HomeMy WebLinkAbout20A - AA - SAN LORENZOREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
OCTOBER 1, 2019
TITLE:
APPROVE AN APPROPRIATION
ADJUSTMENTAND AWARD A
CONSTRUCTION CONTRACT TO
ROCKFORCE CONSTRUCTION, LLC, IN
AMOUNT OF $7,606,500 AND APPROVE AN
AGREEMENT WITH BUTIER ENGINEERING,
INC., TO PROVIDE CONSTRUCTION
ENGINEERING SERVICES FOR THE SAN
LORENZO SEWER LIFT STATION PROJECT
IN AMOUNT NOT TO EXCEED $550,000 —
ESTIMATED TOTAL DELIVERY COST:
$10,058,125
(PROJECT NO 06-3510)
{STRATEGIC PLAN NOS. 6, 1 C & 1 G}
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 111 Reading
❑ Ordinance on 2i1 Reading
❑ Implementing Resolution
❑ Set Public Hearing For
111111•1►oil ►l1l0.i[•1
/s/ Kristine Ridge FILE NUMBER
CITY MANAGER
RECOMMENDED ACTION
1. Approve an appropriation adjustment to spend $1,416,100 from prior year fund balance in
the Sewer Connection Fee fund, Improvements Other Than Building expenditure account.
2. Award a contract to Rockforce Construction, LLC, the lowest responsible bidder, in
accordance with the base bid in the amount of $7,606,500, for construction of the San
Lorenzo Sewer Lift Station Project, for the term beginning upon execution of the contract and
ending upon project completion, and authorize the City Manager to execute the contract
subject to non -substantive changes approved by the City Manager and the City Attorney.
3. Authorize the City Manager to execute an agreement with Butier Engineering, Inc., to provide
Construction Engineering Services for the San Lorenzo Sewer Lift Station project, for the
three-year term beginning October 1, 2019, and expiring on September 30, 2022, with
provisions for two one-year extensions exercisable by the City Manager and City Attorney, in
the total amount not to exceed $550,000, which includes a $479,572 project fee and a
contingency of $70,428, subject to non -substantive changes approved by the City Manager
and City Attorney.
4. Approve the Project Cost Analysis for a total estimated delivery cost of $10,058,125, which
includes the contract base bid, Construction Engineering Services agreement, administration,
20A-1
Award Construction and Construction Engineering Contracts
for the San Lorenzo Sewer Lift Station Project
October 1, 2019
Page 2
inspection and testing, and an authorized contingency of $1,140,975, to be paid with Sewer
Connection Projects funding.
DISCUSSION
The City of Santa Ana Segerstrom Sewer Lift Station, located on the east side of Bristol Street,
about 300 feet north of Segerstrom Avenue, has been in service since 1965. This City -owned
facility is providing a service to a tributary area of approximately 380 acres and pumping
approximately 1.2 million gallons of sewage every day. Currently, this 55-year-old station has
surcharge problems with upstream sewer mains and requires frequent maintenance and repair.
In addition, City maintenance crews and vehicles must divert traffic out of the northbound traffic
lanes on Bristol Street to access the facility. Maintenance efficiencies can be improved by
relocating the facility and replacing the failing pumps and equipment.
The proposed new San Lorenzo Sewer Lift Station will be located at the southwest corner of the
intersection of San Lorenzo Avenue and Baker Street (Exhibit 1). The scope of work includes
approximately 880 linear feet of 15-inch and 12-inch gravity sewer mains and 600 linear feet of
parallel 10-inch force mains, sewer manholes, sewer gate valves, 3 vertical dry pit sewage
pumps, motors with variable frequency drives, in -line grinders, flow meter, underground concrete
dry well and wet well, piping, fittings, and appurtenances. Moreover, this project will construct a
new concrete masonry unit block building with a Heating, Cooling & Ventilation (HVAC) system,
ducting, rails, hoist system, gravity scrubber system, electrical and instrumentation; plus site
grading, landscaping, and irrigation improvements. Once completed, the improvements will
improve system efficiency, reliability, and enhance safety.
Project Construction: Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised
in the Orange County Register newspaper on April 5 and 9, 2019, and bids were received
electronically via the City's web -based electronic bidding system, PlanetBids, on July 9, 2019.
Through the PlanetBids online portal, vendors may register to receive notifications on all current
and future City projects, as well as download contract documents, receive project updates and
submit bids electronically.
A total of 137 vendors, including 7 located in the City of Santa Ana, were notified of the project
via PlanetBids. 108 vendors requested bidding documents and 5 bids were received, including 1
bid from a Santa Ana contractor.
20A-2
Award Construction and Construction Engineering Contracts
for the San Lorenzo Sewer Lift Station Project
October 1, 2019
Page 3
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
Rockforce Construction, LLC.
Lake Forest
$7,606,500
2
MMC, Inc
La Palma
$7,854,000
3
Steve P. Rados, Inc.
Santa Ana
$9,761,700
4
PCL Construction, Inc.
Long Beach
$10,712,501
5
Lonerock, Inc.
Irvine,
$10,714,824
All 5 bids received were deemed responsive. Rockforce Construction, LLC. submitted the lowest
responsive bid in the amount of $7,606,500 (Exhibit 2). Based on the bid analysis and a
contractor's reference check, staff recommends awarding the construction contract to Rockforce
Construction, LLC, in the amount bid (Exhibit 3).
Construction Engineering Services
Currently, the Construction Services department is assisting with the construction management
for the Orange County Streetcar project and providing field inspections, as well as ongoing
coordination with other capital improvement projects. Therefore, the Construction Services
department will utilize a consultant to oversee the San Lorenzo Sewer Lift Station project. The
Public Works Agency issued a request for proposals (RFP) on the City's Website and notified
qualified consulting firms to provide Construction Engineering Services for this project. Seven
proposals were received and evaluated by a review committee from the Public Work Agency.
Each firm was rated according to its organization, credentials, resumes, references, and fees to
provide the required services, the list of the firms and their respective scores are listed on the
following table.
FIRM
LOCATION
SCORE
Butier Engineering, Inc.
Tustin
88
MWH Constructors
Pasadena
85
Interwest Consulting Group
Huntington Beach
84
Lee & Ro, Inc.
City of Industry
81
NV5
Irvine
79
Willdan Group
Anaheim
79
GK & Associates
Diamond Bar
71
Butier Engineering, Inc., is the top ranking consultant for this project. Their cost proposal was
negotiated to ensure the City would receive the highest quality and value. Staff recommends that
Butier Engineering, Inc. be retained and a contract awarded for construction engineering services
20A-3
Award Construction and Construction Engineering Contracts
for the San Lorenzo Sewer Lift Station Project
October 1, 2019
Page 4
in the amount not to exceed $550,000, which includes a $479,572 project fee and a contingency
of $70,428, for the term of the agreement (Exhibit 4).
Protect Delivery
In order to deliver a complete project, in addition to the construction contract awarded to the
lowest responsible bidder, the estimated total construction delivery cost of the project includes
construction administration, inspection and testing, along with an allowance for contingencies to
account for unexpected or unforeseen conditions. Construction administration and inspection
includes construction management, implementation of the City's Community Workforce
Agreement requirements, inspection of the contractor's work to ensure contract compliance,
workmanship and quality, and material testing. As indicated in the Cost Analysis (Exhibit 5) and
as summarized in the table below, the estimated total construction delivery cost of the project is
$10,058,125.
Construction Contract
$7,606,500
Construction Engineering Services Agreement
$550,000
Inspection and Testing
$608,520
Construction Administration
$152,130
Contingencies
$1,140,975
ESTIMATED CONSTRUCTION DELIVERY COST
$10,058,125
Project funds will cover all staffing costs associated with the delivery of this capital project. No
additional funding will be used.
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 — Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy C (invest resources and technology to extend the service life of existing
infrastructure to protect the City's investment and support a high quality of life standard) and
Strategy G (develop and implement the City's Capital Improvement Program in coordination with
the Community Investment Plan).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are
exempt from further review. Categorical Exemption Environmental Review No. ER-2011-04 was
filed for the project.
20A-4
Award Construction and Construction Engineering Contracts
for the San Lorenzo Sewer Lift Station Project
October 1, 2019
Page 5
FISCAL IMPACT
As indicated in the Cost Analysis (Exhibit 5), the estimated total construction delivery cost of the
project is $10,058,125, which includes the construction contract, contract administration,
inspection, testing, and project contingency.
Approval of the requested Appropriation Adjustment will authorize expense of $1,416,100 from
the prior year fund balance in the Sewer Connection Fee Fund - Improvements Other Than
Building expenditure account (No. 05517660-66220). The estimated fund balance at June 30,
2019 is $12,866,589, which is sufficient for the proposed appropriation adjustment.
The following table summarizes the budget to deliver construction of this project:
Accounting Unit—
Accounting Unit —
Fiscal Year
Account No.
Fund Description
Account No.
Amount
Project No.
Description
Sewer Connection
FY 2019-20
05517660-66220
Sewer Connection
Projects —
$10,058,125
Oct. - June
(Proj. 06-3510)
Fee
Improvements Other
Than Building
Total
$10,058,125
All Funds are scheduled for expenditure in Fiscal Year 2019-20.
Fuad S. Sweiss, PE, PLS
Executive Director
Public Works Agency
FSS/TC/MO
Exhibits: 1. Location Map
2. Bid Proposal
3. Construction Contract
4. Consultant Agreement
5. Cost Analysis
APPROVED AS TO FUNDS & ACCOUNTS:
Kathryn Downs, CPA
Executive Director
Finance and Management Services Agency
20A-5
City of Santa Ana
San Lorenzo Sewage Lift Station (06.3510), bidding on July 9, 2019 2:00 PM (Pacific)
Bid Results
Bidder Details
Vendor Name
Rockforce Construction, LLC
Address
26772 Vista Terrace
Lake Forest, CA 92630
United States
Respondee
Craig Roth
Respondee Title
Vice President
Phone
949-441-5200 Ext. 5245
Email
craigr@rockforce.com
Vendor Type
License #
999390
CA DIR
Bid Detail
Bid Format
Electronic
Submitted
July 9, 2019 1:52:38 PM (Pacific)
Delivery Method
Bid Responsive
Bid Status
Submitted
Confirmation #
184065
Ranking
0
Respondee Comment
Buyer Comment
Attachments
File Title
General Forms
Ownership Affidavit
Bid Bond
Non Collusion Affidavit
Subs
Line Items
Type Item Code
Base Bid Proposal
1 Mobilization/Demobilization*
File Name
Proposal.pdf
Ownership Affidavit.pdf
Bid Bond.pdf
Non Collusion.pdf
Subs.pdf
UOM oty
LS 1
2 Sheeting, Shoring, Bracing and Excavationffrench Protection
LS 1
Page 1
Printed 08/15/2019
EXHIBIT 2
File Type
General Forms
Ownership Affidavit (Notary
Public) - REQ Original Hard
Copy Submittal In Addition
Bid Bond Guaranty (Notary
Public) - REQ Original Hard
Copy Submittal In Addition
Non -Collusion Affidavit
(Notary Public) - REQ
Original Hard Copy
Submittal in Addition
Subcontractor Listing Form
Unit Price Line Total Comment
$350,000.00 $360,000.00
$700,000.00 $700,000.00
PlanetBids, Inc.
20A-7
City of Santa Ana
Page 2
San Lorenzo Sewage Lift Station (06-3510), bidding on July 9, 2019 2:00 PM (Pacific)
Printed 08/15/2019
Bid Results
Type
Item Code UOM city
Unit Price
Line Total Comment
3
Construct, Operate and Maintain a Dewatering System
LS 1
$300,000.00
$300,000.00
4
Construct Sewage Lift Station
LS 1
$3,200,000.00
$3,200,000.00
5
Furnish and Install Electrical Equipment and Facilities
LS 1
$570,000.00
$570,000.00
6
Furnish and Install Instrumentation and Control Equipment and Facilities including
Programming
LS 1
$116,000.00
$116,000.00
7
Construct Site Piping
LS 1
$50,000.00
$50,000.00
8
Construct Site Improvements
LS 1
$300,000.00
$300,000.00
9
Construct Temporaty Sewer Bypass of Existing 10" Sewer at Lift Station Site
LS 1
$76,000.00
$75,000.00
10
Construct Electrical Conduit from Existing Generator by Directional Drilling
LS 1
$20,000.00
$20,000.00
11
Demolition of Existing Segerstrom Lift Station
LS 1
$20,000.00
$20,000.00
12
Construct Parallel Force Mains and Valves, and 16" Gravity Sewer and Manholes from Sts. 7+87f to
Sta. 25+72f
LS 1
$550,000.00
$550,000.00
13
Construct 15" Gravity Sewer and Manholes from Sta. 20+00 to Sta. 25+72±
LS 1
$580,000.00
$680,000.00
14
Construct 12" Gravity Sewer and Manholes from Sta. 30+00 to Ste. 31+90f
LS 1
$200,000.00
$200,000.00
15
Construct Connection to OCSD Existing Manhole (Manhole No. 11)
LS 1
$5,000.00
$5,000.00
16
Abandon In Place Existing Sewer Mains
LS 1
$12,000.00
$12,000.00
17
Furnish and Install Irrigation and Landscaping
LS 1
$16,000.00
$15,000.00
18
Prepare and Obtain Approval of Traffic Control Plans
LS 1
$10,000.00
$10,000.00
PlanetBids, Inc.
20A-8
City of Santa Ana
Page 3
San Lorenzo Sewage Lift Station (06-3510), bidding on July 9, 2019 2:00 PM
(Pacific)
Printed 08/15/2019
Bid Results
Type
Item Code UOM
Qty
Unit Price
Line Total Comment
19
Provide and Maintain Traffic Control
LS
1
$50,000.00
$50,000.00
20
Prepare and Implement Stormwater Pollution Prevention Plan
LS
1
$20,000.00
$20,000.00
21
Removal of Existing Median/Landscaping, Construct Temporary Pavement including Re -striping, and Replacement of Median and
Landscaping
LS
1
$130,000.00
$130,000.00
22
Removal and Replacement of Concrete Bus Pad
LS
1
$30,000.00
$30,000.00
23
Removal and Replacement of Curb, Gutter, Sidewalk and Medians
LS
1
$18,000.00
$18,000.00
24
Replacement of Traffic Lopps, Detectors and Wiring
LS
1
$15,000.00
$15,000.00
25
Construct Grind and ARHM Overlay
SF
44000
$2.25
$99,000.00
26
Furnish and Install Final Striping and Replacement of Pavement Markings
LS
1
$15,000.00
$15,000.00
27
TV Inspection of Gravity Sewer Mains
LS
1
$5,000.00
$5,000.00
28
Potholing
LS
1
$50,000.00
$50,000.00
29
Over -Excavation and Subgrade Stabilization of Trenches'
CY
100
$225.00
$22,500.00
30
Construction Staking
LS
1
$30,000.00
$30,000.00
31
Start-up, Testing and Training
LS
1
$15,000.00
$15,000.00
32
As -Built Plans, O&M Manuals and Warranties
LS
1
$5,000.00
$5,000.00
33
Permits
LS
1
$20,000.00
$20,000.00
34
Labor Agreement Oversight
LS
1
$10,000.00
$10,000.00
PlanetBids, Inc.
20A-9
City of Santa Ana Page 4
San Lorenzo Sewage Lift Station (06-3510), bidding on July 9, 2019 2:00 PM (Pacific) Printed O6/15/2010
Bid Results
Type Item Code UOM Oty Unit Price Line Total Comment
Subtotal $7,606,500.00
Asterisk Notes (per P-3 of P-17 of Specifications) - NOT part of Total Bid Calculation
35 "= Mobilization/Demobilization bid item is limited to a maximum of 5%of the Total Bid
as 0 0 0
36 "°"' = The quantity for this bid item is shown for bid comparison only. This bid Item shall not be subject to the 25% limit as stated in Section
3-2 of the Standard Specifications...
as 0 0 0
Subtotal 0
Total $7,606,500.00
PlanetBids, Inc.
