HomeMy WebLinkAbout20C - AA FY 2019-30 CIP FLOWER STREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
JANUARY 21, 2020
TITLE:
APPROVE AN APPROPRIATION
ADJUSTMENT, AMEND THE FY 2019-20
CAPITAL IMPROVEMENT PROGRAM, AND
AWARD A CONSTRUCTION CONTRACT
TO EBS GENERAL ENGINEERING, INC., IN
THE AMOUNT OF $2,546,154, FOR THE
GAS TAX LOCAL STREET IMPROVEMENT
FY 19/20 AND FLOWER STREET SEWER
MANHOLE IMPROVEMENTS PROJECTS,
WITH AN ESTIMATED TOTAL PROJECT
DELIVERY COST OF $3,226,287
(PROJECT NOS. 20-6956 & 20-6437)
{STRATEGIC PLAN NOS. 6, 113; C; AND G}
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 1" Reading
❑ Ordinance on 2ntl Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
/s/Kristine Ridge FILE NUMBER
CITY MANAGER
RECOMMENDED ACTION
Approve an Appropriation Adjustment recognizing $2,092,796 from prior year fund balance in
the Special Gas Tax Fund, Prior Year Carry Forward revenue account, transferring the funds
to the Select Street Construction revenue account, and appropriating the same to the Select
Street Construction, HUTA 2103 Gas Tax, Improvements Other Than Building expenditure
account.
Approve an Appropriation Adjustment recognizing $1,133,491 from prior year fund balance in
the Sanitary Sewer Capital Fund, and appropriating the same amount to the Capital Recovery
Charges, Improvements Other than Buildings expenditure account.
3. Approve an amendment to the Fiscal Year 2019-20 Capital Improvement Program to include
$2,092,796 in construction funds for the Gas Tax Local Street Improvements Fiscal Year 2019-
20 Project.
4. Approve an amendment to the Fiscal Year 2019-20 Capital Improvement Program to include
$1,133,491 in construction funds for the Flower Street Sewer Manhole Improvements Project.
5. Award a construction contract to EBS General Engineering, Inc., the lowest responsible bidder,
in accordance with the Base Bid and Additive Alternate 1 in the amount of $2,546,154, for
construction of the Local Street Improvement FY 2019-20 and Flower Street Sewer Manhole
20C-1
Award Contract EBS General Engineering, Inc., for the Local Street Improvement
FY 19/20 and Flower Street Sewer Manhole Improvements Projects
January 21, 2020
Page 2
Improvements projects, for the term beginning upon execution of the contract and ending upon
project completion, and authorize the City Manager to execute the contract subject to non -
substantive changes approved by the City Manager and the City Attorney.
6. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$3,226,287, which includes $2,546,154 for the construction contract; $381,922 for contract
administration, inspection, and testing; and a $298,211 project contingency (approximately
11.7% of the construction contract amount).
DISCUSSION
The City's Pavement Management System has identified 19th Street from Flower to Broadway, a
local concrete street, and Santa Fe Street south of Chestnut Avenue, a heavily used asphalt street
in an industrial area as high priority streets in need of rehabilitation (Exhibit 1). In addition, Public
Works Water Resources staff has identified the need to replace the existing sewer manholes on
Flower Street from 19th Street to Memory Lane.
Manhole replacements will be performed with any underground work, which includes upsizing a
portion of the sewer main, reconstructing the manhole chambers, and installing appurtenances
related to sewer main repairs. Once the manholes and related work is completed, the street
improvements will begin. The street improvement preparatory consists of localized concrete or
asphalt pavement repairs; replacing damaged concrete curbs, gutters, sidewalks, cross gutters,
and curbs ramps; and sealing cracks. This preparatory work is followed by either asphalt concrete
pavement reconstruction or concrete panel replacements
Once completed, the street improvements will enhance ride quality and surface drainage. The
sewer manhole repairs will reduce potential sewer overflows, reduce maintenance, and improve
sewer flow conveyance.
Staff is requesting appropriation adjustments to authorize the expenditure of $3,226,287 to
complete these projects (Recommended Action Nos.1, 2 & 3). The Fiscal Year 2019-20 Capital
Improvement Program will be amended to include these improvement projects totaling $3,226,287
(Exhibit 2).
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised in
the Orange County Register newspaper on December 13 and 18, 2019. Bids were received
electronically via the City's web -based electronic bidding system, PlanetBids, on January 3, 2020.
Through the PlanetBids online portal, vendors may register to receive notifications on all current
and future City projects, as well as download contract documents, receive project updates and
submit bids electronically. Additionally, a total of 968 vendors, including 52 located in the City of
Santa Ana, were notified of the project via PlanetBids. 32 vendors requested bidding documents
and 6 bids were received. No bids were received from Santa Ana contractors.
20Ci-2
Award Contract EBS General Engineering, Inc., for the Local Street Improvement
FY 19/20 and Flower Street Sewer Manhole Improvements Projects
January 21, 2020
Page 3
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BID*
1
EBS General Engineering, Inc.
Corona
$2,546,154
2
R.J. Noble Company, Inc.
Orange
$2,584,378
3
All American Asphalt
Corona
$2,624,670
4
Vido Samarzich, Inc.
Rancho Cucamonga
$2,767,961
5
Excel Paving Co
Long Beach
$2,886,081
6
Hardy & Harper, Inc.
Lake Forest
$3,590,000
* The Bid Documents specified the lowest bid would be determined by including the amount for Bid Alternate 1
All 6 bids were responsive and EBS General Engineering Inc., submitted the lowest responsive bid
(Exhibit 3), in the amount of $2,546,154. Based on the bid analysis and a contractor's reference
check, staff recommends awarding the construction contract (Exhibit 4) to EBS General
Engineering Inc., in the amount bid.
