDDER is about to
submit a bid to AGENCY for the above -stated project, if said bid is rejected, or if said bid is
accepted and a contract is awarded and entered into by BIDDER in the manner and time
specified, then this obligation shall be null and void, otherwise it shall remain in full force and
effect in favor of AGENCY.
IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seal this
4th day of April —12018.
BIDDER*
197tI:P.I:fL M1TISfPA11VIC112IL UIr]
SURETY*
Fidelity and Deposit Companv of Maryland - 777 S. Figueroa Street. Suite 3900. Los Anoeles. CA 90017
David Wei (213) 270-0600
Rebecca Haas -Bates, Attorney -in -Fact
Subscribed and sworn to before me "Please See Attached•• this day of
,20—.
Signature:
Notary Public in and for the County of
, State of
Provide BIDDER/ SURETY name, address, and telephone number and the name, title,
address, and telephone number of authorized representative.
P-8 of P-17
23A-15
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached. and not the truthfulness. accuracv. or validity of that document.
State of California
County of Riverside
On April 13, 2018 before me, Courtney Chavas, Notary Public
Data Here Insed name and Idle of i;.—Officer
personally appeared Edward J. Carlson
Names) of Signers)
--��
COURTNEY CHAPAS
rVNotary
Public - California
z4
Riverside County Zz
Commission # 2172884
My Comm. Expires Nov 20, 2020
who proved to me on the basis of satisfactory evidence to be the
person(s) whose name(s) Is/are subscribed to the within instrument
and acknowledged to me that hel&heAhey executed the same in
his1hef4heir authorized capacity(ies), and that by his/he4their
signature(a) on the instrument the person(&), or the entity upon behalf
of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of
California that the forgoing paragraph is true and correct.
WITNESS my hand and officipl seal
Signature
Place Notary Seal Above Signa Dof Notan ublic
OPTIONAL
Though the information below is not required by law, it may prove valuable to person relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document Bid Bond
Document Date: Anri14, 2018 Number of Pages: 1
Signer(s) Other Than Named Above: None
Capacity(les) Claimed by Signer(&)
Signer's Name: Edward J. Carlson
o Individual
X Corporate Officer—Title(s): Vice President
o Partner n o Limited o General
o Attorney in Fact
o Trustee
Top of avanb beta
❑ Other:
if CorporateOffLce
o Partner 17 ❑ Lim
o Attorney in Fact
❑ Trustee
o Other:
23A-16
Title(s): _
o General
Top of Numb bare
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT CIVIL CODE § IMS
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of Orange )
On 04/04/2018 before me, A. MacFarlane, Notary Public
Date Here Insert Name and Title of the Officer
personally appeared Rcbccca Haas -Bates
NameKof SlgnerN
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(* is/bm
subscribed to the within instrument and acknowledged to me that he/she/they executed the same in
hislher/their authorized capacity I�, and that by his(her/the& signaturej4 on the instrument the person(s),
or the entity upon behalf of which the person(s) acted, executed the instrument.
_ A. MACFIA NE
Notary Public—California z
jOrange County
Y Commission x 2188592
My Comm. Expires Mar 27, 2021
Place Notary Seal Above
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official seal.
Signature
Signature of Notary Public
OPTIONAL
Though this section is optional, completing this Information can deter alteration of the document or
fraudulent reattachment of this form to an unintended document.
Description of Attached Document
Title or Type of Document: Bid Bond
Number of Pages: One 1 Signer(s)
Document Date: 04/04/2018
Other Than Named Above: All American Asphalt
Capacity(ies) Claimed by Signer(s)
Signer's Name: Rebecca Haas -Bates
O Corporate Officer — Title(s):
❑ Partner — ❑ Limited ❑ General
❑ Individual RAttorney in Fact
❑ Trustee ❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
Fidelity and Deposit Company of Maryland
Signer's Name:
❑ Corporate Officer — Title(s):
❑ Partner — ❑ Limited ❑ General
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
❑ Other.