20A-10
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Rockforce Construction, LLC
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1*
Mobilization/Demobilization
1
LS
$
$
2
Sheeting, Shoring, Bracing and
1
LS
$
$
Excavation/Trench Protection
3
Construct, Operate and Maintain a
l
LS
$
$
Dewatering System
4
Construct Sewage Lift Station
I
LS
$
$
5
Furnish and Install Electrical Equipment
1
LS
S
$
and Facilities
6
Furnish and Install Instrumentation and
1
LS
$
$
Control Equipment and Facilities including
Proerammina
7
Construct Site Piping
I
LS
$
$
8
Construct Site Improvements
I
LS
$
$
9
Construct Temporary Sewer Bypass of
I
LS
$
$
Existing 10" Sewer at Lift Station Site
10
Construct Electrical Conduit from Existing
I
LS
$
$
Generator by Directional Drilling
11
Demolition of Existing Segerstrom Lift
l
LS
$
$
Station
12
Construct Parallel Force Mains and Valves,
1
LS
$
$
and 15" Gravity Sewer and Manholes from
Sta. 7+87+ to Sta. 15+49t
13
Construct 15" Gravity Sewer and
1
LS
$
$
1
Manholes from Sta. 20+00 to Sta. 25+72+
P-1 ofP-17
20A-11
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
Item
Description
Qty
Unit
Unit Price
Amount
14
Construct 12" Gravity Sewer and
1
LS
$
$
Manholes from Sta. 30-00 to Sta. 31+90t
15
Construct Connection to OCSD Existing
1
LS
$
$
Manhole (Manhole No. 11)
16
Abandon in Place Existing Sewer Mains
1
LS
$
$
17
Furnish and Install Irrigation and
I
LS
$
$
Landscaping
18
Prepare and Obtain Approval of Traffic
I
LS
$
$
Control Plans
19
Provide and Maintain Traffic Control
1
LS
$
$
20
Prepare and Implement Stormwater
I
LS
$
$
Pollution Prevention Plan
21
Removal of Existing Median/Landscaping,
1
LS
$
$
Construct Temporary Pavement including
Re -striping, and Replacement of Median
and Landscaping
22
Removal and Replacement of Concrete
I
LS
$
$
Bus Pad
23
Removal and Replacement of Curb, Gutter,
I
LS
$
$
Sidewalk and Medians
24
Replacement of Traffic Loops, Detectors
1
LS
$
$
and Wiring
25
Construct Grind and ARHM Overlay
44,000
SF
$
$
26
Furnish and Install Final Striping and
I
LS
$
$
Replacement of Pavement Markings
27
TV Inspection of Gravity Sewer Mains
I
LS
$
$
28
Potholing
1
LS
$
$
29**
Over -Excavation and Subgrade
100
CY
$
$
Stabilization of Trenches
30
Construction Staking
1
LS
$
$
31
Start-up, Testing and Training
1
LS
$
$
32
As -Built Plans, O&M Manuals and
1
LS
$
$
Warranties
33
Permits
I
LS 1
$ 20,000
$ 20,000
P-2 ofP-17
20A-12
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIEF STATION
Item
Description
Qty
Unit
Unit Price
Amount
34
Labor Agreement Oversight
1
LS
$ 10,000
$ 10,000
TOTAL BASE BID $
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* Mobilization/Demobilization bid item is limited to a maximum of 5% of the Total Base Bid.
** The quantity for this bid item is shown for bid comparison only. This bid item shalt not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within three hundred (300) workine days after the commencement date stated in the
Notice to Proceed.
The liquidated damages amount, in lieu Of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,500 per calendar day.
Name of Firm Rockforce nstrucfon, LLC
Signature of BIDDER
a
Title Chief Estimator / VP Heavy Civil
(If an individual, so state. if a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof)
P-3 o f P-17
20A-13
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
BIDDER'S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council
with her signature and official seal noting hereon the action of approval of the Council, signed by
the Public Works Agency Executive Director or his/her duly authorized agent, and signed by the
City Attorney, denoting his approval of the form of this document, and its execution, and when it
or an exact copy of it has been either delivered to BIDDER or deposited with the United States
Postal Service properly addressed to the BIDDER with the correct postage affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of damages
actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond
Substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation under
the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Firm Rockforce Construction_ LLC
Signature of BIDDER
Title Chief Estimator / VP Heavy Civil
(If an individual, so state. if a firm or co -partnership, state the firm name and give the names ol
all individual co-partners composing the firm. If corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof)
P-4 of P-17
20A-14
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
CQNNTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she and
all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: Rockforce Construction, LLC
Business Address: 26772 Vista Terrace Lake Forest, CA 92630
Business E-Mail Address: Estimating@RockPorce.com
Telephone: (949) 441-5200
State Contractor's License No. and Class: 999390 "A"
License Expiration Date
12/31 /2020
State Dept. of Industrial Relations (DIR)
Registration No.: 1000004540
State Dept. of Industrial Relations (DIR)
Registration E�p{rationPqte: 6/30/2021
Signed:
Title: Chief Estimator / VP Heavv Civil
igfP-16
dX
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well as
California Code of Regulations, Title 8, Section 16,000, et seq., ("Prevailing Wage Laws"), which
require the payment of prevailing wage rates and the performance of other requirements on "public
works" and "maintenance" projects. Since the services are being performed as part of an applicable
"public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and since the
total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing
Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the
commencement of this Agreement. Contractor shall make copies of the prevailing rates of per
diem wages for each craft, classification or type of worker needed to execute the services available
to interested parties upon request, and shall post copies at the Contractor's principal place of
business and at the project site.
Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and
agents free and harmless from any claim or liability arising out of any failure or alleged failure to
comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct.
Name of Firm Rockforce Construction_ LLC
Signature of BIDDER
Title Chief Estimator/VP Heavy Civil
(if an individual, so state)
P-6 of P-17
20A-16
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
1. County of San Bernardino - 157 West Fifth St. San Bernardino, CA 92415
Name and Address of Owner.
Jeff Rienev (909) 387-5967
Name and Telephone Number of person familiar with project.
$11,385,700,00 Dam Rehabilitation
Contract Amount Type of Work
5/31/2019
2. Metropolitan Water District - 700 North Alameda St. Los Angeles, CA 90012
Name and Address of owner.
Date Completed
Name and Telephone Number of person familiar with project.
$5,285,000 Siphons Erosion Protection 11/19/2018
Contract Amount Type of Work Date Completed
3. County of San Bernardino - Sp_ ecial Districts Dept. 825 East Third St. San Bernardino, CA 92415
Name and Address of owner.
Name and Telephone Number of person familiar with project.
$14.574,460.00 Basin and Dam Construction 8/1 1/2020
Contract Amount Type of Work
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Bonding Co. / Surety - Arch Insurance Company 3 Parkway Suite 41500 Philadelphia, PA 19145 (215) 606-1600
Name of Surety Agent - CSBA 1411 No. Batavia. Suite #20I Orange. CA 92867 (714) 516-1232
Contact: Arturo Ayala
P-10 of P-17
20A-17
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
Name and Address of Owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
z. NIA
Name and Address of owner,
3.
Name and Telephone Number of person familiar with project.
Contract Amount
of owner.
Type of Work
Name and Telephone Number of person familiar with project.
Contract Amount
Type of Work
Date Completed
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
I •,
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
1. The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf
of the Contractor, state that all qualified applicants will receive consideration for employment
without regard to race, color, religion, sex, or national origin.
3. The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
The Contractor shall furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders ofthe Secretary of Labor, or pursuant
thereto, and will permit access to his/her books, records, and accounts by the administering
agency and the Secretary of Labor for purposes of investigation, to ascertain compliance with
such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible for
further Government contracts or federally assisted construction contracts in accordance with
procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as otherwise
provided by law.
P-13 ofP-17
20A-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless
exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section
204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding
upon each subcontract or purchase order as the administering agency may direct as means of
enforcing such provisions, including sanctions for noncompliance; provided, however, that in
the event the Contractor becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as a result of such direction by the administering agency, the
Contractor may request that the United States enter into such litigation to protect the interests
of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation oChapte�
Signed: �(/ �t1/��%
0
Title: Chief Estimator / VP Heavy Civil
Firm: Rockforce Construction, LLC
Date: 7/9/19
P-14 ofP-1
20A-2
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
1. Apply to the joint apprenticeship connnittee administering the apprenticeship standards of the
craft or trade in the area of the site of the public work for a certificate approving the contractor
under the apprenticeship standards for the employment and training of apprentices in the area
or industry affected.
2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
3. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like amount to t California Apprenticeship Council.
Signed: Z�"i
Title: Chief Estimator / VP Heavy Civil
Firm: Rockforce Construction. LLC
Date: 7/9/19
P-15 ofP-17
20A-21
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
STATEMENT REGARDING "ANTI -KICKBACK" REOUIREMENT
The undersigned is submitting this proposal for performing by contract the work required by these
bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repair of public work, to give up any part of the compensation to
which he/she is Trwi21ZN�
entitled.
Signed: =�
z
Title: Chief Estimator / VP Heavy Civil
Firm: Rockforce Construction, LLC
Date: 7/9/19
��6Qf PnlZ
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 06-3510
SAN LORENZO SEWAGE LIFT STATION
PUBLIC CONTRACT CODE SECTION 10162 OUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented from
bidding on, or completing a federal, state, or local government project because of a violation of
law or a safety regulation?
Yes No X
If the answer is yes, explain the circumstances in the following space
P-17 ofP-17
20A-23
EXHIBIT 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 06-3510
SAN LORENZO SEWAGE LIFT STATION PROJECT
This CONSTRUCTION CONTRACT is made and entered into this 17h day of September, 2019 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and
existing under the Constitution and laws of the State of California (hereinafter "CITY"), and Rockforce
Construction, LLC (hereinafter "CONTRACTOR").
WPI'NESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the
satisfaction of the City Engineer of the CITY, the San Lorenzo Sewage Lift Station Project
(hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with
the Contract Documents prepared by the City's Public Works Agency and approved by the City
Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Seven Million Six Hundred Six Thousand
Five Hundred and No Cents ($7,606,500.00), as set forth and identified in the BID PROPOSAL,
which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
rev. 09/01/2017 20A-24 Page 1 of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
http://www.santa-ana.org/pwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
//
20 " -25 Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By: 4 / "-f
WiN FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
FUAD SWEISS, PE, PLS
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
Rockforce Construction, LLC
AME:
TITLE:
20A-26
Page 3 of 3
EXHIBIT 4
AGREEMENT TO PROVIDE CONSTRUCTION ENGINEERING SERVICES
FOR THE SAN LORENZO SEWAGE LIFT STATION PROJECT
THIS AGREEMENT is made and entered into this 1 st day of October, 2019 by and between Butier
Engineering, Inc. ("Contractor"), and the City of Santa Ana, a charter city and municipal
corporation organized and existing under the Constitution and laws of the State of California
("City").
RECITALS
A. On .Tune 14, 2018, the City issued Request for Proposal No. 18-049, by which it
sought a contractor to provide construction engineering services for the San
Lorenzo Sewage Lift Station Project.
B. Contractor submitted a responsive proposal that was selected by the City.
Contractor represents that it is able and willing to provide the services described in
the scope of work that was included in REP No, 18-049.
C. In undertaking the performance of this Agreement, Contractor represents that it is
knowledgeable in its field and that any services performed by Contractor under this
Agreement will be performed in compliance with such standards as may reasonably
be expected from a professional contracting firm in the field.
NOW THEREFORE, in consideration of the mutual and respective promises, and subject to the
terms and conditions hereinafter set forth, the parties agree as follows:
1. SCOPE OF SERVICES
Contractor shall perform the services that were described in the scope of work that was
included in REP No. 18-049 and that is attached as Exhibit A, and as further delineated in
Contractor's proposal, which is attached as Exhibit B and incorporated in Rill.
2. COMPENSATION
a. City agrees to pay, and Contractor agrees to accept as total payment for its services
under this Agreement, the rates and charges identified in Exhibit C. The total sum
to be expended under the terra of this Agreement, including any extension periods,
shall not exceed $550,000. This sum is comprised of (1) base amount of $479,572
and (2) an approximate 15% contingency of $70,428 for additional services at the
City's sole discretion.
b. Payment by City shall be made within forty-five (45) days following receipt of
proper invoice evidencing work performed, subject to City accounting procedures.
Payment need not be made for work which fails to meet the standards of
performance set forth in the Recitals and Scope of Work, which may reasonably be
expected by City.
Page t of. 8
20A-27
3. TERM
This Agreement shall commence on the date first written above and terminate on
September 30, 2022, unless terminated earlier in accordance with Section 17, below. The term of
this Agreement may be extended for up to two 1-year periods upon a writing executed by the City
Manager and City Attorney,
4. PREVAILING WAGES
Contractor is aware of the requirements of California Labor Code Section 1720, et seq.,
and 1770, of seq., as well as California Code of Regulations, Title 8, Section I6000, et seq.,
("Prevailing Wage Laws"), which require the payment of prevailing wage rates and the
performance of other requirements on "public works" and "maintenance" projects. If the services
being performed are part of an applicable "public works" or "maintenance" project, as defined by
the Prevailing Wage Laws, and the total compensation is $1,000 or more, Contractor agrees to
fully comply with such Prevailing Wage Laws. Contractor shall defend, indemnify and hold the
City, its elected officials, officers, employees and agents free and harmless from any claim or
liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws,
5. INDEPENDENT CONTRACTOR
Contractor shall, during the entire teen of this Agreement, be construed to be an
independent contractor and not an employee of the City. This Agreement is not intended nor shall
it be construed to create an employer -employee relationship, a joint venture relationship, or to
allow the City to exercise discretion or control over the professional manner in which Contractor
performs the services which are the subject matter of this Agreement; however, the services to be
provided by Contractor shall be provided in a manner consistent with all applicable standards and
regulations governing such services. Contractor shall pay all salaries and wages, employer's social
security taxes, unemployment insurance and similar taxes relating to employees and shall be
responsible for all applicable withholding taxes.
6. OWNERSHIP OF MATERIALS
This Agreement creates a non-exclusive and perpetual license for City to copy, use,
modify, reuse, or sublicense any and all copyrights, designs, and other intellectual property
embodied in plans, specifications, studies, drawings, estimates, and other documents or works of
authorship fixed in any tangible medium of expression, including but not limited to, physical
drawings or data magnetically or otherwise recorded on computer diskettes, which are prepared or
caused to be prepared by Contractor under this Agreement ("Documents & Data"). Contractor
shall require all subcontractors to agree in writing that City is granted a non-exclusive and
perpetual license for any Documents & Data the subcontractor prepares under this Agreement.
Contractor represents and warrants that Contractor has the legal right to license any and all
Documents & Data. Contractor makes no such representation and warranty in regard to
Documents & Data which were provided to Contractor by the City. City shall not be limited in
any way in its use of the Documents and Data at any time, provided that any such use not within
the purposes intended by this Agreement shall be at City's sole risk.
Page 2 of 8
20A-28
7. INSURANCE
Prior to undertaking performance of work under this Agreement, Contractor shall maintain
and shall require its subcontractors, if any, to obtain and maintain insurance as described below:
a. Commercial General Liability Insurance. Contractor shall maintain commercial
general liability insurance naming the City, its officers, employees, agents,
volunteers and representatives as additional insured(s) and shall include, but not be
limited to protection against claims arising from bodily and personal injury,
including death resulting therefrom and damage to property, resulting from any act
or occurrence arising out of Contractor's operations in the performance of this
Agreement, including, without limitation, acts involving vehicles. The amounts of
insurance shall be not less than the following: single limit coverage applying to
bodily and personal injury, including death resulting therefrom, and property
damage, in the total amount of $1,000,000 per occurrence, with $2,000,000 in the
aggregate. Such insurance shall (a) name the City, its officers, employees, agents,
volunteers and representatives as additional insured(s); (b) be primary with respect
to insurance or self-insurance programs maintained by the City; and (c) contain
standard separation of insureds provisions.
b. Business automobile liability insurance, or equivalent form, with a combined single
limit of not less than $1,000,000 per occurrence. Such insurance shall include
coverage for owned, hired and non -owned automobiles.
C. Workers' Compensation Insurance. In accordance with the California Labor Code,
Contractor, if Contractor has any employees, is required to be insured against
liability for workers' compensation or to undertake self-insurance. Prior to
commencing the performance of the work under this Agreement, Contractor agrees
to obtain and maintain any employer's liability insurance with limits not less than
$1,000,000 per accident.
d. If Contractor is or employs a licensed professional such as an architect or engineer:
Professional liability (errors and omissions) insurance, with a combined single lhnit
of not less than $1,000,000 per claim with $2,000,000 in the aggregate.
e. The following requirements apply to the insurance to be provided by Contractor
pursuant to this section:
(i) Contractor shall maintain all insurance required above in full force and
effect for the entire period covered by this Agreement,
(ii) Certificates of insurance shall be furnished to the City upon execution of
this Agreement and shall be approved by the City.
(iii) Certificates and policies shall state that the policies shall not be cancelled
or reduced in coverage or changed in any other material aspect, by
Contractor, without thirty (30) days prior written notice to the City.
(iv) Contractor shall supply City with a fully executed additional insured
endorsement.
Page 3 of 8
20A-29
If Contractor fails or refuses to produce or maintain the insurance required by this
section or fails or refuses to furnish the City with required proof that insurance has
been procured and is in force and paid for, the City shall have the right, at the City's
election, to forthwith terminate this Agreement. Such termination shall not affect
Contractor's right to be paid for its time and materials expended prior to notification
of termination. Contractor waives the right to receive compensation and agrees to
indemnify the City for any work performed prior to approval of insurance by the
City.