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total cost to
deliver the project also includes construction administration, inspection, and testing, along with an
allowance for contingencies to account for unexpected or unforeseen conditions. Construction
administration and inspection includes construction management; implementation of the City's
Community Workforce Agreement requirements; inspection of the Contractor's work to ensure
contract compliance, workmanship, and quality; and material testing. As indicated in the Cost
Analysis (Exhibit 5) and as summarized in the table below, the estimated total construction delivery
cost of the project is $3,226,287.
Construction Contract
1 $2,546,154
Construction Administration, Inspection, and Testing
$381,922
Contingencies
$298,211
ESTIMATED CONSTRUCTION DELIVERY COST
$3,226,287
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 - Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe and aesthetically pleasing for all users), Strategy C (invest resources
and technology to extend the service life of existing infrastructure to protect the City's investment
and support a high quality of life standard), and Strategy G (develop and implement the City's
Capital Improvement Program in coordination with the Community Investment Plan - e.g.,
neighborhood streets, traffic improvements, etc.).
20C-3
Award Contract EBS General Engineering, Inc., for the Local Street Improvement
FY 19/20 and Flower Street Sewer Manhole Improvements Projects
January 21, 2020
Page 4
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are exempt
from further review. Categorical Exemption Environmental Review No. ER-2019-114 and ER-
2020-002 were filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis (Exhibit 5), the estimated total construction delivery cost of the
project is $3,226,287, which includes the construction contract, contract administration, inspection,
testing, and project contingency. The requested appropriation adjustments will provide the
necessary funding as follows:
1) Recognize and appropriate $2,092,796 from prior year fund balance in the Special Gas Tax
Fund, Prior Year Carry Forward account (No. 02917002-50001) and facilitate an interfund
budgetary expenditure transfer from the Special Gas Tax Fund Interfund Transfer account (No.
02917019-68000-59) to the Select Street Construction Interfund Transfer account (No.
05917002-59000-29) and appropriate the same amount to the Select Street Construction,
HUTA 2103 Gas Tax, Improvements Other Than Building expenditure account (No. 05917663-
66220).
2) Recognize $1,133,491 from prior year fund balance in the Sanitary Sewer Capital Fund, Prior
Year Carry Forward account (No. 05417002-50001) and appropriate the same amount to the
Capital Recovery Charges, Improvements Other than Buildings expenditure account (No.
05417647-66220).
The following table summarizes the funds budgeted to deliver construction of this project:
Fiscal Year
Accounting
Fund
Accounting Unit, Account
Amount
Unit -Account #
Description
Description
APPROPRIATION ADJUSTMENTS
FY 2019-20
05917663-66220
Select Street
HUTA 2103 Gas Tax,
Jan. -June
(Prof. 20-6956)
Construction
Improvements Other Than
$2,092,796
Building
FY 2019-20
05417647-66220
Sanitary Sewer
Capital Recovery Charges,
July -June
(Proj.20-6437)
Capital
Improvements Other Than
$1,133,491
Building
Total:
$3,226,287
All funds are scheduled for expenditure in Fiscal Year 2019-20.
20C-4
Award Contract EBS General Engineering, Inc., for the Local Street Improvement
FY 19/20 and Flower Street Sewer Manhole Improvements Projects
January 21, 2020
Page 5
APPROVED AS TO FUNDS & ACCOUNTS:
Nabil Saba, PE Kathryn Downs, CPA
Acting Executive Director Executive Director
Public Works Agency Finance and Management Services Agency
NS/TC/MO
Exhibits: 1. Location Map
2. Amended FY 2019-20 CIP Project Sheets
3. Bid Proposal
4. Construction Contract
5. Cost Analysis
20C-5
EXHIBIT 1
20C-6
Gas Tax Local Street Improvements FY 19120
Street Improvements -
Local Street Resurfacing
EXHIBIT 2
CITY OF SANTA ANA FY 19120 CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
IOJECT DESCRIPTION:
is project entails the rehabilitation of existing
)dwaypavement. The project will include the removal
J replacement of existing streets. Various
dacement pavement strategies will be investigated to
tennine the most cost effective and maintainable
atment. Minor concrete repair to severely damaged
missing curbs, gutters, sidewalks, and wheelchair
nos will also be included.
PROJECT NEED:
The local street network has 316 miles citywide. In
2007 the City embarked on an extensive citywide
improvement plan to rehabilitate and slurry seal the
majority of the network. By the end of 2015, the City
has completed rehabilitating all asphalt residential
streets and currently working toward improving all
residential and industrial concrete streets.
PROJECT COSTS FY 1920 FY 2021 FY 2122 FY 2223 FY 2324 FY 2425 FY 2526
C0'5V( Oo0 $2,092797
TOTAL $2, 092,797
SOURCE OF FUNDS FY 19/20 FY 2021 FY 2122 FY 2223 FY 2324 FY 2425 FY25M
GAS TAX $2,092797
TOTAL $2, 092,797
AGENCY DIVISION: CONTACT: DATE:
Public Works Agency Design Engineering Sean Thomas, Senior Civil Engineer 12-Jan-2020
-1-
20C-7
Flower Street Sewer Manhole Improvements
U61dy/Drainage/Lighting Impmvements -
Sewer Improvements
CITY OF SANTA ANA FY 19120 CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
=CT DESCRIPTION:
eject will replace existing deteriorated sewer
and related sewer assets, such as, manhols.