Signer Is Representing:
MAIM01mir • •a `•` • •, L• ia1 i•r •r
23A-17
EXTRACT FROM BY-LAWS OF THE COMPANIES
"Article V, Section 8, Attomevs-in-Fact. The Chief Executive Officer, the President, or any Executive Vice President or Vice President
may, by written instrument under the attested corporate seal, appoint attomeys-in-fact with authority to execute bonds, policies,
recognizances, stipulations, undertakings, or other like instruments on behalf of the Company, and may authorize any officer or any such
attomey-in-fact to affix the corporate seal thereto; and may with or without cause modify of revoke any such appointment or authority at any
time."
CERTIFICATE
1, the undersigned, Vice President of the ZURICH AMERICAN INSURANCE COMPANY, the COLONIAL AMERICAN
CASUALTY AND SURETY COMPANY, and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify that the
foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that Article V, Section 8, of
the By -Laws of the Companies is still in force.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the ZURICH AMERICAN INSURANCE COMPANY at a meeting duly called and held on the 15th day of December 1998.
RESOLVED: "That the signature of the President or a Vice President and the attesting signature of a Secretary or an Assistant Secretary
and the Seal of the Company may be affixed by facsimile on any Power of Attorney... Any such Power or any certificate thereof bearing such
facsimile signature and seal shall be valid and binding on the Company."
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at a meeting duly called and held on the 5th day of
May, 1994, and the following resolution of the Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a
meeting duly called and held on the 10th day of May, 1990.
RESOLVED: "That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically reproduced signature
of any Vice -President, Secretary, or Assistant Secretary of the Company, whether made heretofore or hereafter, wherever appearing upon a
certified copy of any power of attorney issued by the Company, shall be valid and binding upon the Company with the same force and effect
as though manually affixed.
N TESTIMONY WHE OF, I have hereunto subscribed my name and affixed the corporate seals of the said Companies,
this i day of ik�Jt/'1 r .20 L.
a��' • Ulm
a e
v y t}a� I a
Michael Bond, Vice President
TO REPORT A CLAIM WITH REGARD TO A SURETY BOND, PLEASE SUBMIT ALL REQUIRED
INFORMATION TO:
Zurich American Insurance Co.
Attn: Surety Claims
1299 Zurich Way
Schaumburg, IL 60196-1056
23A-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
LIST OF SUB -CONTRACTORS
Section 4100 et. seq. of the Public Contract Code requires listing of all subcontractors with the bid for all
subcontract work exceeding the following amount:
o Streets, highways including bridge projects: %:% of the bid or $10,000, whichever is greater
o Buildings, parks, or other projects: Y2% of the bid
Section 1725.5 of the Public Contract Code requires all Subcontractors be registered with the State
Department of Industrial Relations (DIR).
BIDDER proposes to subcontract certain portions of the work to the firms listed below:
Name OW
0
License #/Exp.
3
DIR Reg. #/Exp.
16000 USS 41
Location
616AQ P
Phone
—4;S
Type Of Work
31
Amount $
2-Y. iS , 0 0
Name 5(hli'loY1 �Pv1Y�c.
License #/Exp. _kj 1 � S I $
DIR Reg
License
Location
Phone
Type Of
Amount
Name MD
-CRA-CRA��
=Z*610, fj'11
License #/Exp.
610 U l0 ` u
DIR Reg. #/Exp.
/ dduo o r0µ3 9
License #
8 (p (0 Rul
Location
! rVyif- Arid
Phone
31
Type Of Work
a7A - ID(1.1
Amount$
1314W.od
Signature of Bidder Edward J. Carlson, Vice President
Name
License #/Exp.
DIR Reg.#/Exp.
Location
Phone
Type Of Work
Amount $
Name
License #/Exp.
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
Name
License #/Exp.
DIR Reg.#/Exp.
License # _
Location _
Phone
Type Of Work
Amount $
P-9 of P-17
23A-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
1. City of Rancho Cucamonga 10500 Civic Center Drive Rancho Cucamonga, CA 91730
Name and Address of Owner.