8. INDEMNIFICATION
Contractor agrees to defend, and shall indemnify and hold harmless the City, its officers,
agents, employees, contractors, special counsel, and representatives from liability: (1) for personal
injury, damages, just compensation, restitution, judicial or equitable relief arising out of claims for
personal injury, including death, and claims for property damage, which may arise from the
negligent operations of the Contractor or its subcontractors, agents, employees, or other persons
acting on their behalf which relates to the services described in section 1 of this Agreement; and
(2) from any claim that personal injury, damages, just compensation, restitution, judicial or
equitable relief is due by reason of the terms of or effects arising from this Agreement. This
indemnity and hold harmless agreement applies to all claims for damages, just compensation,
restitution, judicial or equitable relief suffered, or alleged to have been suffered, by reason of the
events referred to in this Section or by reason of the terms of, or effects, arising from this
Agreement. The Contractor further agrees to indemnify, hold harmless, and pay all costs for the
defense of the City, including fees and costs for special counsel to be selected by the City,
regarding any action by a third party challenging the validity of this Agreement, or asserting that
personal injury, damages, just compensation, restitution, judicial or equitable relief due to personal
or property rights 'arises by reason of the terms of, or effects arising from this Agreement. City
may make all reasonable decisions with respect to its representation in any legal proceeding.
Notwithstanding the foregoing, to the extent Contractor's services are subject to Civil Code
Section 2782.8, the above indemnity shall be limited, to the extent required by Civil Code Section
2782.8, to claims that arise of, pertain to, or relate to the negligence, recklessness, or willful
misconduct of the Contractor.
9. INTELLECTUAL PROPERTY INDEMNIFICATION
Contractor shall defend, indemnify and hold harmless the City, its officers, agents,
representatives, and employees against any and all liability, including costs, and attorney's fees,
for infringement of any United States' letters patent, trademark, or copyright contained in the work
product or documents provided by Contractor to the City pursuant to this Agreement.
10. RECORDS
Contractor shall keep records and invoices in connection with the work to be performed
under this Agreement. Contractor shall maintain complete and accurate records with respect to
the costs incurred under this Agreement and any services, expenditures, and disbursements
charged to the City for a minimum period of three (3) years, or for any longer period required by
Page 4 of 8
20A-30
law, from the date of final payment to Contractor under this Agreement. All such records and
invoices shall be clearly identifiable. Contractor shall allow a representative of the City to
examine, audit, and make transcripts or copies of such records and any other documents created
pursuant to this Agreement during regular business hours. Contractor shall allow inspection of all
work, data, documents, proceedings, and activities related to this Agreement for a period of three
(3) years from the date of final payment to Contractor under this Agreement.
11. CONFIDENTIALITY
If Contractor receives from the City information which due to the nature of such
information is reasonably understood to be confidential and/or proprietary, Contractor agrees that
it shall not use or disclose such information except in the performance of this Agreement, and
further agrees to exercise the same degree of care it uses to protect its own information of like
importance, but in no event less than reasonable care. "Confidential Information" shall include all
nonpublic information. Confidential information includes not only written information, but also
information transferred orally, visually, electronically, or by other means. Confidential
information disclosed to either party by any subsidiary and/or agent of the other party is covered
by this Agreement. The foregoing obligations of non-use and nondisclosure shall not apply to any
information that (a) has been disclosed in publicly available sources; (b) is, through no fault of the
Contractor disclosed in a publicly available source; (c) is in rightful possession of the Contractor
without an obligation of confidentiality; (d) is required to be disclosed by operation of law; or (e)
is independently developed by the Contractor without reference to information disclosed by the
City.
12. CONFLICT OF INTEREST CLAUSE
Contractor covenants that it presently has no interest and shall not have interests, direct or
indirect, which would conflict in any manner with performance of services specified under this
Agreement.
13. NOTICE
Any notice, tender, demand, delivery, or other communication pursuant to this Agreement
shall be in writing and shall be deemed to be properly given if delivered in person or mailed by
first class or certified mail, postage prepaid, or sent by fax or other telegraphic communication in
the manner provided in this Section, to the following persons:
To City: Clerk of the City Council
City of Santa Ana
20 Civic Center Plaza (M-30)
P.O. Box 1988
Santa Ana, CA 92702-1988
Executive Director
Public Works Agency
City of Santa Ana
Pngc S of 8
20A-31
20 Civic Center Plaza (M-21)
P.O. Box 1988
Santa Ana, CA 92702
To Contractor: Mark M. Butier
Vice President/Chief Financial Officer
Butier Engineering, Inc.
17822 E. 17th Street, Suite 404
Tustin, CA 92780
A party may change its address by giving notice in writing to the other party. Thereafter,
any communication shall be addressed and transmitted to the new address. If sent by mail,
communication shall be effective or deemed to have been given three (3) days after it has been
deposited in the United States mail, duly registered or certified, with postage prepaid, and
addressed as set forth above. If sent by fax, communication shall be effective or deemed to have
been given twenty-four (24) hours after the time set forth on the transmission report issued by the
transmitting facsimile machine, addressed as set forth above. For purposes of calculating these
timeframes, weekends, federal, state, County or City holidays shall be excluded.
14. EXCLUSIVITY AND AMENDMENT
This Agreement represents the complete and exclusive statement between the City and
Contractor regarding the subject matter herein, and supersedes any and all other agreements, oral
or written, between the parties. In the event of a conflict between the terms of this Agreement and
any attachments hereto, the terms of this Agreement shall prevail. This Agreement may not be
modified except by written instrument signed by the City and by an authorized representative of
Contractor. The parties agree that any terms or conditions of any purchase order or other instrument
that are inconsistent with, or in addition to, the terms and conditions hereof, shall not bind or
obligate Contractor or the City. Each party to this Agreement acknowledges that no
representations, inducements, promises or agreements, orally or otherwise, have been made by any
party, or anyone acting on behalf of any party, which are not embodied herein.
15. ASSIGNMENT
Inasmuch as this Agreement is intended to secure the specialized services of Contractor,
Contractor may not assign, transfer, delegate, or subcontract any interest herein without the prior
written consent of the City and any such assignment, transfer, delegation or subcontract without
the City's prior written consent shall be considered null and void. Nothing in this Agreement shall
be construed to limit the City's ability to have any of the services which are the subject to this
Agreement performed by City personnel or by other Contractors retained by City.
16, WAIVER
No waiver of breach, failure of any condition, or any right or remedy contained in or
granted by the provisions of this Agreement shall be effective unless it is in writing and signed by
the party waiving the breach, failure, right or remedy. No waiver of any breach, failure or right, or
Page 6 of 8
20A-32
remedy shall be deemed a waiver of any other breach, failure, right or remedy, whether or not
similar, nor shall any waiver constitute a continuing waiver unless the writing so specifies.
17. TERMINATION
This Agreement may be terminated by the City upon thirty (30) days written notice of
termination. In such event, Contractor shall be entitled to receive and the City shall pay Contractor
compensation for all services performed by Contractor prior to receipt of such notice of
termination, subject to the following conditions:
a. As a condition of such payment, the Executive Director may require Contractor to
deliver to the City all work product completed as of such date, and in such case
such work product shall be the property of the City unless prohibited by law, and
Contractor consents to the City's use thereof for such purposes as the City deems
appropriate.
Payment need not be made for work which fails to meet the standard of
performance specified in the Recitals of this Agreement.
18. NON-DISCRIMINATION
Contractor shall not discriminate because of race, color, creed, relation, sex, marital status,
sexual orientation, age, national origin, ancestry, or disability, as defined and prohibited by
applicable law, in the recruitment, selection, training, utilization, promotion, termination or other
employment related activities or in connection with any activities under this Agreement.
Contractor affirms that it is an equal opportunity employer and shall comply with all applicable
federal, state and local laws and regulations.
19. JURISDICTION -VENUE
This Agreement has been executed and delivered in the State of California and the validity,
interpretation, performance, and enforcement of any of the clauses of this Agreement shall be
determined and governed by the laws of the State of California. Both parties furtber agree that
Orange County, California, shall be the venue for any action or proceeding that may be brought or
arise out of, in connection with or by reason of this Agreement,
20, PROFESSIONAL LICENSES
Contractor shall, throughout the term of this Agreement, maintain all necessary licenses,
permits, approvals, waivers, and exemptions necessary for the provision of the services hereunder
and required by the laws and regulations of the United States, the State of California, the City of
Santa Ana and all other governmental agencies. Contractor shall notify the City immediately and
in writing of its inability to obtain or maintain such permits, licenses, approvals, waivers, and
exemptions. Said inability shall be cause for termination of this Agreement.
Page 7 of 8
20A-33
21. MISCELLANEOUS PROVISIONS
a. Each undersigned represents and warrants that its signature herein below has the
power, authority and right to bind their respective parties to each of the terms of
this Agreement, and shall indemnify City fully, including reasonable costs and
attorney's fees, for any injuries or damages to City in the event that such authority
or power is not, in fact, held by the signatory or is withdrawn.
All exhibits referenced herein and attached hereto shall be incorporated as if fully
set forth in the body of this Agreement.
IN WITNESS WHEREOF, the patties hereto have executed this Agreement the date and year first
above written.
ATTEST: CITY OF SANTA ANA
Daisy Gomez Kristine Ridge
Clerk of the Colmcil City Manager
APPROVED AS TO FORM CONTRACTOR
SONIA R. CARVALHO
City Attorney
By:
JWn M.Funk Name:
Assistant City Attorney Title: �a�f"Fo
RECOMMENDED FOR APPROVAL
Fuad S. Sweiss, PE, PLS
Executive Director
Public Works Agency
Page 8 of 8
20A-34
EXHIBIT A
Appendix
ATTACHMENT 1
SCOPE OF WORK
CITY OF SANTA ANA
REQUEST FOR PROPOSALS
FOR
CONSTRUCTION ENGINEERING SERVICES FOR
SAN LORENZO SEWAGE LIFT STATION
RFP NO.: 17-115
Introduction and Sack round:
The City desires to engage a professional consultant to perform construction engineering
services for the San Lorenzo Sewage Lift Station project. The consultant shall provide three
individuals to act as Project Manager (PM), Inspector, and a Contract Administrator (CA), and
serve as an extension of City staff to assist in the overall delivery of this project, including pre -
construction tasks, managing construction and ensuring that the work is completed in
accordance with the contract documents, and project closeout and warranty phase. The
consultant team will report directly to the City's Construction Manager or his authorized
representative. City staff may assist in managing construction and will oversee the work of the
Project Manager, Inspector, and Contract Administrator,
The estimated construction cost for the San Lorenzo Sewage Lift Station project is $6 million,
The City anticipates advertising construction bids in the early fall 2018, and starting
construction, by late 2018. Total construction duration for the project is anticipated to be 14
months.
Description of Work:
The required services by the Project Manager, the Inspector and the Contract Administrator may
include the following:
The PM shall be a registered engineer in the State of California and shall
represent the City Construction Manager in the field. The CM shall possess a
minimum of (5) years' experience in sewer lift station construction management.
The Inspector and the Contracts Administrator should have relevant experience
in sewer lift station construction management and certifications that affirm the
experience.
2. Prior to the start of the project, the PM shall be responsible for conducting a bid
analysis to determine who the lowest responsible bidder for the project will be.
Shall obtain certificates of insurance, performance bond and `New Vendor
Packet" requirements have been satisfied. This includes verifying that all sub-
contractors have a valid City ,Business License. Once determined, a staff report
will need to be generated to recommend the award of a Construction Contract.
City oT Santa Ana RFP 18,049
Page At-1
20A-35
3. The PM shall be responsible for review of completeness and quantity of all
required shop drawings, product data, samples and other submittals
("Submittals"). Shall transmit the Submittals to City staffing for review and
approval, and shall establish and implement procedures for expediting the
processing and approval of Submittals.
4. Attend pre -construction meeting and schedule and conduct weekly construction
and progress meetings to discuss such matters as procedures, progress, problems
and scheduling. Will prepare and promptly distribute minutes.
5. Shall be responsible for ensuring that all building permits and special permits, if
required are obtained and that all applicable fees have been paid, and shall obtain
approvals from authorities having jurisdiction over the Project.
6. Shall review construction schedule, including activity sequences and duration,
schedule of submittals and schedule of delivery for products with long lead-time.
Update the project schedule as required showing current conditions and revisions
required by actual progress.
7. Shall conduct comprehensive evaluation of change order requests, provide
independent estimates, render recommendations and assist in claim resolution.
Shall regularly monitor and report on the status of the Project Construction
Budget on a monthly basis, indicating actual costs for completed activities and
work in progress, and indicating estimates for uncompleted work. Report should
identify variances between actual and budgeted or estimated costs, and shall
advise the City whenever it appears that the Actual Construction Cost has
exceeded, or will exceed, the Project Construction Budget for the entire Project
or any Project Component.
8. Monitor the contractor's safety program. Take necessary steps to ensure the job
site conditions are in compliance with OSHA regulations.
9. Maintain cost accounting records on authorized work performed under unit costs
and additional work performed on the basis of actual costs of labor and materials,
or other work requiring accounting records.
10. May develop and implement procedures for the review and processing of
applications by contractor for progress and 'frnal payments. Make
recommendations for certification to the City for payment.
11, Determine that the work of contractor is being performed in accordance with the
contract documents. Make recommendations to the City regarding special
inspection or testing of work not in compliance with the provisions of the
contract documents. Subject to review by the City. reject work which does not
conform to the requirements of contract documents,
12. The individuals, Project Manager, Inspector and Contract Administrator, shall
City of Santa Ana RFP 1 B-049
Page Al-2
20A-36
not be responsible for construction means, methods, techniques, sequences and
procedures employed by the contractor in the performance of the contract, and
shall not be responsible for the failure of the contractor to carry out work in
accordance with the contract documents. However, any errors, omissions, or
discrepancies found in the Contract Documents shall be called to the attention of
the City's Construction Manager and clarified prior to construction starts.
13. Consult with the City when the contractor requests interpretations of the meaning
and intent of the drawings and specifications, and assist in achieving the
resolution of problems which may arise.
14. Record the progress of the project. Submit written daily and progress reports to
the City. Keep daily logs containing a record of weather, contractor's work on the
site, number of workers and equipment, work accomplished, problems
encountered, and other relevant data. Make the log available to the City. Prepare
and send Weekly Statement of Working Days to the contractor. Monitor
contractor's compliance with labor code requirements.
15. Maintain, at the job site, records of contract documents including drawings,
addenda, change orders, and other modifications of plans and specifications
marked to show all changes made during construction. Maintain as -built records
of underground utilities, including locations and depths of trenches. At the
completion of the project, deliver to the City all contract documents including as -
built records.
16. Evaluate the completion of the work of the contractor and make
recommendations to the City when work is ready for final inspection. Assist the
City in conducting final inspections.
17. Facilitate and coordinate inspection by representatives of other agencies
18. Schedule and coordinate special inspection and material testing with the County
of Orange or other consultants.
19. Shall monitor and enforce prevailing wage forms and requirements for
conformance to the prevailing wage rates on a weekly basis. Shall verify that all
Trade personnel listed in the daily log are also listed in the certified payroll and
shall conduct weekly employee interviews, one for each trade, and submit
verification with the monthly progress payments.
20, Shall monitor and enforce the City's Community Workforce Agreement (CWA)
forms and requirements to ensure compliance. Verification should be provided
with the monthly progress payments.
21. The PM shall be responsible for all project closeout items, such as: As -Built
plans and related documentation, punch list completion, commissioning,
warranty requests doing the one-year period. Shall schedule and oversee the
City of Santa Ana RFP 18-049
Page Al-3
20A-37
warranty repair, Should include site visits as requested by the City to look at
defects or imperfection to determine if it is a warranty issue.
The city reserves the right to add or reduce some of the above tasks and duties as it sees
fit. The consultant, serving as staff extension, shall remain sufficiently flexible to meet
the needs of the City and of the project.
ON lieSnQnsibilities:
1. Provide a testing laboratory for special inspection and material testing and other
quality assurance program as required by the contract documents.
2. Process progress payments upon receipt of approved payment requests from the
resident engineer/inspector.
3. Furnish copies of constriction documents, including plans and specifications.
4. Communicate with other consultant to review shop drawings and submittals,
respond to requests for information and revise plans if needed.
5. Provide a field office for the Project Manager, the Inspector and the Contract
Administrator.
6. Coordinate with the CM and serve as liaison with other City departments
Fee Proposal:
In addition to Section III.13.3 (Submittal Requirements: Fee Proposal) fez schedule shall be
structured as follows:
The cost proposal must include the projected staff hours, hourly rates, unit prices and
reimbursable expenses for the project, as follows:
[I] Itemized estimated breakdown for services for construction engineering services for the
duration of construction. The breakdown should include pre -construction services,
construction services, and warranty period services.
a. Personnel costs - Itemized to show the following:
1. Personnel by classification/responsibilities.
2. Hourly rate for each classification.
3. Estimated hours for each personnel category.
4. Subtotal cost for each category.
5. Total estimated personnel cost.
City of Santa Ana RFP 18-049
Page Al-4
20A-38
6. Include percent breakdown availability for each of the classifications
The estimated construction duration stated above is for the purpose of cost estimate only.