PROJECT NEED:
This project is required to maintain effective operation
of the City's sanitary sewer system. These
improvements will eliminate the undersized sewer
mains, reduce sewer maintenance, and prevent sewer
PROJECT COSTS FY 1920 FY 2021 FY 2122 FY 2223 FY 2324 FY 2425 FY 2526
Gons�mc�lon $1,133491
TOTAL 81, 133.491
SOURCE OF FUNDS FY 19P29 FY 2021 FY 2122 FY 2223 FY 2324 FY 2425 FY2525
SEWER $1.133491
TOTAL $1,133,491
AGENCY DIVISION: CONTACT: DATE:
Public Works Agency Water Resources Armando Fernandez, Senior Civil Engineer 12-Jan-2020
-1-
20C-V
City of Santa Ana
Page 1
Gas Tax Local Street Improvements FY 19/20 & Flower Street Sewer Manhole Improvements (Project Nos. 20-6956 & 20-
Printed 01/06/2020
EXHIBIT 3
Bid Results
Bidder Details
Vendor Name EBS GENERAL ENGINEERING INC
Address 1320 E SIXTH ST
STE 100
CORONA, CA 92879
United States
Respondee THOMAS NANCI
Respondee Title PRESIDENT
Phone 951-279-6869 Ext.
Email BIDS@EBSGENERAL.COM
Vendor Type CADIR
License # 720016
CA DIR
Bid Detail
Bid Format Electronic
Submitted January 3, 2020 1:38:07 PM (Pacific)
Delivery Method
Bid Responsive
Bid Status Submitted
Confirmation # 198771
Ranking 0
Respondee Comment
Buyer Comment
Attachments
File Title
File Name
File Type
PROPOSAL
EBS Proposal.pdf
General Forms
OWNERSHIP
OWNERSHIP.pdf
Ownership Affidavit (Notary
Public) - RED Original Hard
Copy Submittal in Addition
BID BOND
BID BOND.pdf
Bid Bond Guaranty (Notary
Public) - RED Original Hard
Copy Submittal in Addition
NON -COLLUSION
NON-COLLUSION.pdf
Non -Collusion Affidavit
(Notary Public) - REQ
Original Hard Copy Submittal
in Addition
Line Items
Type
Item Code
UOM
city
Unit Price
Line Total Comment
Base Bid Items
1
Asphalt Rubber Hot -Mix (ARHM)
TN
1380
$109.00
$150,420.00
2
Crushed Miscellaneous Base (CMB)
TN
290
$129.00
$37,410.00
3
Coldmill (2")
SF
38530
$0.70
$26,971.00
20C-9
City of Santa Ana
Page 2
Gas Tax Local Street Improvements FY 19/20 & Flower Street Sewer Manhole
Improvements
(Project Nos. 20-6956 & 20- Printed 01/06/2020
Bid Results
Type
Item Code UOM
Qty
Unit Price
Line Total Comment
4
Coldmill (3")
SF
13230
$0.90
$11,907.00
5
Removal of 6" PCC at Various Locations
CY
1680
$138.00
$231,840.00
6
Construct 6" PCC with (3-day) Cure including Dowels
CY
1680
$408.00
$685,440.00
7
Crack Seal with Deere Super Gray'
LF
15750
$3.10
$48,825.00
8
Construct PCC V-Gutter Longitudinal (T=8")
LF
4730
$37.00
$175,010.00
9
Construct PCC Sidewalk (T=4")
SF
810
$10.50
$8,505.00
10
Construct PCC Driveway Approach (T-6")
SF
1210
$14.00
$16,940.00
11
Construct PCC Curb Ramp
SF
7880
$16.20
$127,656.00
12
Construct PCC Curb & Gutter (Type A-2-6)
LF
710
$53.00
$37,630.00
13
Construct Cross -Gutter
SF
3890
$19.00
$73,910.00
14
PCC Grinding
LF
50
$95.00
$4,750.00
15
Root Shave
EA
5
$900.00
$4,500.00
16
Adjust Manhole Frame and Cover to Finished Grade
EA
23
$995.00
$22,885.00
17
Furnish and Install New Water Valve Frame and Cover to Grade
EA
38
$875.00
$33,250.00
18
Construct New PCC Sewer Manhole
EA
3
$19,242.00
$57,726.00
19
Construct New PCC Drop Sewer Manhole with two drop connections
EA
1
$40,127.00
$40,127.00
20CA 0
City of Santa Ana
Page 3
Gas Tax Local Street Improvements FY 19/20 & Flower Street Sewer
Manhole Improvements
(Project Nos. 20-6956
& 20- Printed 01/06/2020
Bid Results
Type
Item Code
UOM
City
Unit Price
Line Total Comment
20
Remove Existing Manhole Structure
EA
3
$3,292.00
$9,876.00
21
Bypass Pump Existing Sewer Flow
LS
1
$19,227.00
$19,227.00
22
Remove Existing Sewer Main and Construct
8" PVC, Sewer Main SDR-26
LF
130
$453.00
$58,890.00
23
Remove Existing Sewer Main and Construct
15" VCP Sewer Main
LF
16
$1,190.00
$19,040.00
24
Signing and Striping
LS
1
$17,270.00
$17,270.00
25
Project Advertisement Sign
EA
2
$1,886.00
$3,772.00
26
Labor Agreement Oversight
LS
1
$10,000.00
$10,000.00
27
Traffic Control
LS
1
$58,900.00
$58,900.00
28
Changeable Message Signs (CMS)`
EA
4
$2,480.00
$9,920.00
29
Adjust Pull Box to Grade'
EA
1
$2,230.00
$2,230.00
30
Abandon Existing Sewer Manhole Structure
per City Std. Plan
1209
EA
1
$10,977.00
$10,977.00
31
Remove Existing Gate Valve Structure and Construct new Gate Valve Riser, Valve Box Fame and Cover Per City Ste. Plan 1410
EA
3
$6,590.00
$19,770.00
Subtotal
$2,035,574.00
Add Alternative Bid One
32
Unclassified Excavation
CY
3240
$66.00
$213,840.00
33
AC Pavement
TN
4010
$74.00
$296,740.00
Subtotal
$510,580.00
Add Alternative Bid Two (Replaces Add Alternate One)
34
Unclassified Excavation
CY
970
$66.00
$64,020.00
I20Cs; 111
City of Santa Ana
Gas Tax Local Street Improvements FY 19/20 & Flower Street Sewer Manhole Improvements (Project Nos. 20-6956 & 20-
Bid Results
Type Item Code UOM Qty Unit Price Line Total Comment
35 AC Pavement
TN 2510 $84.00 $210,840.00
36 Full Depth Reclamation with Foamed Asphalt including 3 % asphalt binder and 1.5% cement
SF 88500 $2.45
$216,825.00
Page 4
Printed 01/06/2020
37 Remove 5.5" Pulverized Material
CY 1550 $84.00 $130,200.00
Subtotal $621,885.00
Notes per P-3 of Specifications
38 The lowest responsible bidder shall be selected based on the law Total base bid + Add Alternate I. The City reserves the right to award the Base
Bid, and any, all, or none of the add -alternate bid items (if any).
