HomeMy WebLinkAbout20B - AA FOR HAZARD BIKE LANES PR NO. 18-6903REQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
MAY 5, 2020
TITLE:
APPROVE AN APPROPRIATION
ADJUSTMENT, AUTHORIZE A BUDGET
REALLOCATION, AND AWARD A
CONSTRUCTION CONTRACT TO HYM
ENGINEERING, INC. IN THE AMOUNT OF
$882,919, FOR THE HAZARD AVENUE
BIKE LANES PROJECT WITH AN
ESTIMATED TOTAL COST OF $1,081,000
(PROJECT NO. 18-6903)
(NON -GENERAL FUND)
/s/Kristine Ridge
CITY MANAGER
CLERK OF COUNCIL USE ONLY:
APPROVED
❑
As Recommended
❑
As Amended
❑
Ordinance on 1"Reading
❑
Ordinance on 2i1 Reading
❑
Implementing Resolution
❑
Set Public Hearing For_
CONTINUED TO
1�1��►1�1i!1:7q:7
RECOMMENDED ACTION
1. Approve an appropriation adjustment recognizing $935,000 in Fiscal Year 2018-19 Congestion
Mitigation and Air Quality (CMAQ) construction funds in the Select Street Construction, Federal
Grant -Indirect revenue account and reappropriating the same amount in Fiscal Year 2019-20
Select Street Construction, Improvements Other Than Building expenditure account.
2. Authorize reallocation of $18,000 in unspent Measure M2 Local Fairshare funds from the Bike
Lane Development Project (No. 19-6904) to the Hazard Avenue Protected and Class II Bike
Lanes Project (No. 18-6903), to fulfill the City matching funds requirement.
3. Award a construction contract to HYM Engineering, Inc., the lowest responsible bidder, in
accordance with the base bid in the amount of $882,919, for construction of Hazard Avenue
Bike Lanes Project, for the term beginning on May 5, 2020 and ending upon project completion,
and authorize the City Manager to execute the contract subject to non -substantive changes
approved by the City Manager and the City Attorney
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of $1,081,000,
which includes $882,919 for the construction contract; $109,741 for contract administration,
inspection and testing; and a $88,340 project contingency for unanticipated or unforeseen work.
DISCUSSION
On August 8, 2016, the Orange County Transportation Authority Board of Directors approved a list
of recommended projects to be funded by the 2016 Bicycle Corridor Improvement Program (BCIP)
recommended projects, which included $1,035,000 for the Hazard Avenue Bike Lanes project.
This project will install 0.65 miles of protected bike lanes and 0.45 miles of Class III bike route on
20B-1
Award Contract to HYM Engineering, Inc. for
Hazard Avenue Protected and Class III Bike Lanes
May 5, 2020
Page 2
Hazard Avenue from Euclid Avenue to Harbor Boulevard (Exhibit 1). This bicycle corridor passes
through a mix of land uses, such as residential, schools, and parks.
Grant funds in the amount of $100,000 were recognized in the Fiscal Year 2017-18 Capital
Improvement Program (CIP), which were used for Preliminary Engineering (Design) in FY 2017-
18, and $935,000 was recognized in the Fiscal Year 2018-19 CIP for Construction. However,
spending authorization for the $935,000 in Construction funding was not received until August
2019. Staff is requesting City Council approval to recognize and reappropriate this grant allocation
for expenditure in Fiscal Year 2019-20 to complete the bike lane project.
Staff also seeks approval for the reallocation of $18,000 of Measure M2 Local Fairshare funds to
meet the matching funds requirement of $146,000. Upon approval of the requested appropriation
adjustment and reallocation, the total funds available for construction will be $1,081,000, which is
comprised of $935,000 in grant funds, and $146,000 in the required local match.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised in
the Orange County Register newspaper on February 5 and February 12, 2020. The project was
also advertised in PlanetBids from February 5, 2020 through February 26, 2020. Bids were
received electronically via PlanetBids, on February 26, 2020.
A total of 382 vendors, including vendors in the City of Santa Ana, were notified of the project via
PlanetBids. Thirty vendors requested bidding documents and two bids were received. No bids
were received from Santa Ana contractors.
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
HYM Engineering, Inc.
