HomeMy WebLinkAbout55C - RESO BICYCLE CORRIDOR GRANTREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: CLERK OF COUNCIL USE ONLY: DECEMBER 4, 2018 Warner Avenue to St. Andrew Place TITLE: APPROVED ADOPT A RESOLUTION AUTHORIZING ❑ As Recommended THE SUBMISSION OF APPLICATIONS EI As Amended Or ❑ Ordinance on 15' Reading FOR BICYCLE CORRIDOR ❑ Ordinance on 2n° Reading IMPROVEMENT PROGRAM GRANTS ❑ Implementing Resolution (STRATEGIC PLAN NO. 1, 313) ❑ Set Public Hearing For CONTINUED TO r FILE NUMBER CI 1ANAGER RECOMMENDED ACTION Adopt a resolution authorizing the Executive Director of the Public Works Agency to submit six applications for Bicycle Corridor Improvement Program grants. DISCUSSION The Orange County Transportation Authority (OCTA) issued a call for Bicycle Corridor Improvement Program (BCIP) applications for federal Fiscal Years 2019-20 through 2023-24. BCIP is a federally funded program which provides construction funds for projects that improve safety and convenience for bicycle commuters. In response to this call, staff prepared and submitted six applications for the following projects: • Protected Bike Lanes on Bristol Street: Warner Avenue to St. Andrew Place • Protected Bike Lanes on Bristol Street: St. Andrew Place to Edinger Avenue • Protected Bike Lanes on Bristol Street: First Street to Washington Avenue • Protected Bike Lanes on Bristol Street: Civic Center Drive to Washington Avenue • Protected Bike Lanes on Warner Avenue: Oak Street to Grand Avenue • Protected Bike Lanes on Memory Lane: The City Drive to Flower Street The grant program guidelines require submission of an authorizing resolution (Exhibit 1) to complete the applications. The project descriptions include estimated costs (Exhibit 2) and the general locations of the projects shown in the project location map (Exhibit 3). The proposed projects will provide needed bicycle infrastructure, including protected bike lanes. These projects will improve traffic safety, encourage active transportation, and increase mobility. Although the application deadline is November 15, 2018, the grant program guidelines allow the authorized resolution to be submitted after the application deadline. 55C-1 Resolution Authorizing Grant Applications Bicycle Corridor Improvement Program December 4, 2018 Page 2 STRATEGIC PLAN ALIGNMENT Approval of this item supports the City's efforts to meet Goal #1 — Community Safety, Objective #3 (promote fiscal accountability to ensure financial responsibility at all levels of the organization), Strategy B (promote ongoing efforts to obtain grant funding for activities that will assist in preventing, enforcing and reducing criminal activity and traffic collisions). ENVIRONMENTAL IMPACT Pursuant to Section 15061(b)(3) of the California Environmental Quality Act, this action is exempt from further review as there is no potential for any environmental impact. FISCAL IMPACT For any project that is approved for funding, the BCIP Program will cover 88 percent of the eligible costs and the City will need to provide the remaining 12 percent match. If all projects are funded, $1,360,130 will provide 12% of the total project cost as match to the requested $9,974,284 in OCTA BCIP funds for a total project cost estimated to be $11,334,414. The City's portion of Measure M Fairshare or other funding source will be budgeted in a future Capital Improvement Program in the Select Street Construction Fund (Account No. 05917660-66220). APPROVED AS TO FUNDS AND ACCOUNTS: p 1A�. Fuad S. eiss, PE, PLS K thryn Do ns, CPA #15 o d Executive Director Executive Director Public Wo ks Agency Finance and Management Services Agency Exhibits: 1. Resolution 2. Project Description & Cost 3. Location Map 55C-2 Jmf 11/14/18 RESOLUTION NO. 2018 -XXX A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SANTA ANA AUTHORIZING APPLICATION FOR FUNDS FOR THE BICYCLE CORRIDOR IMPROVEMENT PROGRAM FUNDED WITH CONGESTION MITIGATION AND AIR QUALITY IMPROVEMENT PROGRAM FUNDING UNDER THE FIXING AMERICA'S SURFACE TRANSPORTATION FEDERAL TRANSPORTATION ACT WHEREAS, the United States Congress enacted the Fixing America's Surface Transportation (FAST) Federal Transportation Act on December 4, 2015, which mal<es Congestion Mitigation and Air Quality Improvement Program (CMAQ) funds available to the Orange County Transportation Authority (OCTA); and WHEREAS, OCTA has established the procedures and criteria for reviewing proposals; and WHEREAS, the City of Santa Ana possesses authority to nominate bicycle projects funded using Congestion Mitigation and Air Quality Improvement Program funding and to finance, acquire, and construct the proposed projects; and WHEREAS, by formal action, the City Council of the City of Santa Ana authorizes the nomination of the projects listed below, including all understanding and assurances contained therein, and authorizes the person identified as the official representative of the City to act in connection with the nomination and to provide such additional information as may be required; and WHEREAS, the City of Santa Ana will maintain and operate the property acquired, developed, rehabilitated, or restored for the life of the resultant facility(ies) or activity; and WHEREAS, with the approval of the California Department of Transportation (Caltrans) and/or OCTA, the City of Santa Ana or its successors in interest in the property may