The length of time requiring Consultant's services will be dependent on the construction
progress. For services under this category, the Consultant shall be paid according to hourly
rates set forth herewith and the actual hours of service.
b. Estimated reimbursable Expenses:
1, Costs of supplies and materials (itemized).
2. Travel - Transportation and per diem or subsistence listed separately, if any.
3. Any other direct charges.
4, Total estimated reimbursable expenses.
For services under this category, the Consultant shall be paid according to the rates set forth
herewith and the actual reimbursable expenses.
c. Subtotal of a and b.
[II] Contingency services for each month after the original construction contract time,
Services under this category will be provided when requested by the City, and the Consultant
shall be paid according to hourly rates set forth herewith and the actual hours of sernrice.
For the purpose of comparison, each proposer shall use the same number of hours: 500 hours for
the Project Manager, the Inspector and the Contract Administrator. The subtotal of this category
shall be calculated as follows:
Proposed
Hourly Rate Hours Total
Project Manager $ Mr. 500
Inspector $ Mr. 500
Contract Administrator $ Mr. 500
City of Santa Ana RFP 15-049
Page Al-5
20A-39
Fs O
it
J
k t
I
Proposal for Due Date
RFP No. 18-049
Construction Engineering Services for the July 31, 2018
San Lorenzo Sewage Lift Station
No kV
. p1
• 1 •
Proposal to Provide
Construction Engineer] ng Services
for the San Lorenzo Sewage Lift Station
RFP No. 18-049
Due: July 31, 2018
BUTIER
Con T@rE/F.tioa �8J1€gE'i'S� (:plly JE egg IIueiS
SECTION A
Cover Letter
SECTION B
Firm & Team Experience
SECTION C
Understanding of Need
SECTION D
Relevant Project Experience
SECTION E
References
SECTION F
Scope of Services and Schedule
SECTION G
Certifications
20A-41
t
rl "{�N3-,y yy,Fi' x 1 !N,k F* fl F`. 5Fi'' ,� RAY•` 3 "qr 4 MY sTs,S$s� {P
..0 ..,
+.-
R� �y .ry �>'t�jy,3C t • � � a�
4 t
L
20A-42
Section A. Cover Letter
July 26, 2018
City of Santa Ana
Attn: Tyrone Chesanek
Public Works Agency
20 Civic Center Plaza
3� Floor Reception, Ross Annex
Santa Ana, CA 92701
Subject: RFP No. 18-049—Construction Engineering Services for the San Lorenzo Sewage
Lift Station Project
Dear Mr, Chesanek;
Butler Engineering, Inc. (Butler) is pleased to present five (5) hard copies of its proposal accompanied
by one (1) digital file on a labeled USB Flash Drive for the above stated subject. Per the RFP
instructions, we have also provided one (1) hardcopy of our Fee Proposal In a separate envelope.
Our submittal is fully responsive to the RFP and Addendum Nos. 1 and 2. The Butler Team offers
several distinguishing qualifications and a proven record of performance to the City of Santa Ana. To
address the demands of the San Lorenzo Sewage Lift Station Project, we have assembled a team that
has provided services on some of the largest water/wastewater capital improvement projects in
Southern California.
Contract Agreement Statement
We have reviewed the Contract Agreement and concur with any and all provisions as contained in
the Agreement attached in the RFP as Attachment 2 in the Appendix.
Established Relationship with City of Santa Ana
Butler is currently providing CM and inspection services for OCWD's Mid -Basin Injection Project. The
project, which is located within the City of Santa Ana's 87-acre Centennial Park, includes the
construction of four (4) groundwater injection wells. Our team is coordinating closely with the City and
Santa Ana Unified School District. In addition, Butler performed numerous coordination meetings with
the City's Public Works, Building, and Parks & Recreation Departments during the construction of
OCWD's Groundwater Storage Program. The Program Included eight (8) wells within the OC
groundwater basin, two of which were located in the City of Santa Ana.
Team Member Firm
Butler and ON -SITE Technical Services, Inc. have a 14-year working relationship on major water
capital improvement projects for Orange County Water District (OCWD), Metropolitan Water District
(MIWD), West Basin Municipal Water District (WBMWD), and San Diego County Water Authority
(SDCWA). Butler and ON -SITE have completed 15 major projects and numerous operation
upgrades for SDCWA and WBMWD. The most recent pump station project that was performed as a
team was OCWD's $20.5 million Burris Pump Station Project —Phase 2. ON-SITE's domestic end
international expertise in the inspection and testing of equipment is unmatched. They conduct quality
assurance inspection services on structural steel, pump stations, recycled water facilities, pipelines,
and engineered equipment manufactured at various domestic and international facilities on a daily
basis.
20A-43
6PT{ER
Cky of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. 16-04g
Unique Team Features
• Professional Relationship with the Design Team--Butier has developed a strong working
history with the Designer of Record. Butler and Tetra Tech —specifically, Mr. Tom Epperson —
have nearly 25 years of project history. Our firm has provided CM and inspection services on
several large, multi -phase projects designed by Tetra Tech, including the City of Tustin's
Rawlings Reservoir Replacement and City of Anaheim's Noh€ Canyon Water Storage Tank
projects. In addition, our firms recently worked together on OCW D's Burris Pump Station
Project —Phase II. Our long-standing relationship with Tetra Tech and Mr. Epperson will
make the development of our management approach more efficient and cost effective.
• IT Infrastructure and Project Documentation —Butler will provide a sophisticated IT
infrastructure. This web -based platform allows project information to be disseminated via the
internet using Procoro as a cloud -based construction project management software. The
program affords the project team with 2417 visibility into project status and a centralized,
comprehensive platform to manage all vital project data. The platform will allow us to create
"dashboards" specific to the user. This will allow the City to quickly access the project record for
key metrics and provide near real time updates of project progress,
• Extensive Experience in the Analysis and Defense of Contractor Claims—Butier's senior
staff has been responsible for the administration and defense of complex construction claims.
The firm's focus in water gives us a specific case history that aligns CM practices with the type of
issues encountered on projects of this size and complexity.
• Local Market Knowledge —The Butler team will provide unmatched cost control and estimating
services. The firm's strong relationship with the Southern California construction community
allows us to provide market price cost estimates. WE) also have the ability to survey local
contractors on the current market environment. This provides our clients with an assessment of
the best time to release a project for bidding.
The construction management team will be managed out of Butler's corporate office located at
17822 E. 171h Street, Suite 404: Tustin, CA. We appreciate the opportunity to meet the City's project
challenges with our most experienced personnel, and are confident that we have assembled a team
that will serve the best interests of all project participants. If you have any questions regarding our
proposal, please direct them to me for clarification at (714) 832-7222,
Respectfully Yours,
HUTtER Engineering, Inc,
Construction
/Managers, ConsultingEm'neer
6
Mark M. Butler, Jr.
Vice PresidenUCFO
A. COVER LETTER
20A-44
20A-45
Section S. Firm and Team Experience
Butler Engineering, Inc.
Butler Engineering Inc.'s focus as a firm is to
provide third -party construction management
services, a commitment we made to our
clients 42 years ago. Butler Is a Southern
California -based firm that services public
agencies, special districts, and the private
sector in the delivery of heavy civil
infrastructure. Our project expertise is in pump
stations, small and large diameter pipelines,
Flow control facilities, water production wells,
water/wastewater treatment facilities,
reservoirs, and water quality laboratories.
Representative clients include, but are not
limited to, the following:
■ Chino Basin DesalterAuthority
• Cities of Tustin, Anaheim, San Juan
Capistrano, Newport Beach, Huntington
Beach, Carlsbad, Escondido, and Vista
• County of Orange
• East Orange County Municipal Water District
• Irvine Ranch Water District
• Mesa Water District
• Metropolitan Water District of S. California
■ Orange County Sanitation District
• Orange County Water District
• San Bernardino Valley MWD
• San Diego County Water Authority
• Santa Margarita Water District
• South Coast Water District
■ South Orange County Wastewater Authority
• Water Replenishment District of S. California
■ West Basin Municipal Water District
Key Personnel
Butler Engineering, Inc.'s team consists of 35
skilled project managers, schedulers,
estimators, and inspectors who have
successfully managed water/wastewater
treatment, storage, and transmission projects
throughout Southern California The
Construction Management Team is a key link
to a successful project. By having the Butler
Team serve the City as a single -source of
responsibility, the CM and Inspection activities
will be well coordinated and delivered
efficiently. In addition to our licensed
professional engineers, our field engineering
staff possess certifications from the following
organizations:
• American Concrete Institute (Field Testing
Technicians)
• American Welding Society(Certified Welding
Inspectors)
• International Code Council (Reinforced
Concrete, Prestressed Concrete, Structural
Masonry, Soils, Spray -Applied Fireproofing,
Structural Steel And Bolting, Structural
Welding, Electrical)
■ NACE International (Level 1, 2 and 3 Certified
Coating Inspectors)
• Post Tension Institute (Field Technicians)
Approach to Managing Personnel
We propose to approach this project with a
spirit of partnership. This enables us to
combine the knowledge, ideas, and talents of
your staff with our construction administration
experience. Our core team will be
supplemented by as -needed technical and
administrative resources provided by Butler.
Butler's CM and inspection responsibilities are
handled by the project team member best
experienced to provide the needed service.
Butler does not assign inspection staff to
perform project document controls; rather,
inspectors focus on implementing the QA/QC
program and reports required to document
daily activity. Likewise, all project
documentation and controls are the
responsibility of the Contract Administrator. All
projects have a Project Manager assigned to
monitor project field staff performance.
Following this formula is critical for the
Owner's defense in the event of project
claims. It is also more cost efficient by
matching staff skills to project needs.
The Project Director has full access to teams
of civil, mechanical, electrical, and structural
engineers, specialty consultants, and
inspectors through existing relationships and
teaming arrangements with local firms. The
CM Team is always vigilant during
preconstruction, construction, and close-out to
meticulously document project activities and
minimize contractor claims.
41 A A
{
\\
.
,u
fr«!$
- f
�
�
�
20A- 7
BUTEER
Conslrvellon Idonapere, famsr(m,p Cnglnaort
Mark M. Butier, Jr.
Project Director
Professional Summary
EDUCATION
Mr. Butler serves as Vice -President and Chief Financial Officer for Butler
MBA, Finance, university of
Engineering. His primary duties include functioning as the primary point of
California, Irvine, Graduate
contact between Butlerand its clients; contract management; sub -consultant
School of Management,
contract management; maintenance of Butler's project Information system;
1998
development of thefirm's field procedural manuals; and staff resource
Graduate Studies, Civil
management. Mr. Butler works closely with the field construction management
Engineering, Callomla state
staff to ensure all contract scope requirements are being fully Implemented. Mr.
University at Long Beach
Butler also serves as the firm's contact between the field construction
management stafflclient and the project public outreach effort, when necessary.
B.A., Economics, University
He has been responsible for generating, distributing, and presenting to
of southern California, 1987
numerous public boards and community associations dealing with the impact of
B.A., social Sciences,
construction activity on the local community.
University of Southern
Project Experience
California, 1987
Project Director, Mid -Basin Injection: Centennial Park Project; Santa
LICENSES I
Ana, CA; Orange County Water District (Est. Completion: 2018)—The
CERTIFICATIONS
Mid -Basin Injection project consists of the construction of the following: four
General Engineering
groundwater injection wells in below grade vaults; a monitoring well at the
Contractor, state of
Heritage Museum site; a purified recycled water injection supply pipeline
California, Class A 716863
approximately 5,000 feet long that connects to the District's existing
Registered Construction
Groundwater Replenishment System (GWRS) pipeline and crosses the Santa
Inspector, ACIA: Division I
Ana River; a backflush discharge pipeline approximately 4,000 feet long that
Engineering 5572
discharges to the Greenville -Banning Channel and Centennial Park Lake;
installation of submersible pumps within the four injection wells; replacement
YEARS WITH FIRM
of approximately 9.6 acres of paving within the Park; demolishing an existing
31 yea rs
City of Santa Ana restroom facility; and constructing two new buildings with
shared City and District uses. Butler is coordinating closely with the City of
AVAILABILITY
Santa Ana, Santa Ana Unified School District, Heritage Museum, and
As-NGeded
state and federal agencies,
Project Director, Edinger Avenue Well —Phase 11 Equipping Project; City
of Tustin, Public Works (Estimated Completion: 2016; Value:
$4,103,650)—Butier is providing construction management and inspection
services for the Edinger Avenue Well - Phase II Equipping Project.
Construction of the building and equipping of the pump includes installation of
a 225 LF of 12-inch diameter CML ductile iron pipe discharge water line;
connection to 12-inch ductile iron watermain; installation of 162 LF of 18-inch
diameter C-905 drain line; connection to the existing storm drain; placement
of new onsite sewer manhole; installation of 76 LF of 8-inch diameter SDR 26
sewer lateral; and connection to existing OCSD sewer manhole. The scope of
nrork also includes the erection of 2.376 SF of CII block wall with a metal
roof building to enclose the well pump, electrical equipment and chlorine
room. The project is part of the City of Tustin's Water Services Division,
which is responsible for the production and safe delivery of domestic water to
more than 14,100 service connections through approximately 172 miles of
water mains. Butler staff coordinated with several agencies including the City
of Tustin, City of Santa Ana, and Caltrans,
KO -•
BUTLER
� uno7rnn Munepere, Cnnrufni¢,Enyfnnors
Mark M. Butler, Jr.
Project Director
Owner's Representative, Agua Hedionda Sewer Lift Station and
VistalCarlsbad Interceptor Sewer Replacement; Vista, CA; Cities of
Vista and Carlsbad (Completion: 2018; Value $64.2 million)•—Butier is
performing as the Owner's Representative for the construction of the sewer
lift station and interceptor sewer reaches. The project begins at the north
shore of the Agua Hedionda Lagoon in Carlsbad and extends a distance of
2.3 miles to the Encina Water Pollution Control Facility. Major project
components include the following: 1) Removal and replacement of the
existing wood trestle sewer support bridge across the lagoon with a new steel
support bridge. The existing 42-inch diameter sewer pipe along the bridge will
be replaced with a new 54-Inch pipe; 2) Removal and replacement of the
existing Ague Hedionda lift station. The new structure will house replacement
motors and pumps, as well as new system enhancements including an
emergency generator and bypass motors and pumps, an electrical control
building, and odor control facilities; and 3) Construction of a new 30-inch
diameter force main and a new 54-inch diameter gravity sewer line to
increase system capacity and reliability. The force main will provide 4,000
linear feet of high density polyethylene pipe parallel to an existing line and will
connect into 7,000 linear feet of new 54-inch diameter gravity sewer to be
constructed in Avenida Encinas from Cannon Road to the Encina Water
Pollution Control Facility.
Project Director, Orange County Groundwater Storage Program; Orange
County, CA (Orange County Water District) —The Orange County
Groundwater Storage Program consisted of equipping eight (8) municipal
water production wells in the cities of Santa Ana, Anaheim, Garden
Grove, Westminster, Cypress, Placentia, and Buena Park, The scope of work
for the wells included site work; installation of deep well turbine pump and
motors, electrical and instrumentation work, disinfection facilities, discharge
piping and valving, and off -site piping and valving, construction of concrete
block buildings, paving, drainage, fencing, and landscaping; and startup,
testing, and training. Mr. White coordinated with building officials, City
engineers, and public works departments to learn the organization's
operation, discover the hierarchy, and present solutions tailored to each of
the agency's needs.
Project Director, Burris Pump Station Project —Phase 2; Anaheim, CA;
Orange County Water District (Completion: 2016; Value: $20,585,400}--
Mr. Butler oversaw the construction management and inspection services
team for the Burris Pump Station Project — Phase 2, Phase 1 included the
construction of a portion of the building site and an earthen berm. The berm
allows the basin to remain in operation during final construction of the wet
well and pump station. Phase 2 consisted of the construction of a new 10,000
SF storm water pump station that uses four conventional vertical turbine
pumps installed in a circular wet well. The pump station also consists of new
mechanical, electrical, and control systems. An intake pipe was installed on
the slope of the embankment, connecting the new pumps to the intake invert.