Chino
$882,919
2
Vido Samarzich, Inc.
La Puente
$898,549
Both bids were responsive with HYM Engineering, Inc. submitting the lowest responsible bid in the
amount of $882,919 (Exhibit 2). Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to HYM Engineering, Inc. in the amount of
$882,919 (Exhibit 3).
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total project
delivery cost includes construction administration, inspection, and testing, along with an allowance
for contingencies to account for unexpected or unforeseen conditions. Construction administration
and inspection includes construction management; implementation of the City's Community
Workforce Agreement requirements; inspection of the Contractor's work to ensure contract
compliance, workmanship, and quality; and material testing. As indicated in the Cost Analysis
20B-2
Award Contract to HYM Engineering, Inc. for
Hazard Avenue Protected and Class III Bike Lanes
May 5, 2020
Page 3
(Exhibit 4) and as summarized in the table below, the estimated total construction delivery cost of
the project is $1,081,000.
Project Item
Grant
Funds
City
Match
Total
Amount
Construction Contract
$781,648
$101,271
$882,919
Construction Administration, Inspection, and
Testing
$97,153
$12,588
$109,741
Contingencies
$56,199
$32,141
$88,340
TOTAL CONSTRUCTION DELIVERY COST
$935,000
$146,000
$1,081,000
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 - Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe, and aesthetically pleasing for all users), and Strategy G (develop
and implement the City's Capital Improvement Program in coordination with the Community
Investment Plan (e.g., neighborhood streets, traffic improvements, park facilities, bike master plan,
etc.)).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are exempt
from further review. Categorical Exemption Environmental Review No. 2016-36 was filed for this
project.
FISCAL IMPACT
As indicated in the Cost Analysis (Exhibit 4), the estimated total delivery cost of this project is
$1,081,000, which includes construction contract, contract administration, inspection and testing,
and project contingency. Approval of the Appropriation Adjustment will recognize $935,000 in
Fiscal Year 2018-19 Congestion Mitigation and Air Quality (CMAQ) construction funds in the Select
Street Construction, Federal Grant -Indirect revenue account (No. 05917002-52001) and
reappropriate the same amount into the Select Street Construction, Improvements Other Than
Building expenditure account (No. 05917660-66220). The reallocation of $18,000 in unspent
Fiscal Year 2018-19 Measure M2 Local Fairshare funds will be available to fully fund the City's
$146,000 matching funds requirement.
r1-
Award Contract to HYM Engineering, Inc. for
Hazard Avenue Protected and Class III Bike Lanes
May 5, 2020
Page 4
The following table summarizes the funds budgeted to deliver construction of this project:
Fiscal Year
Accounting Unit-
Fund Description
Accounting Unit,
Amount
Account #
Account Descri tion
EXISTING PROJECT BUDGET
Measure M2 Local
FY 2019-20
03217662-66220
Measure M-Street
Fairshare,
$128,000
(18-6903)
Construction
Improvements Other
Than Building
APPROPRIATION ADJUSTMENT— REAPPROPRIATION
Select Street
FY 2019-20
05917660-66220
Select Street
Construction,
$935,000
(18-6903)
Construction
Improvements Other
Than Building
PROJECT BUDGET REALLOCATION
Measure M2 Local
FY 2019-20
03217662-66220
Measure M-Street
Fairshare,
$18,000
(18-6903)
Construction
Improvements Other
Than Building
Total:
$1,081,000
NS/MM/WEG
Exhibits: 1. Location Map
2. Bid Proposal
3. Construction Contract
4. Cost Analysis
City of Santa Ana
Page 1
Hazard Avenue Protected Bike Lanes (18-6903 (CML 5963(182))), bidding on February 26, 2020 2:00 PM (Pacific)
Printed 03/25/2020
EXHIBIT 2
Bid Results
Bidder Details
Vendor Name HYM Engineering, Inc.
Address 1559 W. Commonwealth Ave.
Fullerton, CA 92833
United States
Respondee Abraham Jean
Respondee Title President
Phone 714-523-2372 Ext.