Romeo David (909) 477-2740
Name and Telephone Number of person familiar with project,
$1,130,470.00 Pavement Reabilitation 07/2017
Contract Amount Type of Work Date Completed
2. City of Temecula 41000 Main Street Temecula, CA 92590
Name and Address of owner.
William Becerra (951) 694-6444
Name and Telephone Number of person familiar with project.
$2,577,770.00 Pavement Rehabilitation 11/2017
Contract Amount Type of Work Date Completed
3. Town of Apple Valley -14955 Dale Evans Parkway Apple Valley, CA 92307
Name and Address of owner.
Rich Berger(760)240-7000
Name and Telephone Nur
$849,182.00
Contract Amount
Road Rehabilitation
Type of Work
11/2017
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Fidelity and Deposit Company of Maryland (Broker Surety)
777 S, Fiqueroa Street #3900 Los Anoeles. CA 90017 (213) 270-0600
Owen M. Brown Insurance Millennium Corporate Solutions (Agent)
5530 Trabuco Road Irvine, CA 92620 (949) 857- 4500
Edgewood Partners Insurance Center (insurance)
3633 Inland Empire Blvd. Suite 640 Ontario, CA 91764
P-10 of P-17
23A-20
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
1, City of Victorville 14343 Civic Dr. Victorville, CA 92392
Name and Address of Owner.
Carlos Seanez (760) 955-5162
Name and Telephone Numb
$251,008.00 Paving Prolect 06/2017
Contract Amount Type of Work Date Completed
2. City of Santee 10601 Magnolia Avenue Building 4 Santee, CA 92071
Name and Address of owner.
Toby M. Espinola (619) 25814100
Name and Telephone Number of person familiar with project.
$285,061.90 Slurry Seal 10/2017
Contract Amount Type of Work Date Completed
3. City of Yucaipa- 34272 Yucaipa Blvd. Yucaipa, CA 92399
Name and Address of owner.
John Larose (909) 797-2489
Name and Telephone Number of person familiar with project.
$252,379.06 Micro -Surfacing 08/2017
Contract Amount Type of Work
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Fidelity and Deposit Company of Maryland (Broker Surety)
777 S. Figueroa Street #3900 Los Angeles, CA 90017 (213) 270-0600
Owen M. Brown Insurance Millennium Corporate Solutions (Agent)
5530 Trabuco Road Irvine, CA 92620 (949) 857- 4500
Edgewood Partners Insurance Center (Insurance)
3633 Inland Empire Blvd. Suite 640 Ontario, CA 91764
P-11 of P-17
23A-21
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
NON -COLLUSION AFFIDAVIT
(Title 23 United States Code Section 112 and Public Contract Code Section 7106)
In conformance with Title 23 United States Code Section 112 and Public Contract Code 7106 the
BIDDER declares that the bid is not made in the interest of, or on behalf of, any undisclosed
person, partnership, company, association, organization, or corporation; that the bid is genuine
and not collusive or sham; that the BIDDER has not directly or indirectly induced or solicited
any other BIDDER to put in a false or sham bid, and has not directly or indirectly colluded,
conspired, connived, or agreed with any BIDDER or anyone else to put in a sham bid, or that
anyone shall refrain from bidding; that the BIDDER has not in any manner, directly or indirectly,
sought by agreement, communication, or conference with anyone to fix the bid price of the
BIDDER or any other BIDDER, or to fix any overhead, profit, or cost element of the bid price,
or of that of any other BIDDER, or to secure any advantage against the public body awarding the
contract of anyone interested in the proposed contract; that all statements contained in the bid are
true; and, further, that the BIDDER has not, directly or indirectly, submitted his or her bid price
or any breakdown thereof, or the contents thereof, or divulged information or data relative
thereto, or paid, and will not pay, any fee to any corporation, partnership, company association,
organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham
bid.
Note: The above Non -collusion Affidavit is part of the Proposal. BIDDERS are
cautioned that making a false certification may subject the certifier to criminal
prosecution.