ea 0 0 0
39 ' = The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of
the Standard Specifications.
ea 0 0 0
40 t - This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
ea 0 0 0
Subtotal 0
Total $3,168,039.00
,20Q; 12
CITY OF SANTA ANA PROJECT 2089% GASTAX LOCAL STREET IMPROVEMETNS FV 192O
PROJECT 206437 FLOWER STREET SEWER MANHOLE IMPROVEMENTS
PROPOSAL ADDENDUM ONE
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: EBS General Engineering, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Asphalt Rubber Hot -Mix (ARHM)
1,380
TN
$
$
109
150,420
2
Crushed Miscellaneous Base (CMB)
290
TN
$
$
129
37,410
3
Coldmill (2")
38,530
SF
$
$
0.70
26,971
4
Coldmill (K)
13,230
SF
$
$
0.90
11,907
5
Removal of 6" PCC at Various
1,680
CY
$
$
Locations
138
231,840
6
Construct 6" PCC with (3-day) Cure
1,680
CY
$
$
including Dowels
408
685,440
7
Crack Seal with Deere Super Gray*
15,750
LF
$
$
3.10
48,82
8
Construct PCC V-Gutter
4,730
LF
$ 37
$ 175,010
Longitudinal (T=8")
9
Construct PCC Sidewalk (T=4")
810
SF
$
$
10.50
8505
10
Construct PCC Driveway Approach
1,210
SF
$
$
(T=6")
14
16,940
11
Construct PCC Curb Ramp
7,880
SF
$
$
16.20
127,656
12
Construct PCC Curb & Gutter (Type
710
LF
$
$
A-2-6)
53
37,630
13
Construct Cross -Gutter
3,890
SF
$
$
19
73,910
494;
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
PROJECT20895 GASTAR LOCAL STREET IMPROVEMETNS FV 1900
PROJECT206 7 FLOWER STREETSEWER MANHOLE IMPROVEMENTS
ADDENDUM ONE
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
Item
Description
Qty
Unit
Unit Price
Amount
14
PCC Grinding
50
LF
$
$
95
4750
15
Root Shave
5
EA
$
$
900
4500
16
Adjust Manhole Frame and Cover to
23
EA
$
$
Finished Grade
995
22,885
17
Furnish and Install New Water
38
EA
$
$
Valve Frame and Cover to Grade
875
33,250
18
Construct New PCC Sewer Manhole
3
EA
$
$
19,242
57,726
19
Construct New PCC Drop Sewer
1
EA
$
$
Manhole with two drop connections
40,127
40,127
20
Remove Existing Manhole Structure
3
EA
$
$
3292
9876
21
Bypass Pump Existing Sewer Flow
1
LS
$
$
19,227
19,227
22
Remove Existing Sewer Main and
130
LF
$
$
Construct 8" PVC, Sewer Main
453
58,890
SDR-26
23
Remove Existing Sewer Main and
16
LF
$
$
Construct 15" VCP Sewer Main
1190
19,040
24
Signing and Striping
1
LS
$
$
17,270
17,270
25
Project Advertisement Sign
2
EA
$
$
1886
3772
26
Labor Agreement Oversight
1
LS
$10,000
$10,000
27
Traffic Control
1
LS
$
$
58,900
58,900
28
Changeable Message Signs (CMS)*
4
EA
$
$
2480
9920
29
Adjust Pull Box to Grade*
1
EA
$
$
2230
2230
30
Abandon Existing Sewer Manhole
1
EA
$
$
Structure Per City STD Plan 1209
10,997
10,997
31
Remove Existing Gate Valve Vault
3
EA
$
$
Structure and Construct New Gate
6590
19,770
Valve Riser, Valve Box Frame and
Cover Per City STD. Plan 1410
CITY OF SANTA ANA
T� T� p TOPOSAL PROJECT2069% GASTAX LOCAL STREET IMPROVEMETNS FY 19M
PRPROJECT 2OM37 FLOWER STREET SEWER MANH OLE IMPROVEMENTS
PROJECT NO.: 20-6956 ADDENDUM ONE
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
TOTAL BASE BID
$ 2,035,574.00
ADD ALTERNATE I
32
Unclassified Excavation
3,240
CY
$ 66
$ 213,840
33
AC Pavement
4,010
TN
$ 74
$ 296,740
TOTAL ADD ALTERNATE I BID
$ 510,580.00
ADD ALTERNATE II (REPLACES ADD ALTERNATE I)
34
Unclassified Excavation
970
CY
$ 66
$ 64,020
35
AC Pavement
2,510
TN
$ 84
$ 210,840
36
Full Depth Reclamation with
Foamed Asphalt including 3%
asphalt binder and 1.5% cement
88,500
SF
$ 2.45
$ 216,825
37
Remove 5.5" Pulverized Material
1,550
CY
$ 84
$ 130,200
TOTAL ADD ALTERNATE II BID
$ 621,885
TOTAL BASE BID + ADD ALTERNATE I BID 1 $ 2,546,154.00
The lowest responsible bidder shall be selected based on the low Total base bid + Add
Alternate L The City reserves the right to award the Base Bid, and any, all, or none of the add -
alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
494§
14I M11W.YVY IIwr_l
PROJECT20895 GASTAX LOCAL STREET IMPROVEMETNS FY 192D
PROPOSAL PROJECT20037 FLOWER STREET SEVHR MANHOLE IMPROVEMENTS
PROJECT NO.: 20-6956 ADDENDUM ONE
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
T This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number 100 working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $3,730 per calendar day.