20A-49
BUTTER
C rtSbbNlpa M1vxhhjn2, COnauI,LVJ knylnavrr
Casey Harris
Principal -in -Charge/ Senior Scheduler/ Claims
Professional Summary
EDUCATION
Mr. Harris has over 40 years of varied experience as a project/construction
B.S., construction
manager, resident engineer, and senior scheduler. As the on-sitelowner
Engineering, Arizona State
representative for major municipal, public agency, and special district capital
University, 1977
improvement projects, Mr. Harris has successfully managed the construction of
Graduate Studies, Arizona
multi-milllon dollar water and wastewater treatment facilities, pipelines, airports,
State university
solid waste landfills, water quality laboratories, and ports. Collectively, this
project experience represents over $700 million in construction costs.
YEARS WITH FIRM
Mr. Harris is an expert CPM scheduler, has established and implemented
37 years
effective change order control systems, negotiated change orders wRh
design/build contractors, performed routine shop drawing reviews, and
AVAILABILITY
20%
resolved contractor claims. As a Senior Scheduler, Mr. Harris conducts pre-
construction scheduling meetings with the owner and contractor to discuss the
scheduling specification requirements and format. The meeting facilitates
timely submittal, review, and approval of the contractor's baseline schedule
and helps to reduce the number of resubmiltals. Mr. Harris evaluates and
monitors the contractor's baseline schedule, weekly look -ahead schedules,
and provides monthly schedule updates, time impact analyses (TIAs),
schedule revisions, and as -built schedule submittals. He is also responsible for
updating the overall project schedule to reflect actual progress and changes.
He Identifies slippage of contract activities on the critical path, as well as time
sequence problems, early on so that the construction management team may
take corrective action.
Project Experience
Senior Scheduler, Mid -Basin Injection: Centennial Park Project; Santa
Ana, CA; Orange County Water District (Completion: 2018; Value: $23.2
million) —The Mid -Basin Injection project consists of the construction of the
following: four groundwater injection wells in below grade vaults; a monitoring
well at the Heritage Museum site; a purified recycled water injection supply
pipeline approximately 5,000 feet long that connects to the District's existing
Groundwater Replenishment System (GWRS) pipeline and crosses the Santa
Ana River; a backflush discharge pipeline approximately 4,000 feet long that
discharges to the Greenville -Banning Channel and Centennial Park Lake;
installation of submersible pumps within the four injection wells; replacement
of approximately 9.6 acres of paving within the Park; demolishing an existing
City of Santa Ana restroom facility; and constructing two new buildings with
shared City and District uses. Mr. Burce is coordinating closely with the City
of Santa Ana, Santa Ana Unified Sehoot District, Heritage Museum, and state
and federal agencies.
Constructability Review and Senior Scheduler, Burris Pump Station
Project —Phase 2; Anaheim, CA (Orange County Water District) —Mr.
Harris performed civil/structural design review for the Burris Pump Station
Project —Phase 2 as a part of Butier's construction management agreement
with OCW D. The scope of services included report and data review and
Phase 2 Design Review at the 75% design stage. Mr. Harris also provided
schedule review services under the construction phase of the Burris Pump
20A-50
BUT1ER
Cerpp,rciyu Ma„g„�, C-ibbiny Enyu,cen
Casey Harris
Principal -In -Charge / Senior Scheduler/ Claims
Station Project, Phase 2 consisted of the construction of a new 10,000 SF storm
water pump station that uses four conventional vertical turbine pumps installed in
a circular wet well. The pump station also consists of new mechanical, electrical,
and control systems. An Intake pipe was Installed on the slope of the
embankment, connecting the new pumps to the intake Invert.
Senior Scheduler, Chino It Desalter Concentrate Reduction Facility;
Jurupa Valley, CA; Chino Basin Desalter Authority (Completion. 2016—
Value: $46.6 miilion) --Senior Scheduler for the CRF groundwater treatment
facility. Both ion exchange (IX) and RO treatment trains are used to treat
brackish groundwater from eight welts that also have elevated nitrate
concentrations. The project scope included construction of new softening,
clarification, filtration, and secondary RO (SRO) treatment and solids
dewaterfng and storage; installation of a new decarbonator; Installation of a
now transfer pump with motor with associated VFD and motor controls and
discharge piping and valves; installation of new cartridge filters; modification
of the existing sulfuric acid chemical system; modification of the existing
threshold Inhibitor chemical system; and site modifications. Including fencing
and gates, yard piping, and storm drain replacement.
Senior Scheduler, Carlsbad 50 MGD Seawater Reverse Osmosis
Desalinatlon Plant and 10-Mlle Conveyance Pipeline; Carlsbad, CA;
Poseidon Water (Completion: 1212015; Value: $697 mtllton)—Mr. Harris
provided scheduling services for the new construction of a 50 MGD seawater
reverse osmosis desalination plant at the Enclna Power Station located In
Carlsbad, CA. The scope also included the construction of a 2.5 million gallon
product water storage tank; product pump station; and conveyance pipeline to
deliver the drinking water produced by the Project to water utilities and
municipalities in San Diego County. The 10-mile, 54-inch diameter pipeline was
constructed under Interstate 5 Highway and a railroad using a jack and bore
tunnel method. Butier staff coordinated closely with the City of Carlsbad,
SDCWA, SDG&E, Poseidon and the Coastal Commission during the
construction of the tunnel option across Macario Canyon. The pipeline
alignment includes over 6,000 feet of tunnels performed by four different
tunneling subcontractors. One of the tunnels is over 1,700 linear feet, 30 feet
below sea level, and required a vertical shaft over 00 feet In height.
Senior SchedulerlRisk Analysis, Groundwater Reliability Improvement
Program (GRIP) Advanced Water Treatment Facility Project; Water
Replenishment District of Southem California (Value: $100 million) —Mr.
Harris is providing scheduling and risk analysis services as a part of GHD's
Owner's Agent/Owner's Engineer team for the GRIP Advanced Water
Treatment Facility Project. As a part of the GRIP Program, an advanced
water treatment facility is being constructed to purify 10.000 acre feet (3.25
billion gallons) of tertiary treated (recycled) water annually, The GRIP AWTF
is being built on a 5.2 acre property in the City of Pico Rivera, adjacent to the
San Gabriel River. The GRIP AWTF will include the following treatment
processes: automatic strainer; microflltratlon (MF) and reverse osmosis (RO)
followed by ultraviolet advanced oxidation (UVAO); cartridge filtration;
decarbonation; and pH adjustmenticorrosivity stabilization.
20A-51
HUTIER
CmMdwNlwr Men,gara. C¢nnJlln� Gngu,nan
Kyle Morgheim, P.E.
Project Manager
Professional Summary
EDUCATION
Mr. Kyle Morgheim is a professional engineer with over 15 years of
M.6,A. and M.S., Finance,
comprehensive experience in civil engineering and project and construction
University of Denver,
Colorado, 2010
management, including resource allocation and cost! schedule management
of major projects. He has extensive experience In providing PM and CM
as., civil Engineering,
services for water / wastewater treatment facilities, pump stations, reservoirs,
University or Nebraska,
pipelines, transportation, and land development projects from design through
Lincoln, 2003
construction phases.
LICENSES !
Mr. Morghalm has strong decision -making, leadership, communication, and
CERTIFICATIONS
technical skills, He Is extremely focused on Identifying potential problem
Registered Professional
areas, minimizing issues, and formulating and executing competent solutions.
Engineer (Civil), State
te oof
His project management responsibilities typically include coordinating with
California, No. 71736
agencies and stakeholders; scheduling; preparing and reviewing cost
9
estimates; managing the construction project field office and personnel; full
SOFTWARE
contract administration; leading project meetings; responding to contractor
PROFICIENCY
correspondence; negotiating and recommending monthly progress payments;
AutcCAD Land Desktop
maintaining a daily diary of events; preparing monthly project status reports, -
Development
and monitoring as-buflf drawings.
Agtek 3-D Modeling
Project Experience
HEC-HMS
Storm CAD
Assistant Resident Engineer, Rawlings Reservoir Repair and
Flowmaster
Replacement; Tustin, CA; City of Tustin (Completion: 2013; Value: $12.5
A,E.s, (California Hydrology
million) —The City's former4 MG hopper bottom reservoirwas taken out of
Program)
service due to its age and deteriorating condition. After its decommissioning,
WSPG (California Hydraulic
the City proceeded with the design of two 3.0 MG prestressed circular
Modeling Program)
concrete tanks to replace the reservoir. Prior to bidding, Butler assisted the
City with solving construction access and temporary shoring issues. The
YEARS WITH FIRM
project originally required the construction of a tie -back retaining wall, which
e years
would have extended the project into an adjacent property. At the City's
direction, Butler performed a constructability review and proposed using a
AVAILABILITY
cantilevered shoring system, which would keep the project within the City's
50%
property line. In addition, Butler assisted the City in obtaining a temporary
construction easement from the adjacent landowner to the north. Use of this
undeveloped property provided the Project team with an access road down to
the bottom of the tank elevation, as well as laydown and stockpiling areas.
Resident Engineer, Chino Desalter Phase 3 Expansion Project; Norco,
CA (Chino Basin Desalter Authority) —The Chino Desafter Phase 3
Expansion Project included the drilling of six (6) additional wells, new raw
water and product water pipelines, and expansion of the Chino Desalter's
treatment facilities. The scope of the Expansion increased desalter
groundwater pumping from the lower Chino Basin to 40,000 acre-feet per
year (AF/yr) and provides at least 10 MGD of additional product water
capacity. The treatment processes include reverse osmosis (RO), ion
exchange (IC), and air stripping.
20A-52
BUTNER
C rmn:on Managnra. smlrna Crry�rvaz,n
Kyle Morghelm, P.E.
Project Manager
Resident Engineer, Milliken 1010 Zone Pump Station; Chino, CA; Chino
Basin Desalter Authority (Completion: 2014; Value: $1.3 million) —The
scope of work includes the following potable water improvements: construction
of a ventilated CMU Pump Station, 198 LF of 16-Inch discharge piping and
interconnection to an existing 30-inch transmission line, and 24-inch suction
piping and interconnection to an existing 24-inch transmission line; installation of
3 vertical turbine pumps and associated piping, fittings, valves, appurtenances,
electrical instrumentation, and controls; and site improvements, including grading
and paving and restoration of existing improvements.
Technical Advisor, Moffett Drive and Park Avenue Roadway Extension
Project; City of Tustin, Public Works (Completion: 2016; Value: $14.5
million) —Mr. Morgheim provided construction management services for the
Moffett Drive and Park Avenue Extension Roadway Project, The project included
the removal and compaction of 250,000 CY of removal and compaction of soil;
275,000 SF of subgrade preparation and street fine grading; and 4,000 LF of
reinforced concrete box storm drain. The project also includes the construction of
street improvements, paving, utility installation, signing, traffic installation,
landscaping, and irrigation. Approximately 15,000 CY of concrete was used to
construct the reinforced concrete box storm drain, which includes lateral storm
drains with catch basins. Major dewatering efforts and shoring under the
Jamboree Bridge at Moffett Drive presented significant challenges that Butler
coordinated with success,
Technical Advisor, Peter's Canyon Channel and Moffett Drive Bridge
Construction and Street Improvements Project; City of Tustin, Public
Works (Estimated Completion: 2018)—Mr. Morgheim is providing
construction management services for the Peter's Canyon Channel and
Moffett Drive Bridge Construction and Street Improvements Project. The
scope of work consists of removing the existing bridge and constructing a
single span cast -in -place concrete box girder bridge approximately 108 feet in
length and 73.25 feet in width. The work also includes an architectural steel
arch on each side of the bridge. In addition to the construction of bridge, the
work shall include, but not limited to construction of barriers, sidewalks, wing -
walls, foundation, railings, structure excavation, backfill, drainage, and bridge
lighting. The channel work includes demolition, widening, and relining
approximately 5,000 feet of the existing channel within the Cities of Tustin
and Irvine. The channel scope of work also includes construction of new
storm drain lines, extension of existing storm drain lines, and road
undercrossings.
Technical Support, Armstrong Avenue & Warner Avenue Extension
Phase 2 Street Improvements, City of Tustin (Completion 2015; Value
$13.2 million) ---Mr. Morgheim provided technical support services for the
Armstrong/Warner Ave. Extension Phase 2 project. The scope of work
included roadway improvements, traffic signals, landscape, dry utility,
waterline, and reclaimed water and sewer line construction on the following
streets: Armstrong Avenue Extension from Warner Avenue to Barranca
Parkway and Warner Avenue Extension from Red Hill Avenue to Tustin
Ranch Road.
20A-53
BUTIER
{:msvun.'"n M1id,a�pa�. Conruinny En yrnaem
Vladimir Burce, P.E.
Technical Advisor
EDUCATION
Professional Summary
Ms., construction
Management, University of
Mr, Burce is a registered civil engineer with over 23 ears of professional
9 9� Y
Southern California, Los
experience In project and construction management, Including planning,
Angeles, California, 2003
design, resource allocation, and costtschedule management of major projects.
He has extensive experience in providing PM and CM services for
Bs., Civil Engineering,
stateono, Polytechnic
water/wastewater treatment facilities, wells, um stations, storm water
University
university -Pomona,
detention / retentions stems, transportation, parking structures, industrial,
y P P 9
California, 1995
educational, residential, and land development projects during the design and
construction phases.
LICENSES/
CERTIFICATIONS
Mr. Burce has diverse project experience in public works and real estate
P 1 P
professional Civu Engineer:
development. This background provides him with an In-depth understanding
California (CE59405)
of civil engineering disciplines. His professional responsibilities have ranged
from feasibility study, geotechnical, civil design, complex drainage design and
AFFILIATIONS
regulatory requirements, technical spec'Ifications development and preparation
Woject Management Institute
of bid documents, designlconstructability review, schedule preparation, field
Building industry Association,
implementation and supervision, and construction management.
Orange county chapter
Relevant Experience
Urban Land institute
Resident Engineer, Mid -Basin Injection: Centennial Park Project; Santa
YEARS WITH FIRM
Ana, CA; Orange County Water District (Completion: 2018; Value: $23.2
3 years
million) --The Mid -Basin Injection project consists of the construction of the
following: four groundwater injection wells in below grade vaults; a monitoring
AVAILABILITY
well at the Heritage Museum site; a purified recycled water injection supply
As Needed
pipeline approximately 5,000 feet long that connects to the District's existing
Groundwater Replenishment System (GW RS) pipeline and crosses the Santa
Ana River; a backflush discharge pipeline approximately 4,000 feet long that
discharges to the Greenville -Banning Channel and Centennial Park Lake;
Installation of submersible pumps within the four Injection wells; replacement
of approximately 9.6 acres of paving within the Park; demolishing an existing
City of Santa Ana restroom facility; and constructing two new buildings with
shared City and District uses. Mr. Burce is coordinating closely with the City
of Santa Ana, Santa Ana Unified School District, Heritage Museum, and state
and federal agencies.
Resident Engineer, Chino II Well Field Equipping of Raw Water Wells
Nos. 11-10 and 11.11; Eastvale and Ontario, CA; (Chino Basin Desalter
Authority (Completion: 2017; Value: $3.8 milllon)—Mr. Burce provided
resident engineering services for Well Nos. II-10 and II-11. Well II-10 is
located on CDA property in the City of Eastvale within Riverside County. Well
II-11 (Lot "A") is located on CDA property in the City of Ontario within San
Bernardino County. The scope of work included equipping of two water wells
including, but not limited to, the following: construction of 168" W x 41'4"L x
16"H reinforced masonry block building; Installation of 3,300 gpm vertical
turbine stainless steel pumping unit and 600 hp premium efficiency motor,
16-inch diameter epoxy lined steel discharge header pipe, 12-inch diameter
pump to waste piping, 16-inch diameter flow meter, site pressure piping and
tubing, valves, taps and Corp stops, pressure gages, 16-inch diameter C905
PVC underground discharge pipeline, and connection to existing 24-inch
20A-54
HUTIER
Garc�nreHrn Mau»ycrc Cennil�lny, Fnglnaer:
Vladimir Burce, P.E.
Technicai Advisor
diameter discharge pipeline; and on- and off -site electrical, including power,
control, lighting, underground electrical duct, instrumentation equipment and
panels, switchgear, VFD and motor control center equipment, and installation
of SCADA equipment. The project included close coordination with the City of
Ontario, City of Eastvale, County of San Bernardino County Flood Control
District, Southern California Edison, and local businesses and residents,
Resident Engineer, Chino Desalter Reliability Project; Chino, CA; Chino
Basin Desalter Authority (Completion: October 2017; Value: $3.8
million)—Butier provided CM and inspection services for the Chino I Reliability
Project located at the existing Chino I Desaiter. The project scope included the
following; new building built on to the existing Chino I Desalter facility; new RO
train tied into the existing feed water, permeate, concentrate, and CIP piping
manifolds; modification of the existing sulfuric acid chemical system by
replacing two existing metering pumps and furnishing and installing two
metering pumps; trench overflow constructed and connected below the air gap
that conveys water to the brine line; slurry seal all existing and new asphalt
surfaces; coating of the exterior of the existing process building to match the
new process building exterior coating system; and coating of all existing
trenches.