Email ajeon@hymengineedng.com
Vendar Type
License #
CA DIR
Bid Detail
Bid Format Electronic
Submitted February 26, 2020 12:36:55 PM (Pacific)
Delivery Method
Bid Responsive
Bid Status Submitted
Confirmation # 203555
Ranking 0
Respondee Comment
Buyer Comment
Attachments
File Title
File Name
File Type
General
General.pdf
General Attachment
Ownership Affidavit
Ownership Affidavitpdf
Ownership Affidavit (Notary
Public) - REQ Original Hard
Copy Submittal in Addition
hid bond
hid bond.pdf
Bid Bond Guaranty (Notary
Public) - REQ Original Hard
Copy Submittal in Addition
Non Collusion
Non Collusion Affidavit.pdf
Non -Collusion Affidavit
(Notary Public) - REQ
Original Hard Copy Submittal
in Addition
Line Items
Type Item Cade UOM Qty Unit Price Line Total Comment
Section 1
1 Mobilization
LS 1 $50,000.00 $50,000.00
2 White Turn Lane Line ( Thin -mill) (COSA Detail 2)
LF 295 $1.50 $442.50
3 12" White Thermoplastic Stop Bar/Limit Line (Thermoplastic)
SF 180 $4.50 $810.00
120B-6
City of Santa Ana
Page 2
Hazard
Avenue Protected Bike Lanes (18-6903 (CML 5063(182))), bidding
on February 26, 2020 2:00 PM (Pacific)
Printed o3/25/2020
Bid Results
Type
Item Code UOM
City
Unit Price
Line Total Comment
4
Double Yellow (Thin -mill) (COSA Detail 4)
LF
655
$1.50
$982.50
5
Install Two way Left Turn Lane (COSA Detail 5)
LF
5050
$1.50
$7,575.00
6
Furnish and Install 2" PVC conduit and Stub -Out per plan
LF
150
$150.00
$22,500.00
7
6" White Bike Lane Line ( CT Detail 39)
LF
6200
$1.25
$7,750.00
8
6" Dashed White Bike Lane Line ( CT Detail 39-A)
SF
3370
$1.25
$4,212.50
9
Install 6" White Chevron or Diagonal Stripe
LF
230
$3.00
$690.00
10
Install Street Legends and Arrows (Thermoplastic)
EA
16
$90.00
$1,440.00
11
Remove Conflicting Striping (Grinding/Sandblasting)
LF
11250
$1.25
$14,062.50
12
Remove Legend (Grinding/Sandblasting)
EA
17
$80.00
$1,360.00
13
Bike Lane Legend (Detail "A") - Green MMA
EA
34
$860.00
$29,240.00
14
Merging Area (Detail'B") - Green MMA
SF
4000
$10.50
$42,000.00
15
Bike Sharrow Panel (Detail "C") (Green MMA)
EA
20
$450.00
$9,000.00
16
Install Curb Marking
LF
1394
$3.00
$4,182.00
17
Furnish and Install Type E Traffic Loop Detector (with DLC)
EA
29
$280.00
$8,120.00
18
Furnish and Install Type D Traffic Loop Detector (with DLC)
EA
13
$290.00
$3,770.00
19
Furnish and Install Type O Traffic Loop Detector (with DLC)
EA
7
$350.00
$2,450.00
20B-7
City of Santa Ana
Page 3
Hazard
Avenue Protected Bike Lanes (18-6903 (CML 5063(182))), bidding on
February 26,
2020 2:00 PM (Pacific)
Printed o3/25/2020
Bid Results
Type
Item Code UOM
Qty
Unit Price
Line Total Comment
20
Furnish and Install Raised Curb Median Island Treatment (per plan
Detail "L")
EA
4
$1,000.00
$4,000.00
21
12" White Thermoplastic Crosswalk Line, I V O.C. (Thermoplastic)
SF
1370
$4.50
$6,165.00
22
Furnish and Install New Sign and Pole
EA
27
$350.00
$9,450.00
23
Furnish and Install New Sign(s), only
EA
26
$255.00
$6,630.00
24
Furnish and Install New Sign(s), hack -to -hack, only
EA
17
$255.00
$4,335.00
25
Remove existing sign(s), only
EA
12
$16.00
$192.00
26
Remove existing sign(s) and Pole
EA
13
$30.00
$390.00
27
Cement Median Island (8" height Including Dowels)
CY
482
$1,185.00
$571,170.00
28
Traffic Control
LS
1
$50,000.00
$50,000.00
29
SWPPP NO. 1
LS
1
$10,000.00
$10,000.00
30
Labor Agreement Oversight
LS
1
$10,000.00
$10,000.00
Subtotal
$882,919.00
Total