Name of Finn EBS General En¢ineerin¢, Inc.
Signature of BIDDER
Title Thomas Nanci, President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
gQ940
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
BIDDER'S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council
with her signature and official seal noting hereon the action of approval of the Council, signed by
the Public Works Agency Executive Director or his/her duly authorized agent, and signed by the
City Attorney, denoting his approval of the form of this document, and its execution, and when it
or an exact copy of it has been either delivered to BIDDER or deposited with the United States
Postal Service properly addressed to the BIDDER with the correct postage affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of damages
actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond
substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation under
the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Finn EBS General En
Signature of BIDDER
Inc.
Title Thomas Nanci, President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
4947
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
CONTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she and
all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: EBS General Engineering, Inc.
Business Address: 1345 Quarry Street, Ste 101 Corona CA 92879
Business E-Mail Address: bids Pebsgeneral.com
Telephone:
State Contractor's License No. and Class: 720016 A
License Expiration Date: 3/31/20
State Dept. of Industrial Relations (DIR)
Registration No.:
1000005295
State Dept. of Industrial Relations (DIR)
Registration Expiration Date: 6/30/20
Signed:
Title: Thomas Nanci, President
494P
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
UADIAKU01►[fXTAX0DKOM1D»loci!=1621171ML41UK0N1►1MVILI11051OL411
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well as
California Code of Regulations, Title 8, Section 16,000, et seq., ("Prevailing Wage Laws"), which
require the payment of prevailing wage rates and the performance of other requirements on "public
works" and "maintenance" projects. Since the services are being performed as part of an applicable
"public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and since the
total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing
Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the
commencement of this Agreement. Contractor shall make copies of the prevailing rates of per
diem wages for each craft, classification or type of worker needed to execute the services available
to interested parties upon request, and shall post copies at the Contractor's principal place of
business and at the project site.
Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and
agents free and harmless from any claim or liability arising out of any failure or alleged failure to
comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct.
Name of Firm EBS General Engineering, Inc.
Signature of BIDDER
Title Thomas Nanci, President
(if an individual, so state)
MAP
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
OWNERSHIP AFFIDAVIT
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS:
CITY OF SANfA ANA )
Thomas Nanci , being duly sworn, deposes and says:
[]INDIVIDUAL That he/she is the party making the foregoing proposal:
❑ PARTNERSHIP That he/she is a member of the co -partnership firm designated as:
and who has been and is duly vested with the authority to make and execute instruments
for the co -partnership by:
who constitute the other members of the co -partnership.
61ORPORATION That he is of
EBS General Engineering, Inc.
a corporation which is making the foregoing proposal:
❑ JOINT VENTURE That he is of
one of the parties making the foregoing proposal as ajoint venture. and the he/she has been
and is duly vested with the authority to execute instruments for an on behalfof the parties
making said bid who are:
that such a bid is genuine and not collusive or sham, and has not in any manner sought by collusion
to secure any advantage against the City of Santa Ana or any person interested in the proposed
contr t or mself or any other person.
Signature of gidder Thomas Nanci, President
Subscribed and sworn
/Jl'?
t^o/bee3I
fore me this 0 day of nOC— 20
i (bo l FL' Y,
Signature of officer Administering Oath (Notary Public)
,,.-•`_.',,, WILLIAM E. ELLIS
Notary Public - California
_9 Riverside County
Commission N 2306766
"'• My Comm. Expires Oct 23, 2023
�O P�0
BOND# 3-B
PREMIUM: NIL
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
1,1101.10121
KNOW ALL PRESENT that,
EBS GENERAL ENGINEERING, INC. as BIDDER, and
SURETEC INSURANCE COMPANY as SURETY,
are held and firmly bound unto the CITY OF SANTA ANA, as AGENCY, in the penal sum of _
TEN PERCENT OF AMOUNT BID Dollars ($ 10% ), which is ten percent (10%)
of the total amount bid by BIDDER to AGENCY for the above -stated project, for the payment of
which sum, BIDDER and SURETY agree to be bound, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas BIDDER is about to
submit a bid to AGENCY for the above -stated project, if said bid is rejected, or if said bid is
accepted and a contract is awarded and entered into by BIDDER in the manner and time specified,
then this obligation shall be null and void, otherwise it shall remain in full force and effect in favor
of AGENCY.
IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seal this
23RD day of DECEMBER ,2019.
BIDDER*
EBS GENERAL ENGINEERING, INC., 1345 QUARRY ST., #101
BY
SURETY*
Subscribed and sworn to before me
, 20_.
Signature:
Notary Public in and for the County of State of
79
SAN DIEGO. CA 92108
this day of
* Provide BIDDER/ SURETY name, address, and telephone number and the name, title, address,
and telephone number of authorized representative.