Construction Manager, Chino II Desalter Concentrate Reduction
Facility; Jurupa Valley, CA; Chino Basin Desalter Authority
(Completion: 2016—Value: $46.6 million)—Butier provided CM and
inspection services for the CRF groundwater treatment facility. Both ion
exchange (IX) and RO treatment trains are used to treat brackish
groundwater from eight wells that also have elevated nitrate concentrations.
The project scope included construction of new softening, clarification,
filtration, and secondary RO (SRO) treatment and solids dewatering and
storage; installation of a new deearbonator; installation of a new transfer
pump with motor with associated VFD and motor controls and discharge
piping and valves; installation of new cartridge filters; modification of the
existing sulfuric acid chemical system; modification of the existing threshold
inhibitor chemical system; and site modifications, including fencing and gates,
yard piping, and storm drain replacement.
20A-55
BUTTER
LonShpHlnn 3Rfmgvn. 4'nnxolOng GnpH,eece
EDUCATION
Construction Apprenticeship,
Rio Hondo College; Whittier,
CA, 1981
Constructior Management,
Pasadena College;
Pasadena, CA, 1978
LICENSES
CERTIFICATIONS
ICC Reinforced Concrete
Special Inspector
No.5057063
Exp. 01 /31/2019
Amencan Concrete Institute
Field Testing Technician -
Grade I Certification
Exp. 11/1512019
YEARS WITH FIRM
18 yea rs
AVAILABILITY
loom
Bart Crawford
Lead Inspector
Professional Summary
Mr. Bart Crawford came to Butler from the Metropolitan Water District, Los
Angeles, where he spent over five years as an inspector. His heavy
construction experience and knowledge of methods and equipment have
facilitated an expertise in concrete and steel structures, various types of form
work, bridge construction, controlled blasting, pre -stress, earth work, roadway
improvements, rock bolting, reinforcing steel, tunneling, metal decking,
architecturallinterior finish. As an inspector for Butior, Mr. Crawford works
primarily on water capital improvement projects, including water and
wastewater treatment plants, pipelines, pump stations, and reservoirs. His
inspection duties typically include utility/agency coordination, submittals, RFI
and field memo responses, interpretation of drawings and general
correspondence with design engineer. His background includes 18 years of
union carpentry.
Mr. Crawford provides both pipeline encasement construction and pipeline
inspection experience to water projects. Pipeline work has Involved piping for
filtration plants, domestic water lines and reservoirs. Pipe material has
included CML&C and ductile iron Experience has also included flow measure
and flow metering for 144" and 66" lines, and tunneling.
Project Experience
Lead Inspector, Groundwater Reliability Improvement Project (GRIP)
Advanced Water Treatment Facility Project; Water Replenishment
District of Southern California (Value: $100 million) —Mr. Crawford is
providing field inspection services as a part of GHD's Owner's Agent/Owner's
Engineer team for the GRIP Advanced Water Treatment Facility Project. As a
part of the GRIP Program, an advanced water treatment facility is being
constructed to purify 10,000 acre feet (3,25 billion gallons) of tertiary treated
(recycled) water annually. The GRIP AWTF is being built on a 5.2 acre
property in the City of Pico Rivera, adjacent to the San Gabriel River. The
GRIP AWTF will include the following treatment processes: automatic
strainer; microfiltration (Ml and reverse osmosis (RO) followed by ultraviolet
advanced oxidation (UVAO); cartridge filtration; decarbonation; and pH
adjustment(corrosivity stabilization.
Lead Inspector, Chino Creek Well Field Equipping -Wells 1-11 1-17, and I-
18; Chino, CA; Chino Basin Desalter Authority (Completion: 2013;
Value: $1.5 million) —Provided inspection services for the Equipping of
Chino Creek Well Field Wells 1-16, 1-17 & 1-18 project. The groundwater wells
were equipped as part of the CDA Phase 3 Expansion Project. In addition to
well equipping, the project Included the installation of 625 LF of 8" diameter
HDPE corrugated storm drain pipe and the grading and paving of the well
sites. Coordination with other projects was required, including connection of
well discharge lines to the Chino Creek Well Field Raw Water Pipeline. The
project also involved coordination with the City of Chino to secure the
required permits.
20A-56
BUTTER
Bart Crawford
Lead Inspector
Lead Inspector, Edward C. Little Water Recycling Facility Phase V
Design -Build Expansion; Ell Segundo, CA (West Basin Municipal Water
District) —Provided inspection services for the Phase V Design -Build project.
West Basin expanded Title 22, Barrier Water and Low Pressure Bailer Feed
water treatment processes. The Phase V project involved expanding the Title
22 pretreatment capacity by 10 MGD to achieve a total treatment capacity of
40 MGD, along with expanding the Barrier Water production from 12.5 MGD
to 17.5 MGD and the Low Pressure Boller Feed water production from 1.7 to
2.2 MGD to serve Single -Pass RO water to NRG's El Segundo Power Plant,
The Phase V project addressed numerous capacity expansion and treatment
process upgrades. The project included Ozone-Microfiltration Pretreatment
Process; West Coast Barrier; El Segundo Power -Low Pressure Boiler Feed
Water; Title 22 Facility -High Rate Clarifier Expansion; Title 22 Pump Station;
Chemical Facilities; and miscellaneous civil work.
Lead Inspector, Chino It Desalter Concentrate Reduction Facility;
Jurupa Valley, CA; Chino Basin Desalter Authority (Value: $46.6 million;
Completion: 2015E-Mr. Crawford was the Lead Inspector for the CRF
groundwater treatment facility, which is one of two plants managed by the
Chino Basin Desalter Authority. Both ion exchange (IX) and reverse osmosis
(RO) treatment trains are used to treat brackish groundwater from eight wells
that also have elevated nitrate concentrations. The project scope included
construction of new softening, clarification, filtration, and secondary RO
(SRO) treatment and solids dewatering and storage; installation of a new
decarbonator; installation of a new transfer pump with motor with associated
VFD and motor controls and discharge piping and vaives; installation of new
cartridge filters; modification of the existing sulfuric acid chemical system;
modification of the existing threshold inhibitor chemical system; and site
modifications, including new fencing and gates, yard piping, and storm drain
replacement.
Resident Engineer, Chino Desalter Reliability Project; Chino, CA; Chino
Basin Desalter Authority (Completion. October 2017; Value: $3.8
million)—Butier provided CM and Inspection services for the Chino I Reliability
Project located at the existing Chino I Desalter. The project scope included the
following: new building built on to the existing Chino I Desalter facility; new RO
train tied into the existing feed water, permeate, concentrate, and CIP piping
manifolds; modification of the existing sulfuric acid chemical system by
replacing two existing metering pumps and furnishing and installing two
metering pumps; trench overflow constructed and connected below the air gap
that conveys water to the brine line; slurry seal all existing and new asphalt
surfaces; coating of the exterior of the existing process building to match the
new process building exterior coating system; and coating of all existing
trenches.
20A-57
BUTIER
Gonttmrnnn Ndnnymy. FoneulYep Enylnaerx
Bryan Wilson
Contract Administrator
Professional Summary
EDUCATION
Mr. Wilson has over 18 years of construction estimating, cost review,
B.S., Engineering
inspection, and engineering management experience. He has analyzed and
Technology —Construction,
reviewed cost estimates for hundreds of projects ranging from underground
California State Polytechnic
pipelines to high-rise office buildings. These projects involved the training and
University, Pomona, 2000
management of engineers and estimators to determine and track construction
AREAS OF
costs and activities. Mr. Wilson's detailed estimating experience covers all
aspects of building and heavy/civil design and construction, including
EXPERTISE
earthwork, structural, mechanical, electrical, and plumbing components. He
CPM Project Scheduling
has conducted numerous physical inspections in order to verify the accuracy
Cost Control
and scope of quantities and cost estimates derived from construction
Quality control
blueprints. He also has experience in organizing and tracking requests for
Construction a Specialty
information (RFI), project scheduling, negotiating construction change orders,
Trade Estimating
and value engineering analyses.
Cost valuation
Mr. Wilson's range of professional experience Includes working for and with
Value Engineering
construction management firms, general contractors, architecture and
engineering firms, and public accounting and consulting firms. He has also
Construction Inspections
provided asset valuation and classification consulting services to real estate
Surveying
appraisers and construction companies. He has prepared construction cost
Structural Design
estimate studies for federal tax depreciation classification and successfully
Change order Negotiation
defended these studies when audited by the Internal Revenue Service,
Cost Segregation Studies
Project Experience
Project Organization
Engineering Management
Field Engineer/Document Control Specialist, Mid -Basin Injection:
Centennial Park Project; Santa Ana, CA; Orange County Water District
owner Presentations
(Completion: 2018; Value: $23.2 million) —Mr. Wilson is performing as the
Project Review
Document Control Specialist for the Mid -Basin Injection project, which
consists of the construction of the following: four groundwater injection wells
YEARS WITH FIRM
in below grade vaults, including all related appurtenances within Centennial
4yea ra
Park; a monitoring well at the Heritage Museum site; a purified recycled water
injection supply pipeline approximately 5,000 feet long that connects to the
AVAILABILITY
District's existing Groundwater Replenishment System (GWRS) pipeline and
20%
crosses the Santa Ana River; a backf€ush discharge pipeline approximately
4,000 feet long that discharges to the Greenville -Banning Channel and
Centennial Park Lake; installation of submersible pumps within the four
injection wells; replacement of approximately 9.6 acres of paving within the
Park; demolishing an existing City of Santa Ana restroom facility; and
constructing two new buildings with shared City and District uses. Mr. Burce
is coordinating closely with the City of Santa Ana, Santa Ana Unified School
District, Heritage Museum, and state and federal agencies.
Field Engineer/Assistant Resident Engineer, Santa Ana River Enhanced
Recharge Phase 1A Sedimentation Basin and Pipeline; San Bernardino
Valley Municipal Water District (Est. Completion: 2018; Value: $14
million)---Butier (Prime) and GHD (Sub) are providing design, engineering,
and CM services for the SARER Phase 1A project, which is located in an
undeveloped area near the upper reaches of the Santa Ana River. A new
diversion structure and inlet channel is being constructed to divert water to
20A-58
BUTIER
Q: VnNYxnNanagrca, [anculNny Enpinc�,n
Bryan Wilson
Contract Administrator
the new sedimentation basis and the Water Conservation District Canal. The
new sedimentation basin will be 200-foot wide and 600-foot long and
approximately 10 feet deep, The new pipeline will consist of approximately
1,900 linear feet of 96-inch diameter CMLC welded steel pipe and 1,300
linear feet of 78-inch diameter CMLC welded steel pipe connecting the new
sedimentation basin and the existing 78-inch diameter SBVMWD Foothill
Pipeline.
Field Engineer/Document Control Specialist, Vista Verde Reservoir
Replacement Project —Phase II; Vista, CA; City of Escondido
(Completion: 2013; Value $9.5 million) --Mr. Wilson is providing field
engineering and document control services for the replacement of the Vista
Verde Reservoir. The existing 750,000-gallon steel reservoir, which suffered
from internal corrosion, is being replaced with two 1 million -gallon Type I pre-
stressed concrete reservoirs that will be partially buried. The extra capacity
for water storage will allow additional development in the area. The scope of
work also includes new interconnecting piping, valve structure, grading,
paving, site improvements, landscaping, electrical, instrumentation, and
incidentals fora complete and usable facility. The pipeline portion of the
project will extend from the existing pump station along Vista Verde Way, up
to the Vista Verde Way cul-de-sac (approximately 6,000 Linear Feet). It
includes inlet, outlet and drain line up the hill to the vault structure.
Field Engineer/Document Controls, Wineville Extension Recycled Water
Pipeline —Segment A; Inland Empire Utilities Agency (Completion:
September 2015; Value: $10,609,000)—Butier provided construction
management, contract administration, and inspection services for the
construction of the Wineville Extension Recycled Water Pipeline, Segment A is
located in the Cities of Ontario and Fontana and within the San Bernardino
Flood Control District property. It begins along East Airport Drive beside the
east side of the Day Creek Channel continuing to Jurupa Avenue, south along
Wineville Avenue to Francis Street, east along Francis Street and Marlay
Avenue just east of Mulberry Avenue, The construction consisted of the
following: 5,464-1 of 24-inch pipe; 13,500-1 of 36-inch pipe; isolating valves;
air release and vacuum valve assemblies; and blow -off assemblies. Mr. Wilson
managed all financial aspects of project construction, including payment
application review and processing, change order drafting and approval
recommendation, construction cost estimating, and overall project budget
implementation and tracking. Additionally, Mr, Wilson conducted weekly
project meetings, reviewed and processed submittals and RFIs, performed
field inspections, and coordinated the resolution of construction and contractual
issues.
20A-59
20A-60
$04
Section C. Understanding of Need
PROJECT UNDERSTANDING
Based on our review of the project request for
proposal and the associated plans and
specifications, we understand that the San
Lorenzo Sewage Lift Station Project will consist
of construction of the following:
• Lift station —below ground dry and wet wells
Aboveground CMU block building
• Three (3) 15 hp dry pit sewage pumps
• Piping, fittings, valves, flow meter, in -line
grinders, rail and hoist system
• HVAC, ventilation and ducting
• Electrical and instrumentation
• Site grading and improvements
• 560 (LF) of 15" gravity sewer pipe
• 190 (LF) of 12" gravity sewer pipe
• 545 (LF) of 10" force main
• Sewer manholes and appurtenances
• Abandonment of existing Segerstrom Lift
Station
The anticipated start of construction is late fall
2018 with a duration of 14 months. The
estimated cost of construction is $6 million.
PROJECT APPROACH
The Butler Team will use a project control
system consisting of the following four
elements that will provide quality
assurance/quality control procedures and
guidelines in the execution of the San Lorenzo
Sewage Lift Station Project.
The CM Team's ability to monitor and manage
the Contractor's performance will be critical to
minimizing problems during construction and
potential claims. Contractor schedule
requirements will include substantial
completion deadlines and interim and final
completion dates. The construction progress
will be evaluated based on approved,
resource -loaded CPM schedules
(Primavera P6). The Contractor will be
required to submit GPM schedules to the City
for acceptance in addition to timely, detailed
status Information as the work progresses.
The Butler Team will evaluate the Contractor's
actual performance by comparing actual
qualities completed versus planned.
Anticipated work to be accomplished will be
reviewed based on a two -week "look ahead"
schedule updated weekly by the Contractor.
Available information must be evaluated for
schedule exceptions, available contractual
options, and corrective actions required by the
Contractor.
The CM Team will address schedule
variances with the Contractor at weekly
progress meetings. The CM Team will
evaluate each variance, its cause and
possible corrective actions, and require the
Contractor to provide an action plan to correct
unsatisfactory variances. If a satisfactory
resolution is not achieved and the Contractor
falls significantly behind schedule, the CM
Team will require the Contractor to submit a
recovery plan. The plan should address
mitigation efforts such as additional crews,
additional shifts, or developing work -around
schedules that move the delayed activity off the
critical path so that its completion will not affect
critical milestones.
The Butler Team will develop a QA/QC Plan for
the San Lorenzo Sewage Lift Station Project.
The plan will reflect a set of objectives defined
by City staff and assigned CM and field
Inspection personnel. The QAIQC Plan will be
organized accordingly:
Organization and Responsibility;
• Execution and Schedule;
• Procedural Requirements;
• Requirements for Consultants; and
• Project Quality Management Audits
20A-61
These sections define requirements and
procedures for checking, reviewing, distributing,
tracking, and controlling documents for QA/QC.
The project specific QA1OC Plan will be
submitted and reviewed by the City prior to
submittal of other project deliverables. The
individuals performing QA/QC reviews will be
clearly indicated in the project organization
chart. Deliverables will contain a statement that
the information contained In the submittal has
been quality control checked in accordance with
the QAiQC Plan.
Quality Assurance is the confirmation
process that all procedures directing the work
have been developed and followed and any
corrective actions required have been
implemented. Procedures or actions to be
confirmed include:
Construction management plan;
• Training of staff in QA/QC requirements;
• Submittal process plan;
• Document control plan;
Identification of City approvals at
appropriate milestones;
• Control of testing to determine validity and
accuracy of data collected in the field;
• Calibration and testing of equipment;
• Identification of the need for corrective
action; and
• Audit to verify compliance with the QA/QC
Plan,
Quality Control is the actual checking and
validation of the inputs and outputs of the
work. Activities to be verified for the work
include the following:
• Review by quality control team;
• Identification and compliance with
applicable codes, ordinances, permits,
environmental requirements, etc.;
• Review input data and check calculations;
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. 16-049
• Review drawings, specifications, technical
reports, memos, meeting minutes;
• Perform constructability, operability,
maintainability, and usability reviews; and
• Review design for compliance with safety
standards.