$882,919.00
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: HYM Engineering, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
t
Unit
Unit Price
Amount
1
Mobilization
1
LS
$ �m, orce
$ Si v�
2
White Turn Lane Line ( Thin -mill)
295
LF
$ rr ,S D
$
(COSA Detail 2)
3
12" White Thermoplastic Stop Bar/Limit
180
SF
$ Y
$ g`0• o
Line (Thermoplastic)
4
Double Yellow (Thin -mill) (COSA Detail
655
LF
$
$ p8 j Sr
5
Install Two way Leh Turn Lane (COSA
5050
LF
$ /
$
Detail5)
6
Furnish and Install 2" PVC conduit and
150
LF
$ l�
$22js�
Stub -Out per plan
7
6" White Bike Lane Line (CT Detail 39)
6200
LF
$ /f
8
6" Dashed White Bike Lane Line ( CT
Detail 39-A)
3370
SF
$
%,
$ j'
Wy,
9
install 6" White Chevron or Diagonal
230
LF
$ 7l on
$ 690
Stripe
10
Install Street Legends and Arrows
16
EA
$
(Thermoplastic)
I 1
Remove Conflicting Striping
11250
LF
$
(Grinding/Sandblasting)
1 la
Remove Legend (Grinding/Sandblasting)
17
EA
$ go
$ / a
12
Bike Lane Legend (Detail "A") - Green
34
EA
$ bZa
$
MMA
13
Merging Area (Detail `B") - Green MMA
4000
SF
$ (0 S1%
$
Irl—ciT ri7
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
Item
Description
Qty
Unit
Unit Price
Amount
14
Bike Sharrow Panel (Detail "C") (Green
20
EA
$
$ C�
MMA)
15
Install Curb Marking
1394
LF
$ po
$ �gZ
16a
Furnish and Install Tyne E Traffic Loop
29
FA
$
p�
Detector (with DLC)
lJ,
16b
Furnish and Install Type D Traffic Loop
13
EA
$ �r%
$
Detector (with DLC)
16c
Furnish and Install Type O Traffic Loop
7
EA
$
$ ?z
Detector (with DLC)
17
Furnish and Install Raised Curb Median
Island Treatment (per plan Detail "L")
4
EA
$ /� O
$ oo a
18
12" White Thermoplastic Crosswalk Line,
1370
SF
$
$
I I' O.C. (Thermoplastic)
Y'5V
19
Furnish and Install New Sign and Pole
27
EA
$ y� 5V
$
20
Furnish and Install New Sign(s), only
26
EA
$ 2
$ 6 6 3O
21
Furnish and Install New Sign(s), back -to-
17
EA
$ 'JCS
$ 3 3S
back, only
22
Remove existing sign(s), only
12
EA
$ (_
$ �Z
23
Remove existing sign(s) and Pole
13
EA
$ 3p
$ 3�p
24
Cement Median Island (8" height,
Including Dowels)
482
CY
$ ! S
i
$ �/> f ���
25
Traffic Control
1
LS
$ / T coo
$ po b
26
SWPPP NO. I
1
LS
$ i� 0 p 1�
r
$ (/4 vo c�
27
Labor Agreement Oversight
1
LS
$ 10,000
$ 10,000
TOTAL BASE BID $ 919
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number (80) working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,600 per calendar day.
Name of Firm HYM Engineering, Inc.
Signature of BIDDER
Title President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
rI:
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
BIDDER'S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council
with her signature and official seal noting hereon the action of approval of the Council, signed by
the Public Works Agency Executive Director or his/her duly authorized agent, and signed by the
City Attorney, denoting his approval of the form of this document, and its execution, and when it
or an exact copy of it has been either delivered to BIDDER or deposited with the United States
Postal Service properly addressed to the BIDDER with the correct postage affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of damages
actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond
substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation under
the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Firm HYM Engineering, Inc.