Signed
Edward -J. Carlson,
State of California
County Of Riverside
President
Subscribed and sworn to (or affirmed) before rile on this _ day of , 20, by
proved to me on the basis of satisfactory evidence to be the
person(s) who appeared before me "Please See Attached"
Notary Public Signature Notary Public Seal
P-12 of P-17
23A-22
CALIFORNIA GOV CODE8202
g
T._-cY•$3 r �-'t_ -k - -3Faa 6'm`�3`' 9S��r'��'a. elG
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California
County of Riverside
Subscribed and sworn to (or affirmed) before
me on this 13th day of April 2018 .
Date Month
By (1) Edward J. Carlson
Name of Signer
Proved to me on the basis of satisfactory evidence
be the person who appeared before me (.) (,)
(2)
(and
Name of
Proved to me on the basis of satisfactory evidence
be the person who appeared before me.)
Signature W �U
(tenA _ np 1�pq.t'Jn�
Place Notary Seal Above SignatdrA of Not4 Public
OPTIONAL
Though the information below is not required by law, it may prove
valuable to person relying on the document and could prevent
fraudulent removal and reattachment of this forth to another document.
Further Description of Any Attached Document
Title or Type of Document: Noncollusion Affidavit
Document Date: 4-13.2018 Number of Pages: 1
Signer(s) Other Than Named Above:
23A-23
COURTNEY CHAPAS
California
Notary Public -
z
a
Riverside County zCommission
4 2172984
M Comm. Expires Nov 20.2020
Subscribed and sworn to (or affirmed) before
me on this 13th day of April 2018 .
Date Month
By (1) Edward J. Carlson
Name of Signer
Proved to me on the basis of satisfactory evidence
be the person who appeared before me (.) (,)
(2)
(and
Name of
Proved to me on the basis of satisfactory evidence
be the person who appeared before me.)
Signature W �U
(tenA _ np 1�pq.t'Jn�
Place Notary Seal Above SignatdrA of Not4 Public
OPTIONAL
Though the information below is not required by law, it may prove
valuable to person relying on the document and could prevent
fraudulent removal and reattachment of this forth to another document.
Further Description of Any Attached Document
Title or Type of Document: Noncollusion Affidavit
Document Date: 4-13.2018 Number of Pages: 1
Signer(s) Other Than Named Above:
23A-23
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO 1VIACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on
behalf of the Contractor, state that all qualified applicants will receive consideration for
employment without regard to race, color, religion, sex, or national origin.
3. The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the Hiles, regulations, and relevant orders of the Secretary of Labor.
5. The Contractor shall furnish all information and reports required by Executive Order 11246
of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or
pursuant thereto, and will permit access to his/her books, records, and accounts by the
administering agency and the Secretary of Labor for purposes of investigation, to ascertain
compliance with such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible
for further Government contracts or federally assisted construction contracts in accordance
with procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoiced as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as
otherwise provided by law.
P-13 of P-17
23A-24
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
7. The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order
unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to
Section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be
binding upon each subcontract or purchase order as the administering agency may direct as
means of enforcing such provisions, including sanctions for noncompliance; provided,
however, that in the event the Contractor becomes involved in, or is threatened with,
litigation with a subcontractor or vendor as a result of such direction by the administering
agency, the Contractor may request that the United States enter into such litigation to protect
the interests of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation of the Ch` ��
Signed: �✓�
Title: Edward J. Carlson, Vice President
Firm: All American Asphalt
�f
Date: I�t d�1g
P-14 of P-17
23A-25
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
Apply to the joint apprenticeship committee administering the apprenticeship standards of
the craft or trade in the area of the site of the public work for a certificate approving the
contractor under the apprenticeship standards for the employment and training of apprentices
in the area or industry affected.
2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
3. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like amount to the California Apprenticeship Council.
Signed:
Title: Edward J. Carlson, Vice President
Firm: All American Asphalt
Date: 11113lMy
P-15 of P-17
23A-26
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
STATEMENT REGARDING "ANTI -KICKBACK" REQUIREMENTS
The undersigned is submitting this proposal for performing by contract the work required by
these bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repair of public work, to give up any part of the compensation to
which he/she is otherwise entitled.