The Principal -In -Charge and Project Manager
will prepare a specific CM Communications
Manual for the San Lorenzo Sewage Lift
Station Project to be approved by the City.
The manual will Include project
correspondence and other forms of
communication In accordance with the City's
documentforrnatting standards. The manual
will integrate the interdependent roles of the
City, Construction Manager, Design Engineer,
and the Contractor, through pre -construction,
mobilization, construction, and acceptance of
the phases of the work. The Communication
Manual will include the following:
Project Organization: Individual
assignments, responsibilities, phone
numbers, lines of communication, and
methods for interfacing with the City,
project stakeholders, and the Contractor.
Organization chart showing relationships
between the parties.
• Project Control. Description of cost,
schedule and document control systems.
• Communication Management:
Procedures for documenting
communications and correspondence;
distribution and/or routing lists; and
examples of all forms that the Contractor
will be required to use.
• Meeting/Notice Procedures:
Schedules, notices, agendas, reporting
procedures, documentation requirements,
and timely acceptance processes.
• QA/QC: Procedures, laboratory testing,
field-testing, coordination checks, and
HILITIER C. UNDERSTANDING OF NEED
20A-62
construction Inspection activities for all
project features, equipment and materials
• Document Control: Discussion of
Butler's cloud -based project management
document control system used to input
and track various reports and
correspondence between key parties
Contract Administration: Description of
control systems and procedures for
performing and
documenting
submittal reviews,
RFIs, change
orders, claims
management,
contract closeout
activities, and
other contract
administration
procedures.
• Records: The
CM will maintain
records of
inspections,
reports, and test
results received
from the
Contractor,
Design Engineer,
manufacturers,
and others,
erfor5
The Butler Team recommends utilizing
Procore—a cloud -based construction
project management solution —to organize,
manage and control project documentation.
The advantages of Procore include unlimited
users and storage, 2417 visibility into project
status, and a centralized, comprehensive
platform to manage vital project data. All
parties Involved have access to the system.
Each user can access the program via a
web browser on their computer or mobile
device using secure log -in information.
Procore is utilized to store, review, track, and
manage all project documents including
BI.ITIER
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. 18-049
construction drawings and specifications,
RFIs, submittals, transmittals, meeting
agendas and minutes, emails and
correspondence, progress photos, budgets,
schedule of values, payment applications,
change orders, daily inspection reports, final
punch lists, and point of contact information.
Additionally, Procore can be configured to
display the latest Primavera P6
construction
project schedule
and weather
information, both
current and forecast.
Automated emalls
can be generated by
the software program
to remind personnel
of required
documentation
reviews and other
project related tasks
that need attention.
Project
documentation is
continuously updated
and available always
to all involved
personnel, with prior
revisions stored for
reference, At the conclusion of the project,
project -related documentation is converted to
PDF format and distributed to the appropriate
parties.
SPECIAL CONCERNS I SUGGESTIONS
Butler has vetted special concerns that the
City should be made aware of. Table 1,
located on the following pages, provides a
summary of these concerns and suggestions.
C. UNDERSTANDING OF NEED
20A-63
Table 1. Special Concerns/ Suggestions
Schedule Control
Objective: Implement
proposed project according to
its schedule and any
constraints.
Quality Control
Objective: Follow QC
guidelines to minimize rework
that could result In schedule
delays.
Cost Control
Objective: Utilize and follow
cost control management
strategies to keep project
within budget.
Stakeholder Coordination
Objective: Be responsive to
project stakeholder
coordination requirements to
achieve a high confidence level
for project success.
Team Cohesiveness
Objective: Maintain a
streamlined, team that works
well together during CM and
inspection activities.
Constructability,
Objective: Engage an
experienced CM team to
perform constructability
reviews at critical design
milestones.
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. f 8-049
❑ Review Program Schedule during
pre -construction phase
q Conduct Schad ule Workshops
regarding project constraints with
stakeholders
❑ Follow proven Butler Cll plan
with experienced inspection staff.
❑ Document work activities and
distribute to CM members daily
❑ Ensure contractor redlines are up
to date on a weekly basis.
❑ Provide CM/Field Engineering
budget linked to resource -loaded
construction baseline schedule.
❑ Quantify and negotiate PCOs to
ensure contingent costs are
reported to management.
❑ Provide proactive alternatives to
construction sequencing,
❑ Utilize document control tools for
team 24/7 team access.
❑ Participate in any partnering
workshops proposed by City.
❑ Hold issue specific team meetings
/ workshops.
❑ Provide a locally -based team that
has worked well together on
similar projects.
❑ Build from recent CM and
inspection activities for other
similar projects.
❑ Provide local team that is familiar
with local issues and contractors.
❑ Provide an Independent team to
perform reviews.
❑ Provide input and respect
Engineer's design approach.
❑ Confirm project sequencing
requirements are addressed in
Contract Documents.
❑ Confirm proper interface between
construction projects.
❑ Identification of key schedule
constraints early on to mitigate
potential delays.
❑ Minimized cost overruns due to
unforeseen construction issues,
❑ Meet schedule with fully -
functional facility
❑ Concise 2-week look -ahead.
❑ Streamlined sequencing &
coordination
❑ Minimize inspection costs
❑ Provide City staff with current
summarized data weekly. Create
Management "dashboard" for
interface with field CM team.
❑ Maintain a "no surprises' result
when planning progress
payments or approval of PCOs.
❑ Provide a monthly report detailing
progress & delineate project risk.
❑ Facilitated, yet secure, document
filing system for detailed project
progress.
❑ Streamlined communications and
accountability for project success.
❑ Established plan for maintaining
Stakeholder Involvement.
❑ Adaptive CM and inspection team
that Is in close proximity to project
site
❑ Proven integration of our
combined Team's CM and
Inspection expertise.
❑ Team with knowledge of current
bidding climate.
❑ Confidence in constructability
reviews to identify ambiguities
and conflicts.
❑ Lower bid prices, reduced change
orders/claims and fewer delays.
p Mitigate/eliminate impact to
stakeholders on concurrent
construction activities.
ifLlilER C. UNDERSTANDING OF NEED
20A-64
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP Ala 2-049
Safety ❑
Attend Contractors weekly safety
❑
Illness and injury free
meeting. Follow and respect
construction site.
Contractor's safety program.
❑
Maintain a safe working
❑
Observe for testing of the quality
environment in confined space
of air In confined spaces and the
❑
Prevent leakage of odors and
provision of a fresh air source.
explosive gasses. Provide for a
❑
Inspect HVAC duct connections,
hazard free environment.
pipe joints, door/hatch seals,
❑
Provide a safe environment for
penetration seals and equipment
operation and maintenance of the
seals for tightness and longevity.
pump station.
❑
Ensure HVAC system is installed
❑
Facility is provided with
where the fresh air source Is
unobstructed lighting for safety
unobstructed and unadulterated.
and ease of operation and
❑
Inspect to see that all electrical
maintenance.
equipment is properly grounded,
all switches are the non -spark type
and hazardous areas are
equipped with explosion proof
fixtures, switches, boxes, oudets.
Environmental Impacts
Structural Failures
Drive & Pump Shaft
Longevity of Materials
Compliance
Traffic Control
Pump Station and Pipeline
Alignment
❑ Verify all light sources are installed
in a location to provide required
lumens for operation personnel.
❑ Enforce hours of work, raise
levels, and clean work areas.
❑ Require whisper quiet equipment
for 24-hour dewatering operations
and emergency numbers for
Contractor to address
abnormalities.
❑ Inspect all structural components
such as concrete, pump base
plates and other equipment
supports for level and plumb.
❑ Require proper alignment using
millwright(s) for drive and pump
shaft alignment.
❑ Provide a pump Installation within
the manufacturer's requirement.
❑ Insist the Contractor follow the
requirement for corrosion resistant
materials during construction.
❑ Enforce Best Management
Practices (BMP) for site drainage
and eliminate runoff.
❑ Minimize environmental impacts
to the local community.
❑ Minimize community complaints
and possible complications from
spills or interruption of dewatering
operation.
❑ Prevent minor structural failures
that can cause pumps and other
equipment to run inefficiently
causing noise vibration and wear.
❑ Will provide full warranty
performance.
❑ Increase longevity of the Pump
Station and pipeline.
❑ Maintain compliance with all
regulatory agencies.
❑ Monitor and enforce traffic control ❑ Maintain maximum traffic flow
plans for Sergerstrom Avenue. and workers safety.
❑ Check Pump Station and Pipeline
alignment and depth during
construction.
❑ Provide working hydraulic profile
as designed for properly
functioning facilities.
13UTIEIR C. UNDERSTANDING OF NEED
20A-65
I 1 A . .,
Section D. Relevant Project Experience
Project Name
Location / Reference
Project Desciption
Mid -Basin Injection Wells—
Butler Engineering, Inc. Is providing
Centennial Park Project;
constructability review, project coordination,
Santa Ana, CA
resident engineering, and construction inspection
Orange County
services for the Mid -Basin Injection Wells Project
Water District
located within the City of Santa Ana's 87-acre
Centennial Park. The wells will be used to directly
Ben Smith, P.E.
inject product water from the District's
Project Manager
Groundwater Replenishment System (GWRS)
Tel: (714) 378-3211
into the principal groundwater aquifer in the
bsmith@ocwd.com
central portion of the Orange County groundwater basin. The project requires
close coordination with the City of Santa Ana, Santa Ana Unified School District,
Value: $23.2 million
Heritage Museum, and state and federal agencies. The project consists of
Completion: 2019
construction of the following:
Proposed Key Personnel
. Four (4) groundwater injection wells in below grade vaults (1,200 feet deep)
Mark Butler, Casey Harris,
and all related appurtenances
Vladimir Burce, P.E., and
• SR-13 monitoring well at the Heritage Museum site
Bryan Wilson
• 5,500 LF of purified recycled water injection supply pipeline that connects to
the District's existing GWRS pipeline and crosses the Santa Ana River
• 4,200 LF of backflush discharge pipeline that discharges to the Greenville -
Banning Channel and Centennial Park Lake
• Two new buildings with shared City of Santa Ana and District uses
Installation of submersible pumps within the four injection wells
• Replacement of 9.6 acres of paving with the Park
Demolishing an existing City of Santa Ana restroom facility
Edinger Avenue Well
Phase 11 Equipping;
Butler provided project / construction
Tustin, CA
management and inspection services for the
Edinger Avenue Well - Phase I I Equipping
City of Tustin, Public Works
Project. Construction of the building and
Ken Nishikawa, Deputy
equipping of the pump included the following:
Director of Public
installation of a 225 LF of 12-inch diameter CML
Works/Engineering
ductile iron pipe discharge water line; connection
Tel: (714) 573-3389
to 12-inch ductile iron watermain; installation of
knishikawa@tustinca.org
162 LF of 18-inch diameter C-905 drain line; connection to the existing storm
drain; placement of new onsite sewer manhole; installation of 76 LF of 8-inch
Value: $4,103,650
diameter SDR 26 sewer lateral; connection to existing OCSD sewer manhole; and
Completion: 2016
erection of 2,376 SF of CMU block wall with a metal roof building to enclose the
Proposed Key Personnel
well pump, electrical equipment and chlorine room.
Mark Butler and
The project is part of the City of Tustin's Water Services Division, which is
Kyle Morgheim, P.E.
responsible for the production and safe delivery of domestic water to more than
14,100 service connections through approximately 172 miles of water mains.
Butler staff coordinated with several agencies including the City of Tustin, City of
Santa Ana, and Caltrans.
i RELEVANT PROJECT EXPERIENCE
20A-67
Station and Vista /
Carlsbad Interceptor Sewer
Replacement; Vista and
Carlsbad, CA
City of Vista
Greg Mayer, P.E.
City Engineer
Tel: (760) 726-1340 x1206
gmayer@ci.vista.ca.us
Value: $64.2 million
Completion: 2018
Proposed Key Personnel
City of Santa Ann, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. 18-049
Butler Engineering, Inc. performed as
the Owner's Representative for the
construction of the sewer lift station and
interceptor sewer reaches. This is a joint
sewer project with the City of Vista and
the City of Carlsbad to replace existing
facilities, increase sewer capacity and
improve reliability withln the lower
portion of the sewer system. The project
beings at the north shore of the Agua
Hedionda Lagoon in Carlsbad and
extends a distance of 2.3 miles to the
Encina Water Pollution Control Facility.
Major project components include the
following:
Mark Butler Removal and replacement of the
existing wood trestle sewer support
bridge across the lagoon with a new
steel support bridge. The new bridge
will provide vehicle access to sewer
facilities. The existing 42-inch
diameter sewer pipe along the
bridge will be replaced with a new
54-inch pipe.
Removal and replacement of the
existing Agua Hedionda lift station.
The new structure will house
replacement motors and pumps, as
well as new system enhancements
including an emergency generator
and bypass motors and pumps, an electrical control building, and odor
control facilities.
Construction of a new 30-inch diameter force main and a new 54-inch
diameter gravity sewer line to increase system capacity and reliability. The
force main will provide 4,000 linear feet of high density polyethylene pipe
parallel to an existing line and will connect into 7,000 linear feet of new 54-
inch diameter gravity sewer to be constructed in Avenida Encinas from
Cannon Road to the Encina Water Pollution Control Facility.
PILITjER D. RELEVANT PROJECT EXPERIENCE
PKI Wo
20A-69 -
i
V VPU V.. wnY ✓.aLw/ VP� W4wV
l ILY LI ivilP0ul
Interceptor Sewer
Tel: (760) 726-1340 x1206
Replacement
4mayer(& i.vista.ca.us
20A-70
y
YH } a a + 9 WJX�1.'1 GROW
pn
e iGa ,I
BUTIERrat' yr
20A-71
Section F. Scope of Services & Schedule
SCOPE OF WORK
The Butier Team will consist of a Project
Manager (PM), Inspector, and a Contract
Administrator (CA). They will serve as an
extension of City staff to assist in the overall
delivery of the San Lorenzo Sewage Lift
Station Project, including pre -construction
tasks, managing construction, and ensure that
the work is completed in accordance with the
contract documents, and project closeout and
warranty phase. The Butler Team will report
directly to the City's Construction Manager,
The proposed scope of work includes Butler's
understanding of the construction
management and field work needs of the City
as related to this contract. We have provided
sufficient detail to dernonstrate that we grasp
the magnitude of the project, and are
experienced in providing the necessary
services.
L Review of Contract Documents
The PM will perform a thorough review of the
contract documents. The review will Include,
but not be limited to, the appropriateness of the
number of working days allowed, the
appropriateness of the amount of liquidated
damages and timely coordination with other
agencies. If any ambiguities, errors, omissions,
or conflicts exist, the PM will advise the City's
Construction Manager on the need for
document content revision, as appropriate.
2, Old Review
Prior to the start of the project, the PM will
review the submitted bids for responsiveness
and completeness, including verifying
licensing, insurance and bonding, and will
assist in performing reference checking. This
will also include verifying that all subcontractors
have a valid City Business License. The PM
will evaluate bids to ensure they are balanced
and not front-end "loaded." Upon completion of
the bid reviews, Butler will assist the City in
determining the apparent responsible and
responsive low bidder for the project. The PM
will prepare a formal memorandum detailing
the bid proposal review and the
recommendation for award.
3. Kick-OfflPre-Construction Meeting
The Butier Team will organize, schedule,
attend and facilitate all project -related
meetings. The PM will organize a kick-off
meeting with City personnel to discuss the
scope of work, project team, and project
schedule and to receive any additional
background information. In addition, the PM
will schedule and facilitate meetings with the
project stakeholders and City staff to discuss
the following: contract administration
guidelines; contractual roles; and
reinforcement of specific requirements for
safely, access, and coordination issues for the
work. The PM will provide a meeting agenda
three (3) days in advance of the meeting and
transmit meeting minutes to all attendees
within three (3) business days.
4. Construction Schedule 1 Budget
The PM will utilize Oracle Primavera P6
Professional Project Management to
perform detailed monitoring of the Contractor's
master schedule for the duration of the Project,
The PM will establish a cost control system for
monitoring and updating project costs and
budget. He will utilize Primavera P6 to prepare
an independent construction cost estimate and
construction schedule based on a standard
five-day workweek. The cost -loaded CPM
schedule will provide the PM with the basis for
cash flow projections. The budget will be
reviewed with the design team and consultants
and submitted to the City for acceptance. The
PM will revise the budget as directed by the
City,
L Construction Progress Reports
The PM will prepare monthly progress reports
that will include the following items: summary of
the prior month's main accomplishments and
current construction activities; reconciliation of
contract time, work progress, and manpower
usage by the Contractor; project costs to date;
overall contractor's conformance to quality
20A-72
requirements; identification of major issues
addressed or arising from the project requiring
resolution; summary of progress payments,
certified payrolls, change order disputes,
submittals, RFls and responses, and notices of
noncompliance; and daily photographs of
representative project activities.