Signature of BIDDER
Title President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
PTP1;
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
CONTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she and
all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: HYM Engineering, Inc.
Business Address: 1559 W. Commonwealth Ave. Fullerton, CA 92833
Business E-Mail Address: ajeon@hymengineering.com
Telephone: 714-523-2372
State Contractor's License No. and Class: 918130, A, B
License Expiration Date: 1 /31 /2021
State Dept. of Industrial Relations (DIR)
Registration No.: 1000008232
State Dept. of Industrial Relations (DIR)
Registration Expiration Date:
Signed:
Title: President
6/30/2021
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well as
California Code of Regulations, Title 8, Section 16,000, et seq., ("Prevailing Wage Laws"), which
require the payment of prevailing wage rates and the performance of other requirements on "public
works" and "maintenance" projects. Since the services are being performed as part of an applicable
"public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and since the
total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing
Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the
commencement of this Agreement. Contractor shall make copies of the prevailing rates of per
diem wages for each craft, classification or type of worker needed to execute the services available
to interested parties upon request, and shall post copies at the Contractor's principal place of
business and at the project site.
Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and
agents free and harmless from any claim or liability arising out of any failure or alleged failure to
comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct.
Name of Firm HYM Engineering, Inc.
Signature of BIDDER
Title President
(if an individual, so state)
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
OWNERSHIP AFFIDAVIT
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS:
CITY OF SANTA ANA )
Abraham Jaewoo Jeon ,being duly sworn, deposes and says:
❑ INDIVIDUAL That he/she is the parry making the foregoing proposal:
❑ PARTNERSHIP That he/she is a member of the co -partnership firm designated as:
and who has been and is duly vested with the authority to make and execute instruments
for the co -partnership by:
who constitute the other members of the co -partnership.
® CORPORATION Thathe is of., President
a corporation which is making the foregoing proposal:
❑ JOINT VENTURE That he is of:
one of the parties making the foregoing proposal as ajoint venture, and the he/she has been
and is duly vested with the authority to execute instruments for an on behalf of the parties
making said bid who are:
that such a bid is genuine and not collusive or sham, and has not in any manner sought by collusion
to secure any advantage against the City of Santa Ana or any person interested in the proposed
contract, for himself or any other person.
Signature of Bidder
Subscribed and sworn to before me this 25 day of Feb. 2020
Signature of officer Administering Oath (Notary Public)
HI80N KIM
Notary Public • California
•� - orange County E
Commission t 22"196
My Comm. Expires Jul 18, 2023
P.PPliP
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
KNOW ALL PRESENT that,
as BIDDER, and
as SURETY,
are held and firmly bound unto the CITY OF SANTA ANA, as AGENCY, in the penal sum of
Dollars ($ ), which is ten percent (10%)
of the total amount bid by BIDDER to AGENCY for the above -stated project, for the payment of
which sum, BIDDER and SURETY agree to be bound, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas BIDDER is about to
submit a bid to AGENCY for the above -stated project, if said bid is rejected, or if said bid is
accepted and a contract is awarded and entered into by BIDDER in the manner and time specified,
then this obligation shall be null and void, otherwise it shall remain in full force and effect in favor
of AGENCY.
IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seal this
day of f 20_. // I
BIDDER* UD ( OGtd� 11'1 101Al�tt i
SURETY*
Subscribed and sworn to before me this day of
120.
Signature:
Notary Public in and for the County of State of
* Provide BIDDER/ SURETY name, address, and telephone number and the name, title, address,
and telephone number of authorized representative.
r�-
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
LIST OF SUB -CONTRACTORS
Section 4100 et. seq. of the Public Contract Code requires listing of all subcontractors with the bid for all
subcontract work exceeding the following amount:
o Streets, highways including bridge projects: '/z% of the bid or $10,000, whichever is greater
o Buildings, parks, or other projects: '/2% of the bid
Section 1725.5 of the Public Contract Code requires all Subcontractors be registered with the State
Department of Industrial Relations (DIR).
BIDDER proposes to subcontract certain portions of the work to the firms listed below:
Name
License
DIR Reg
Location
Phone
Type Of
Amount
Name
License #/Exp.
DIR Reg. #/Exp.