transfer the responsibility to maintain and operate the property; and WHEREAS, the City of Santa Ana will give Caltrans andlor OCTA's representatives access to and the right to examine all records, books, papers or documents related to the bicycle projects; and WHEREAS, the City of Santa Ana will cause project work to commence within six months following notification from the State or OCTA that funds have been authorized to proceed by the Federal Highway Administration or Federal Transit Administration and that the projects will be carried to completion with reasonable diligence; and Exhibit 1 Resolution No. 2018 -XXX Page 1 of 3 55C-3 jmf 11/14/18 WHEREAS, the City of Santa Ana commits $1,360,130 of Measure M Fairshare or other funding source to be identified in future Capital Improvement Program and will provide 12% of the total project cost as match to the requested $9,974,284 in OCTA CMAQ funds for a total project cost estimated to be $11,334,414; and WHEREAS, the City of Santa Ana may elect to commit additional funds to the projects to fund an expanded scope which provides additional quantifiable benefits. The City is required to notify OCTA to grant approval prior to commencing on the additional scope; and WHEREAS, the City of Santa Ana will comply where applicable with provisions of the California Environmental Quality Act, the National Environmental Policy Act, the American with Disabilities Act, Federal Title VI, Buy America provision, and any other federal, state, and/or local laws, rules and/or regulations; and WHEREAS, the City Council of the City of Santa Ana authorizes the execution of any necessary cooperative agreements between the City and OCTA to facilitate the delivery of the projects; and WHEREAS, the City of Santa Ana will amend the agency Capital Improvement Program (CIP) to include the projects if selected for funding. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Santa Ana as follows: Section 1. The City of Santa Ana hereby authorizes the Executive Director of Public Works as the official representative of the City to apply for the Congestion Mitigation and Air Quality Improvement Program funding under the Fixing America's Surface Transportation Act for the following projects: • Protected Bike Lanes on Bristol Street: Warner Avenue to St. Andrews Place • Protected Bike Lanes on Bristol Street: St. Andrews Place to Edinger Avenue • Protected Bike Lanes on Bristol Street: First Street to Civic Center Drive • Protected Bike Lanes on Bristol Street: Civic Center Drive to Washington Avenue • Protected Bike Lanes on Warner Avenue: Oak Street to Grand Avenue • Protected Bike Lanes on Memory Lane: The City Drive to Flower Street Section 2. The City of Santa Ana agrees to fund its share of the project coats and any additional costs over the identified programmed amount. Resolution No. 2018 -XXX Page 2 of 3 55C-4 jmf 11/14/18 Section 3. This Resolution shall take effect immediately upon its adoption by the City Council, and the Clerk of the Council shall attest to and certify the vote adopting this Resolution. ADOPTED this _ day of , 2018. Miguel A. Pulido Mayor APPROVED AS TO FORM: Sonia R. Carvalho, City Attorney By. lYV T John M. Funk Assistant City Attorney AYES: Councilmembers NOES: Councilmembers ABSTAIN: Councilmembers NOT PRESENT: Councilmembers CERTIFICATE OF ATTESTATION AND ORIGINALITY I, Maria D. Huizar, Clerk of the Council, do hereby certify the attached Resolution No. 2018 - to be the original resolution adopted by the City Council of the City of Santa Ana on .2018. Date: Clerk of the Council City of Santa Ana 55C-5 Resolution No. 2018-)= Page 3 of 3 55C-6 Bicycle Corridor Improvement Program Bicycle Facilities Locations Recommended for Grant Application FY 2018-2019 Project Description Cost Bristol Street Protected Bike Install protected/buffered bike lanes and lane $2,003,873 Lanes: Phase II narrowing on Bristol Street from Warner Avenue to St. Andrews Place. Bristol Street Protected Bike Install protected/buffered bike lanes and lane $1,341,630 Lanes: Phase III narrowing on Bristol Street from St. Andrews Place to Edinger Avenue. Bristol Street Protected Bike Install protected/buffered bike lanes and lane $1,918,593 Lanes: Phase V narrowing on Bristol Street from First Street to Civic Center Drive. Bristol Street Protected Bike Install protected/buffered bike lanes and lane $1,105,380 Lanes: Phase IV narrowing on Bristol Street from Civic Center Drive to Washington Avenue Warner Avenue Protected Bike Install protected/buffered bike lanes and lane $1,442,205 Lanes narrowing on Warner Avenue from Oak Street to Grand Avenue. Memory Lane Protected Bike Install protected/buffered bike lanes and lane $3,522,733 Lanes narrowing on Memory Lane from The City Drive to Flower Street. Total $11,334,414 Exhibit 2 55C-7 55C-8 Memory Lane: The City Drive to Flower Street Bristol Street: Washington Avenue to Civic Center Drive 22 I � Bristol Street: St. Andrews Place to Edinger Avenue 1 Lu Bristol Street: Warner Avenue to St. Andrews Place SANTA ANA � City Council Agenda Date FU9LCMRKS AGERCVA,Ex,y December 4, 21 Bristol Street: Washington Avenue to Civic Center Drive 155 Fairhaven r � 215i o' 17th tre t ° M Washington Ove PlBI® Blvd. _--"I--I-------__ Warner Avenue: Oak Street to Grand Avenue RESOLUTION AND AUTHORIZATION FOR 6 BICYCLE CORRIDOR IMPROVEMENT PROGRAM APPLICATIONS 55C-10