2. Weekly Progress Meetings
The PM will schedule and lead weekly
meetings with the Contractor, City's
Construction Manager, and other
representatives to resolve all project matters
and assess responsibilities for response to
respective participants. The PM will implement
action monitoring to ensure compliance and
timely response. The CA will distribute the
minutes to the attendees within two working
days and include the minutes in the monthly
progress reports.
3. Shop Drawings and Submittals
The Butler Team will be responsible for
processing and monitoring the status of
submittals. In meeting the City's internal
timeframes, submittals will be processed on a
one -week turnaround basis or sooner.
Submittal tracking will be introduced into the
electronic document control system and status
of submittals will be known at all times. This
system will be coordinated with the Contractor
per contract document requirements. The PM
will review the completeness and quantity of
ail required shop drawings, product data,
samples and other submittals received during
the construction phase and transmit to City
staffing for review and approval.
4. Requests for Information
The PM will coordinate the RFI review
process and route all RFls to the appropriate
reviewer. The documentation will be logged,
tracked, maintained, and organized in the
electronic document control system in PDF
format. All responses will be monitored with
suspense action dates and fellow -up
procedures implemented to ensure timely
action by all parties to project issues Including
input from City staff.
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Stetton, RFP No. 18-049
5. Permits
The Butler Team will ensure that all building
permits and special permits are obtained and
that all applicable fees have been paid, and
will obtain approvals from authorities having
jurisdiction over the Project.
6. Change Order Requests
The City or Contractor may initiate a change
or request for changes, or modifications may
arise due to differing site conditions. The PM
will track, document and negotiate all changes
for added costs or credits with the Contractor.
The PM will evaluate all schedule impacts in
addition to advising the District of equitable
cost and time adjustments for proposed or
authorized changes including credits that are
due.
The PM will coordinate change order
procedures for preparation of documents to be
executed by the Contractor and the District.
The RE and claims support will evaluate
Contractor claims seeking additional costs or
time for contract modifications.
The PM will assess if the claim has merit and
make recommendations. Unresolved claims
will be administered through the remedies
clauses of the construction contract under the
direction of the District.
7. Contractor's Safety Program
The Contractor will be required to prepare and
submit a safety program to the PM for review.
The PM will take the necessary steps to ensure
the job site conditions are in compliance with
OSHA regulations. The PM will notify the
Contractor of any safety problems and direct
the Contractorto suspend work if imminent
hazard is not immediately remedied or a
dangerous condition persists.
S. Cost Accounting Records
The Butier Team will maintain cost accounting
records on authorized work performed under
unit costs and additional work performed on
the basis of actual costs of labor and
materials, or other work required accounting
records.
BUTTER , ..- F. SCOPE OF SERVICES & SCHEDULE
20A-73
(9)
9. Progress and Final Payments
The PM will receive, check, and verify all
Contractor monthly progress payment
requests and other project -related invoices
based upon the cost -loaded schedule. The
progress payment worksheet will be based on
an approved schedule of values. Progress pay
requests will be checked against the approved
schedule of assigned values and actual in -
place quantities verified at the end of the pay
period. The pay request format will be
established by the project team to expedite
checking, processing, and subsequent
updating of project budgets and cost
projections and forwarded to the City's
Construction Manager for approval and
payment to the Contractor.
10. Prevailing Wage & CWA Forms
The Butler Team will monitor prevailing wage
forms and requirements for conformation to
the prevailing wage rates on a weekly basis.
The Butler Team will verify that all Trade
personnel listed in the daily log are also listed
in the certified payroll. The Butler Team will
also monitor the City's Community Workforce
Agreement (CWA) forms and requirements to
ensure compliance. Verification of prevailing
wage and CWA will be provided with the
monthly progress payments.
11. Compliance with Contract Documents
The Butler Team will monitor construction
activities to ensure the work adheres to the
contract documents and regulatory agencies.
The PM will lead resolution of day-to-day
construction issues raised and coordinate with
the inspectors, Design Engineer, and
Contractor as required. The PM will make
recommendations to the City regarding special
inspection or testing of work not in compliance
with the contract documents
12. Maintain "As -Built" Records
The Butler Team will review the Contractor's
as -built records on a monthly basis to ensure
that timely recording is being accomplished.
The PM will ensure that the City's as-builts
identify RFIs, shop drawing revisions, change
order modifications, etc, and that they are
City of Santa Ana, Public Works Agency
Coastruc6on Engineering Services for the
San Lorenzo Sewage Lift Station, RFP No. 98-049
updated weekly. The as-builts will be submitted
to the City and the Design Engineer at the
completion of the project. The PM will
coordinate the submittal of completed record
drawings to the City's Construction Manager.
The PM will hold monthly record drawing
review meetings with the City's CM and the
Contractor prior to submittal of monthly
progress payments. Butler will be utilizing Blue
Beam.
13. Construction Inspection
Butler will assign a Lead Inspector to ensure
that the Contractor's work is in compliance
with the contract documents, industry
standards, applicable codes, environmental
and local regulations, and construction
permits. In addition, the Lead Inspector will be
responsible for the following:
Daily Inspection Reports: The Lead
Inspector will maintain daily inspection
reports, which will be submitted to the City
on a weekly basis. The reports will
document construction activities, including
the date, day of week, and weather
conditions; hours of work; personnel on
site; equipment being used; idle or
inoperable equipment; details of each
activity; controversial matters/disputes;
deficiencies and violations; instructions
issued to the construction contractor;
safety concerns; description of accidents;
major material and equipment deliveries to
the site; names of visitors to the site; and
delays and extra work.
Schedule Review: Reviewing the
Contractors' two week "look ahead"
schedules and coordinate staffing needs
with Butler's PM.
RFIs: Discuss responses to RFIs with
Butler's PM as required and coordinate the
replies to the Contractor; review of the
submittals, provide non-conformance
reports; and provide documentation of
construction activities, duration of
activities, manpower and equipment
allocation.
BUTIER F. SCOPE OF SERVICES & SCHEDULE
20A-74
Photographic Records: Provide weekly
photographic/digital records of the project
during construction. Log construction
digital photographs on a daily basis. A
digital photographic library will be
maintained of significant construction
activities. The photographs will be labeled
with the date, location, and narrative
information, Additional digital photographs
will be taken of change order and claim
items, and any special or unique
conditions as they arise. The photographic
library will be turned over to the City at the
completion of the construction contract.
14. Special Inspection I Materials Testing
The PM and Lead Inspector will facilitate and
coordinate inspection by representatives of
other agencies and schedule and coordinate
special inspection and materials testing.
1. Detailed Project Punch Lists
The Butler Team will prepare a project punch
list at substantial completion and coordinate
the correction of deficiencies by the
Contractor. Upon correction of deficiencies,
the PM will coordinate and conduct a final
walk-through prior to the acceptance of work
with the Design Engineer, Uty's Construction
Manager, and other staff as directed.
2. Final Payment Requests
The PM will verify that the Contractor has
made all payments to the subcontractors and
vendors and that any stop notices or liens
have been released. The PM will obtain a
Conditional Waiver of Lien from the Contractor
prior to recommending final payment.
3. Verify Contractor's Project Record
Drawings
The PM will review the Contractor's project
record drawings for completeness.
4. Compile and Submit O & M Manuals
The PM will compile and submit operation and
maintenance manuals, instruction manuals,
parts lists, spare parts, and warranties for
equipment procured. The PM will collect
City of Santa Ana, Public Works Agency
Construction Engineering Services for the
San Lorenzo Sewage Lift Station, RFF No. 98-049
relevant data and information from the
Contractor and material/equipment supplies
and assist the Design Engineer in developing
a comprehensive O&M Manual.
5. Final Report
The PM will prepare and submit a final
progress report to the City no later than 60
calendar days following the filing of the Notice
of Completion. The report will include a
complete overview of the contract,
Contractor's performance, accomplishments,
preliminary and final project costs, cash flows,
schedules, and recommendations for
alleviating problems experienced on the
project.
6. Turn Over All Documents and Files
The Butler Team will furnish all original project
documents and final reports to the City's CM
within 60 calendar days following filing of the
Notice of Completion. The documents will be
delivered to the City in a form and fashion
acceptable to the City. The files will also be
scanned and provided to the City in electronic
format on CD-ROM (two copies) labeled with
the project name.
EIL17fER F. SCOPE OF SERVICES & SCHEDULE
20A-75
.
�
!
�
R
�
--
E
\-
`
}-
v
��-
\
�
�f�;�.�■;
§,
■E
7\
!§
;
/
\.
ii
r;
§§
f\
�
26�
\)
20A- §
Won
20A-77
ON -COLLUSION AFFIDAVIT
(Title 23 United States Code Section 112 and Public Contract Code Section 7106)
In conformance with Title 23 United States Code Section 112 and Public Contract Code 7106 the
BIDDER declares that the bid is not made in the interest of, or on behalf of, any undisclosed
person, partnership, company, association, organization, or corporation; that the bid is genuine
and not collusive or sham; that the BIDDER has not directly or indirectly induced or solicited
any other BIDDER to put in a false or sham bid, and has not directly or indirectly colluded,
conspired, connived, or agreed with any BIDDER or anyone else to put in a sham bid, or that
anyone shall refrain from bidding; that the BIDDER has not in any manner, directly or indirectly,
sought by agreement, communication, or conference with anyone to fix the bid price of the
BIDDER or any other BIDDER, or to fix any overhead, profit, or cost element of the bid price,
or of that of any other BIDDER, or to secure any advantage against the public body awarding the
contract of anyone interested in the proposed contract; that all statements contained in the bid are
true; and, further, that the BIDDER has not, directly or indirectly, submitted his or her bid price
or any breakdown thereof, or the contents thereof, or divulged information or data relative
thereto, or paid, and will not pay, any fee to any corporation, partnership, company association,
organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham
bid.
Note: The above Non -collusion Affidavit is part of the Proposal. BIDDERS are
cautioned that making a false certification may subject the certifier to criminal
prosecution. n
Signed
State of California
County of Orate
Subscribed and sworn to (or affunred) before me on this 20� by
proved to me on the basis lsfactoty evidenceha be the
person(s) who appeared before me a�CL-e
Sd-e 411 k'%-
Notary Public Signature Notary Public Seal
City of Santa Ana RFP 18-029
20A-78
A Notary Public or other officer completing this certificate verifies only the identity of the
individual who signed the document to which this certificate is attached, and not the
truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ORANGE
SUBSCRIBED AND SWORN TO (or affirmed) before me on this 24"d day of June, 2018 by
Mark M. Butler, proved to me on the basis of satisfactory evidence to be the persons who
appeared before me,
' OYNFNIA L. 6YLLESPIE
y. , . ,, Cammlagian p 2096B43 i'
,, *{ Notary Public _ caf9ornla A efnthia L. G' espie, Notary Public
Oranga County 1�
''e•-.—,:.�.C.,o,.COOT, E. dreg Feb 9, 201911
20A-79
NON -LOBBYING CERTIFICATION
The prospective participant certifies, by signing and submitting this bid or proposal, to
the best of his or her knowledge and belief, that:
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of
the undersigned, to any person for influencing or attempting to influence an
officer or employee of any Federal agency, a Member of Congress, an officer or
employee of Congress, or an employee of a Member of Congress in connection
with the awarding of any Federal contract, the making of any Federal grant, the
making of any Federal loan, the entering into of any cooperative agreement, and
the extension, continuation, renewal, amendment, or modification of any Federal
contract, grant, loan, or cooperative agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid
to any person for influencing or attempting to influence an officer or employee of
any Federal agency, a Member of Congress, an officer or employee of Congress,
or an employee of a Member of Congress in connection with this Federal
contract, grant, loan, or cooperative agreement, the undersigned shall complete
and submit Standard Form-LLL, "Disclosure of Lobbying Activities," in
conformance with its instructions.
This certification is a material representation of fact upon which reliance was placed
when this transaction was made or entered into. Submission of this certification is a
prerequisite for making or entering into this transaction imposed by Section 1352, Title
31, U.S. Code. Any person who fails to file the required certification shall be subject to
a civil penalty of not less than $10,000 and not more than $100,000 for each such
failure.
The prospective participant also agrees by submitting his or her bid or proposal that he
or she shall require that the language of this certification be included in all lower tier
subcontracts, which exceed $100,000 and that all such subrecipients shall certify and
disclose accordingly. A/
Signed: -" yt G,/ /
Title: Vice President/CFO
Firm: Butler Engineering, Inc.
Date: 07/26/2018
City of Santa Ana RFP 18-029
r1 M :1
CITY OF SANTA ANA
REP NO.: 18-029
STRUCTURAL ENGINEERING SERVICES
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
1. The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are heated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on
behalf of the Contractor, state that all qualified applicants will receive consideration for
employment without regard to race, color, religion, sex, or national origin.
3. The Contractor shall send to each labor union or representative of workers with which he,/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
5. The Contractor shall furnish all information and reports required by Executive Order 11246
of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or
pursuant thereto, and will permit access to his/her books, records, and accounts by the
administering agency and the Secretary of Labor for purposes of investigation, to ascertain
compliance with such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible
for further Government contracts or federally assisted construction contracts in accordance
with procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as
otherwise provided by law.
Page 1 of 2
20A-81
CITY OF SANTA ANA
RFP NO.: 18-029
STRUCTURAL. ENGINEERING SERVICES
The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order
unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to
Section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be
binding upon each subcontract or purchase order as the administering agency may direct as
means of enforcing such provisions, including sanctions for noncompliance; provided,
however, that in the event the Contractor becomes involved in, or is threatened with,
litigation with a subcontractor or vendor as a result of such direction by the administering
agency, the Contractor may request that the United States enter into such litigation to protect
the interests of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation of the Chapter.
Signed:
Title: Vice PreSident/CFO
Firm: Butler Engineering, Inc.
Date; 07/2612018
Page 2 of 2
20A-82
17822 E. 1717, Street
Suite 404
Tustin, CA 92780
Tel (714) 832-7222
Fax (714) 932-7211
EXHIBIT C
July 26, 2018
City of Santa Ana
Attn: Tyrone Chesanek
Public Works Agency
20 Civic Center Plaza
3t1 Floor Reception, Ross Annex
Santa Ana, CA 92701
Subject: Fee Proposal—RFP No. 18.049: Construction Engineering Services
for the San Lorenzo Sewage Lift Station Project
Dear Mr, Cl
The Butler Team is pleased to submit one (1) hardcopy of our fee proposal in a
sealed envelope to provide construction engineering services for the above
referenced project Our proposal is fully responsive to the City of Santa Ana's (City)
Request for Proposal Issued on June 14, 2018, THE PROPOSED BUDGETS ARE
SUBJECT TO FiNaL SCOPE NEGOTIATIONS,
CLARIFICATIONS/SUGGESTIONS
The proposed level of effort is based on the project schedule provided in the RFP.
The objective of our staffing plan is to take full advantage of our local project
resources. The final xtaffinn nlan will hn hocorl nn Iho �Ilh, A,rll
Rates for the Construction Management Team
Vehicle mileage, computers, computer software, printers, reproduction, cell phone
service, broadband service, office supplies, technical reference materials, training,
and personal protective equipment (PPE) including hard hats, safety boots, work
gloves, safety glasses and other PPE as required shall be billed at the attached
rates per labor hour charged to the project. Rates will be maintained for the
contact period.
Excluded from Rates
Trailer rental costs, Installation of utilities, cost of utilities, cost of sanitary services,
broadband / high speed connections, janitorial, and furniture
Legal
All sub -consultants will be bound to the final terms and conditions of the prime
agreement.
Field Office
We have assumed the contractor will provide
the field CM team. Team meetings can be
Tustin as an option.
BUTLER
the necessary office space to house
conducted In Butler's home office in
417 oe
17822 E. 171h Street
Suite 404
Tustin, CA 92780
Tel (714; 832-7222
Fax (714) 832-7211
We look forward to the opportunity to work with the City on this important
procurement. If you have any questions regarding the attached proposal, please
contact me at (714) 832-7222.
Sincerely,
suTIER Engineering, Inc.
Construction Managers, ConsUlfln glneers
Mark M. Butler, Jr.
Vice President/CFO
r10
m:'h
W`
oa
;y
A
p
0
i.
r
.y.
6 --i
U
O
10
10
L'22
p
b
its
g
8ly
''
Q�
NCNu.LoV
p3pYn
E
b
6G
OOU
m
o
�i']
Y
N r.,
P417MOR
COST ANALYSIS
CONSTRUCTION OF THE PROJECT NO. 16-3510: SAN LORENZO SEWAGE LIFT
STATION
Construction Contract
$
7,606,500
Construction Engineering Service Agreement
$
550,000
Material Testing and Inspection
$
608,520
Contract Administration
$
152,130
Contingencies
$
1,140,975
TOTAL ESTIMATED CONSTRUCTION COSTS
$
10,058,125
20A-87