HomeMy WebLinkAbout23A - SAFE ROUTES TO SCHOOLREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: JULY 17, 2018 TITLE: ACCEPT CONSTRUCTION COMPLETION FOR THE SAFE ROUTES TO SCHOOL ENHANCEMENTS AT HENINGER ELEMENTARY PROJECT (PROJECT NO. 16-6870) (STRATEGIC PLAN NO. 6, 1B & 1G) CITY RECOMMENDED ACTION CLERK OF COUNCIL USE ONLY: APPROVED ❑ As Recommended ❑ As Amended ❑ Ordinance on 1� Reading ❑ Ordinance on 2n° Reading ❑ Implementing Resolution ❑ Set Public Hearing For CONTINUED TO FILE NUMBER Accept the work as completed for the construction of the grant -funded Safe Routes to School Enhancements at Heninger Elementary project. DISCUSSION On December 6, 2017, the City Council awarded a construction contract to California Professional Engineering, Inc., in the amount of $471,341 and also authorized a construction contingency of $41,735. The project consists of installing traffic safety enhancements on city streets adjacent to Heninger Elementary School (Exhibit 1). The traffic safety improvements include a new traffic signal at the intersection of Flower Street and Walnut Street and bulb -outs at the intersection of Walnut Street and Birch Street. The table below is a summary of the authorized project funds and the final expenditures, including any additional work. There were no cost extras on this project. The final accounting shows that total construction expenditures remained within the approved City Council authorized limits. AUTHORIZED FUNDS Construction Contract Award _ $417,341 Contingency $ 41,735 TOTAL AUTHORIZED $459,076 CONSTRUCTION EXPENDITURES Construction Contract $398,9.6.5_ FINAL CONSTRUCTION COST $398,965 23A-1 Construction Completion of SR2S Enhancements - Heninger Elementary July 17, 2018 Page 2 Upon project closeout, unexpended funds automatically return to the unallocated fund balance. Since this project was funded by Measure M2, the unspent funds are available for the future Measure M2 eligible projects. STRATEGIC PLAN ALIGNMENT Approval of this item supports the City's efforts to meet Goal #6 - Community Facilities & Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City assets), Strategy B (equitably maintain existing streets and associated assets in a state of good repair so they are clean, safe and aesthetically pleasing for all users); and Strategy G (develop and implement the City's Capital Improvement Program in coordination with the Community Investment Plan [e.g., neighborhood streets, traffic improvements, etc.]). ENVIRONMENTAL IMPACT There are no environmental impacts associated with the recommended action. FISCAL IMPACT Fuad S. S Executive Public We no fiscal impacts related with the acceptance of the improvements. HE, NLS Agency FSS/EWG/AC/TC/MO Exhibit: 1. Location Map 23A-2 SANTA ANA Project No. 16-6870: PWA Exhibit 1 Safe Routes to School Enhancement for pGBIIL WOSNSAGENCY Heninger Elementary 23A-3 23A-4