AUTHORIZED REPRESENTATIVE:
CULBERTSON INSURANCE SERVICES, INC.
5500 E. SANTA ANA CANYON RD. #201
ANAHEIM, CA 92807 (714) 921-0530
P-8 of P-17
20C-21
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT CIVIL CODE § 1189
... _. .4.Y nlw-..4YA;:w.•..4': A`�A.Y:4•..Y-: w.. ti'.1..4 1. l.n�.4:�614�n...n. .�....�t �. �. �.....�..n.. n..ti .. ... .. ._.� .. .. .. n..n
A notary public or other officer completing this certificate verifies only the identity of the
individual who signed the document, to which this certificate is attached, and not the
truthfulness, accuracy, or validity of that document.
State of California
County of RIVERSIDE )
On (?-r-Q before me, WILLIAM E. ELLIS, JR.
Date Here Insert Name and Title of the Officer
personally appeared
THOMAS E. NANCI
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s)
is/are subscribed to the within instrument and acknowledged to me that he/she/they executed
the same in his/her/their authorized capacity(ies), and that by his/herttheir signature(s) on the
instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the
instrument.
WILL" E. ELLIS
Notary Public - California
< Riverside County
= Commission C 2306766
My Comm. Expires Oct 23. 2023
Place Notary Seal Above
Description of Attached Document
Title or Type of Document:
Number of Pages:
I certify under PENALTY OF PERJURY
under the laws of the State of California that
the foregoing paragraph is true and correct.
WITNESS my hand and ccoffiicial seal.
Signature�i, [7 f_Z4�:
Signature of Notary Public
Document Date:
Signer(s) Other Than Named Above:
Capacity(ies) Claimed by Signer(s)
Signer's Name:
o Corporate Officer — Title(s):
❑ Partner - o Limited In General
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
❑ Other:
Signer is Representing:
Signer's Name:
❑ Corporate Officer — Title(s):
❑ Partner - o Limited ❑ General
❑ Individual ❑ Attorney in Fact
zi Trustee ❑ Guardian or Conservator
❑ Other:
Signer is Representing:
.:i•:t<�:rfc.:n.!XX.4Ta..:.�w`A.Yniw.i2: ti'4s'.4rw.•: iwXxSw.�w.r4r.4^�i�rwX:a�:.c.fw cRS,a.C:aYw.`:...'C,4rc:Y.-"aYa::w.i,t•:w.ti,t'r..•.:,
® 2014 National Notary Association ' w .NationalNotary.ora ` 1-800-USNOTARY (1-800-876-6827) Item #5907
C-16
20C-22
JURAT FORM
A notary public or other officer completing this certificate verifies only the
identity of the individual who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA )
COi.1NTYOF Orange )
Subscribed and sworn to (or affirmed) before me on this 23rd day of
December , 2019 by Spencer Flake
proved to me on the basis of satisfactory evidence to be the person(s) who appeared
before me.
ERIN SHEZ;;O
_ COMM, N-CALIFa
NOTAav aUBUC �CALIFORNIAr
ARY SEAL) y ORANGE COUNTY
NOTARY PUBLIC SIGNATURE, Erin Sherwood I N"CGVM EXPIRES JUlY 08.2023
OPTIONAL INFORMATION
THIS OPTIONAL INFORMATION SECTION IS NOT REQUIRED BY LAW BUT MAY BE BENEFICIAL TO PERSONS
RELYING ON THIS NOTARIZED DOCUMENT.
TITLE OR TYPE OF DOCUMENT
DATE OF DOCUMENT
When executing a jurat, a notary shall administer an oath of affirmation to the affiant and shall
determine, from satisfactory evidence, that the affiant is the person executing the document. The
affiant shall sign the document in the presence of the notary.
20C-23
eoA it: 510123
SureTec Insurance Company
LUMTED POWER OF ATTORNEY
Know AR Men by These Presents, That SURETEC INSURANCE COMPANY (the "Company"), a corporation drily organized and
existing under the laws of the State of Texas, and having its principal office in Houston, Harris County, Texas, does by these presents
make, constitute and appoint
Charles L. Flake, David L. Culbertson, Spencer Flake, Heather Willis
its true and lawful Attorney -in -fact, with full power and authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver any and all bonds, recognizances, undertakings or other instruments or contracts of suretyship to include waivers to the
conditions of contracts and consents of surety for, providing the bond penalty does not exceed
Ten Million and 00/100 Dollars ($10,000,000.00)
and to bind the Company thereby as fully and to the same extent as if such bond were signed by the CEO, sealed with the corporate seal
of the Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attorney -in -Fact may do in the
premises. Said appointment is made under and by authority of the following resolutions of the Board of Directors of the SureTec
Insurance Company:
Be it Resolved that the President, any Vice -President, any Assistant Vice -President, any Secretary or any Assistant Secretary shall be and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attomey(s)-in-Fact to represent and act for and on
behalf of the Company subject to the following provisions:
Attorney -in -Fact may be given full power and authority for and in the time of and of behalf of the Company, to execute, acknowledge and
deliver, any and all bonds, mwgnizmces, contracts, agreements or indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney -in -Fact shall be binding upon the Company as if signed by the President and sealed and effected by the Corporate Secretary.
Be it Resolved, that the signature of any authorized officer and seal of the Company heretofore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signature or facsimile seal shall be valid
and binding upon the Company with respect to any bond or undertaking to which it is attached. (Adopted at a meeting held on 20" of April,
1999.)
In Witness Whereof, SURETEC INSURANCE COMPANY has caused these presents to be signed by its CEO, and its corporate seal to
be hereto affixed this lath day of September, A.D. 2018 .