Signed: f
Title: Edward J. Carlson, Vice President
Firm: All American Asphalt
Date: 1111W019
P-16 of P-17
23A-27
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6916
FLOWER ST. SLURRY: SUNFLOWER AVE. TO MACARTHUR BLVD.
PROJECT NO.: 18-6917
MACARTHUR BLVD. SLURRY: RAITT ST. TO BRISTOL ST.
PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented
from bidding on, or completing a federal, state, or local government project because of a
violation of law or a safety regulation?
Yes
No V
If the answer is yes, explain the circumstances in the following space.
N/A
P-17 of P-17
23A-28
MAYOR
Miguel A. Pulido
MAYOR PRO TEM
Michele Martinez
P. David Benavides
Vicente Sandento
Jose Solorio
Sal Tlnajero
Juan Villages
April 11, 2018
ADDENDUM No. One
CITY OF SANTA ANA
20 Civic Center Plaza, M-36 • P.O. Box 1988
Santa Ana, California 92702
v .santa-ana.orn
CITY MANAGER
Raul Godlnez II
CITY ATTORNEY
Sonia R. Carvalho
CLERK OF THE COUNCIL
Made D. Huizar
SUBJECT: PROJECT No. 18 6916: Flower Street Slurry from Sunflower Ave. to
MacArthur Blvd.
PROJECT No. 18 6917: MacArthur Blvd. Slurry from Raitt St. to Bristol St.
The following changes have been made to the Specifications of the subject projects.
Specifications
1. BID PROPOSAL, P-1, 2, & 3 of P-17: Replace Page P-1, 2, & 3 of P-17 of the Bid
Proposal with the attached.
2. APPENDIX G, Individual Project Quantities: Replace Individual Project Quantities with
the attached.
All other terms and conditions remain the same.
FOR THE CITY OF TA ANA
Edwin "William" Galvez
City Engineer
Public Works Agency
23A-29
SANTA ANA CITY COUNCIL
N6aeel A PUWO
AStld¢ 6brErrez I
Nvsde Samdento E Jose Sdad" I
R Dadd Dere
Mayor
Mayor Pto rem. warm I
WardI 1Yrertl9
W&d4
Wulld.O.ta ene.ora
MMadineilmaantaane.am f
t
VaarmIyWasanla•ana.ar" JSdndudsanaiana.ao _I C)Fkq
1
AdesPolSaMaana
23A-29
23A-30
CITY OF SANTA ANA Exhibit 3
CONSTRUCTION CONTRACT
PROJECT NOS. 18-6916 & 18-6917
FLOWER STREET AND MACARTHUR BOULEVARD SLURRY PROJECTS
This CONSTRUCTION CONTRACT is made and entered into this 15'b day of May, 2018 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and
existing under the Constitution and laws of the State of California (hereinafter "CITY"), and All
American Asphalt (hereinafter "CONTRACTOR').
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the
satisfaction of the City Engineer of the CITY, the Flower Street and MacArthur Boulevard Slurry
Project (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in
accordance with the Contract Documents prepared by the City's Public Works Agency and approved
by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Five Hundred Sixty -Nine Thousand Three
Hundred and Sixty -Six Dollars ($569,366.00), as set forth and identified in the BID PROPOSAL,
which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
mv.09/01/20n 23A-31 Page 1 of
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
hftp://www.santa-ana.orW-owa/documents/CWA.pd
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, famish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
//
23A-32 Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
MARIA D. HUIZAR
Clerk of the Council
APPROVED AS TO FORM:
SONIA R CARVALHO
City Attorney
By: Z
J6 -FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
EDWIN "WILLIAM" GALVEZ
Acting Executive Director
Public Works Agency
CITY OF SANTA ANA
RAUL GODINEZ II
City Manager
CONTRACTOR:
All American Asphalt
EDWARD J. CARLSON
Vice President
23A-33
Page 3 of 3
23A-34
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 16-6916 & 16-6917: Flower Street Slurry
from Sunflower Ave. to MacArthur Blvd. and MacArthur Boulevard Slurry from
Raitt St. to Bristol St. projects
EXHIBIT 4
23A-35
23A-36