SURETEC CE PANY
U3\-11
RANQBy:
John Jr., CState of Texas ss:County of Hams
On this 28th day of September , A.D. 2018 before me personally came John Knox Jr., to me known, who, being by me duly sworn, did depose and say,
that he resides in Houston, Texas, that he is CEO of SURETEC INSURANCE COMPANY, the company described in and which executed the above
instrument; that he knows the seal of said Company; that the seal affixed to said instrument is such corporate seal; that it was so affixed by order of the
Board of Directors of said Company; and that he signed his name thereto by like order.
E[-�:
idetan•' ub:ic. Mite Zmm. E
Naiary
Xe ' — - Z, 6 eJ
avez, Notary Public
Jcommission expires September I , 2020
I, M. Brent Beaty, Assistant Secretary of SURETEC INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy
of a Power of Attorney, executed by said Company, which is still in full force and effect; and furthermore, the resolutions of the Board of Directors, set
out in the Power of Attorney are in full force and effect.
Given under my hand and the seal of said Company at Houston, Texas this 23RD day of DE MBER N.
201 A.D
. Br t eaty, Assistant Secrete _
Any instrument issued in excess of the penalty stated above is totally void and without any validity.
For verification of the authority of this power you may call (713) 812-0800 any business day between 8:30 am and 8:00 pm CST.
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
LIST OF SUB -CONTRACTORS
Section 4100 et. seq. of the Public Contract Code requires listing of all subcontractors with the bid for all
subcontract work exceeding the following amount:
o Streets, highways including bridge projects: 'h% of the bid or $10,000, whichever is greater
o Buildings, parks, or other projects: '/z% of the bid
Section 1725.5 of the Public Contract Code requires all Subcontractors be registered with the State
Department of Industrial Relations (DIR).
BIDDER proposes to subcontract certain portions of the work to the firms listed below:
Name Mike Prlich & Sons, Inc.
License #/Exp. 760474
DIR Reg. #/Exp. 1000006538
Location Baldwin Park
Phone 626-813-1700
Type Of Work Sewer
Amount $ 204,840
Name Pavement Rehab Company
License #/Exp. 1051374
DIR Reg. #/Exp. 1000064823
License #
Location Costa Mesa
Phone 714-238-1444
Type Of Work Crack Seal
Amount $ 43,312.50
Name Pavement Recycling Systems, Inc
License #/Exp. 569352
DIR Reg. #/Exp. 1000003363
License #
Location Turupa Valley
Phone 951-682-1091
Type Of Work Cold Mill
Amount $ 338,791
Signature of Bidder
Name Superior Pavement Markines
License #/Exp.
776306
DIR Reg. #/Exp.
1000001476
Location
Cypress
Phone 714-995-9100
Type Of Work
Sign & Stripe
Amount $
14,221.90
Name
License #/Exp.
DIR Reg. #/Exp.
License # _
Location _
Phone
Type Of Work
Amount $
Name
License #/Exp.
DIR Reg. #/Exp.
License # _
Location _
Phone
Type Of Work
Amount $
4q bf,9§
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
1. See attached reference list
Name and Address of Owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
2.
Name and Address of owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
3.
Name and Address of owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Culbertson Insurance Services: 5500 E. Santa Ana Canyon Rd., Ste 201 Anaheim CA 92807 714-921-0530
Invensure Insurance Brokers: 17991 Cowan Irvine CA 92614 (949) 756-4100
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
1 See attached reference list
Name and Address of Owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
2.
Name and Address of owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
3.
Name and Address of owner.
Name and Telephone Number of person familiar with project.
Contract Amount Type of Work Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
See info on P-10
Q1`df 7
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19120
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
NON -COLLUSION AFFIDAVIT
(Title 23 United States Code Section 112 and Public Contract Code Section 7106)
In conformance with Title 23 United States Code Section 112 and Public Contract Code 7106 the
BIDDER declares that the bid is not made in the interest of, or on behalf of, any undisclosed
person, partnership, company, association, organization, or corporation; that the bid is genuine and
not collusive or sham; that the BIDDER has not directly or indirectly induced or solicited any other
BIDDER to put in a false or sham bid, and has not directly or indirectly colluded, conspired,
connived, or agreed with any BIDDER or anyone else to put in a sham bid, or that anyone shall
refrain from bidding; that the BIDDER has not in any manner, directly or indirectly, sought by
agreement, communication, or conference with anyone to fix the bid price of the BIDDER or any
other BIDDER, or to fix any overhead, profit, or cost element of the bid price, or of that of any
other BIDDER, or to secure any advantage against the public body awarding the contract of anyone
interested in the proposed contract; that all statements contained in the bid are true; and, further,
that the BIDDER has not, directly or indirectly, submitted his or her bid price or any breakdown
thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will
not pay, any fee to any corporation, partnership, company association, organization, bid
depository, or to any member or agent thereof to effectuate a collusive or sham bid.
Note: The above Non -collusion Affidavit is part of the Proposal. BIDDERS are cautioned
that rrlakjpg a f Ise certification may subject the certifier to criminal prosecution.
Signed `�� (1�
Thomas Nanci, President
State of California
County of
Subscribed and sworn to (or affirmed) before me on this ' day of C . 20_4, by
, proved to me on the basis of satisfactory evidence to be the person(s)
who appeared before me
�—
Notary Public Signature Notary Public Seal
WILLIAM E. ELLIS
Notary Public - California
Riverside County €
Commission q 230ri766
My Comm. Expires Oct 23, 2023
�d-f Pz'6
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
1. The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf
of the Contractor, state that all qualified applicants will receive consideration for employment
without regard to race, color, religion, sex, or national origin.
3. The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
5. The Contractor shall furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant
thereto, and will permit access to his/her books, records, and accounts by the administering
agency and the Secretary of Labor for purposes of investigation, to ascertain compliance with
such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible for
further Government contracts or federally assisted construction contracts in accordance with
procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as otherwise
provided by law.
93`df A9
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
7. The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless
exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section
204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding
upon each subcontract or purchase order as the administering agency may direct as means of
enforcing such provisions, including sanctions for noncompliance; provided, however, that in
the event the Contractor becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as a result of such direction by the administering agency, the
Contractor may request that the United States enter into such litigation to protect the interests
of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation of the Chapter.
Signed: -- �_ 0
"Iu_ ►. ' M
Firm: EBS General Engineering, Inc.
Date:
?4419f-A9
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
1. Apply to the joint apprenticeship committee administering the apprenticeship standards of the
craft or trade in the area of the site of the public work for a certificate approving the contractor
under the apprenticeship standards for the employment and training of apprentices in the area
or industry affected.
2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
3. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like amount to the California Apprenticeship Council.
Signed:
Title: Thomas Nanci, President
Firm: EBS General Engineering, Inc.
Date:
M-Al
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
STATEMENT REGARDING "ANTI -KICKBACK" REQUIREMENTS
The undersigned is submitting this proposal for performing by contract the work required by these
bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repair of public work, to give up any part of the compensation to
which he/she is otherwise entitled.
Signed: C -_o
Title: Thomas Nanci. President
Firm: ERS General Engineering, Inc_
Date: 1?11nn4
M-A
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6956
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20
PROJECT 20-6437
FLOWER STREET SEWER MANHOLE IMPROVEMENTS
PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented from
bidding on, or completing a federal, state, or local government project because of a violation of
law or a safety regulation?
Yes No J
If the answer is yes, explain the circumstances in the following space.
?Kf-A
3 YEAR REFERENCES — PUBLIC WORKS
1. Proiect Name
2017/2018 Arterial and Minor Streets Maintenance
City of Riverside
Principal Contact Phone
Steve Howard, Construction Project Manager (951) 826-5708
Price of Contract Dates
$2,376,001 7/2018 — 4/2019
Type of Work
Street Maintenance: Minor PCC, Asphalt Grind & Pave, Adjust Utilities
2. Proiect Name
Westminster Ave from Harbor Blvd. to Clinton St. & Clinton St. to Fairview St. Improvements
Owner
City of Santa Ana
Principal Contact Phone
Tyrone Chesanek, Principal Civil Engineer (714) 647-5074
Price of Contract Dates
$1,399,000 6/2018 — on -going
Street Maintenance: Minor PCC, Asphalt Grind & Pave, Adjust Utilities
3. Proiect Name
FY 2016/17 Annual Sidewalk Repair
Owner
City of Rancho Palos Verdes
Principal Contact Phone
James Flannigan, Asst Eng (310) 544-5295
Price of Contract Dates
$183,548 8/2017—10/2017
Tvoe of Work
Sidewalk Repairs, Grind SW Joints
4. Proiect Name
FY 2016/17 Annual Concrete Replacement
City of Orange
Principal Contact Phone
Matthew Lorenzen, Project Manager (714) 744-5566
Price of Contract Dates
$289,400 6/2017 — 9/2017
Tvoe of Work
Minor PCC— Curb & Gutter, Driveways, Cross Gutter, Sidewalk, Ramps
20C-34
3 YEAR REFERENCES — PUBLIC WORKS
S. Proiect Name
Palos Verdes Southbound Right Turn Lane at PCH
Owner
City of Redondo Beach
Principal Contact Phone
Didar Khander, P.E. (310) 318-0661 x 2456
Price of Contract Dates
$219,570 10/2017 — 7/2018
Construction of Right -Turn Lane: Minor PCC, Asphalt Grind & Pave, Adjust Utilities
6. Proiect Name
Citywide Pothole Repairs
Owner
City of Compton
Principal Contact Phone
John Strickland, Project Manager 310-761-1422
Price of Contract Dates
$640,000 9/2018—12/2017
Type of Work
Pothole Preparation, Asphalt Installation
20C-35
EXHIBIT 4
PROJECT 20-6956 & 20-6437
GAS TAX LOCAL STREET IMPROVEMENTS FY 19/20 AND FLOWER STREET SEWER MANHOLE
IMPROVEMENTS
This CONSTRUCTION CONTRACT is made and entered into this 21' day of January, 2020 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and
existing under the Constitution and laws of the State of California (hereinafter "CITY"), and EBS
General Engineering Inc. (hereinafter "CONTRACTOR").
WH'NESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the
satisfaction of the City Engineer of the CITY, the Gas Tax Local Street Improvements FY 19/20 and
Flower Street Sewer Manhole Improvements Project (hereinafter referred to as the "WORK OF
IMPROVEMENT") identified in and in accordance with the Contract Documents prepared by the
City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Two Million Five Hundred Forty -Six
Thousand One Hundred Fifty -Four Dollars and No Cents ($2,546,154.00), as set forth and identified
in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
20C-36
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
http://www.santa-ana.org/pwa/documents/CWA.pd
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
//
20C-37 Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
Cit:
51
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Acting Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
EBS General Engineering Inc.
NAME: homas Nanci
TITLE: President
20C-38
Page 3 of 3
EXHIBIT 5
COST ANALYSIS
CONSTRUCTION OF THE PROJECT NO. 20-6956 & 20-6437: GAS TAX LOCAL
STREET IMPROVEMENTS FY 19/20 AND FLOWER STREET SEWER MANHOLE
IMPROVEMENTS
Construction Contract
$
2,546,154.00
Contract Administration
$
165,936.00
Inspection and Testing
$
215,986.00
Contingencies
$
298,211.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$
3,226,287.00
20C-39