License # _
Location _
Phone
Type Of Work
Amount $
Name
License #/Exp,
DIR Reg. #/Exp.
License # _
Location _
Phone
Type Of Work
Amount $
Signature of Bidder
Name "Pfv C",,
License #/Exp.
317$6do
DIR Reg. #/Exp.
/00000!
Location
loom
Phone —
Type Of Work
Amount $
/
Name
License #/Exp.
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
I16M"11
License #/Exp.
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
City of Anaheim / 200 S. Anaheim Blvd. Anaheim, CA
Name and Address of Owner.
David Sanchez / 714-765-5100
Name and Telephone Number of person familiar with project.
$ 872,203.72 Improvement street and traffic signal improvement May. 2019
Contract Amount Type of Work Date Completed
2. City of Anaheim / 200 S. Anaheim Blvd. Anaheim, CA
Name and Address of owner.
Thomas Bekele / 714-765-4937
Name and Telephone Number of person familiar with project.
$ 166.917.50 Street Intersection improvement Aug. 2019
Contract Amount Type of Work Date Completed
3. City of Whittier / 13230 Penn Street Whittier, CA 90602
Name and Address of owner.
Isaac Bravo / (562)567-9518
Name and Telephone Number of person familiar with project.
$ 309,409.00 Improve trail walkway and fences and shade structure Oct. 2019
Contract Amount Type of Work Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
AMERICAN CONTRACTORS INDEMNITY COMPANY
7
MAIN: (714) 516-1232
Orange CA gP867
D AGENCY
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
County of Orange / 601 N Ross St, Santa Ana, CA 92701
Name and Address of Owner.
Richard De Jong / (714) 667-4966
Name and Telephone Number of person familiar with project.
$ 141 ,653.57 grading, CMU wall, steel structure and concrete July. 2019
Contract Amount Type of Work Date Completed
2. Caltransl2 / 6681 Marine Way, Irvine, CA 92618
Name and Address of owner.
Dennis Yum / (714) 641-4730
Name and Telephone Number of person familiar with project.
$ 484.935.00 Slope paving and Minor Concrete Work Aug. 2019
Contract Amount Type of Work Date Completed
3. Caltransl2 / 6681 Marine Way, Irvine, CA 92618
Name and Address of owner.
Dennis Yum / (714) 641-4730
Name and Telephone Number of person familiar with project.
$ 658,956.60 Slope paving, Rock Blanket and Minor Concrete Work Sep. 2019
Contract Amount
Type of Work
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
AMERICAN CONTRACTORS INDEMNITY COMPANY
801 S FIGUEROA STREET SUITE 700
CA 5UU1
CSBA — COMMERCIAL SURETY BOND AGENCY
1411 N. Batavia St., Suite 201
MAIN: (714) 516-1232
Orange. CA 92867
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
NON -COLLUSION AFFIDAVIT
(Title 23 United States Code Section H 2 and Public Contract Code Section 7106)
In conformance with Title 23 United States Code Section 112 and Public Contract Code 7106 the
BIDDER declares that the bid is not made in the interest of, or on behalf of, any undisclosed
person, partnership, company, association, organization, or corporation; that the bid is genuine and
not collusive or sham; that the BIDDER has not directly or indirectly induced or solicited any other
BIDDER to put in a false or sham bid, and has not directly or indirectly colluded, conspired,
connived, or agreed with any BIDDER or anyone else to put in a sham bid, or that anyone shall
refrain from bidding; that the BIDDER has not in any manner, directly or indirectly, sought by
agreement, communication, or conference with anyone to fix the bid price of the BIDDER or any
other BIDDER, or to fix any overhead, profit, or cost element of the bid price, or of that of any
other BIDDER, or to secure any advantage against the public body awarding the contract of anyone
interested in the proposed contract; that all statements contained in the bid are true; and, further,
that the BIDDER has not, directly or indirectly, submitted his or her bid price or any breakdown
thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will
not pay, any fee to any corporation, partnership, company association, organization, bid
depository, or to any member or agent thereof to effectuate a collusive or sham bid.
Note: The above Non -collusion Affidavit is part of the Proposal. BIDDERS are cautioned
that making a false certification may subject the certifier to criminal prosecution.
Signed
State of California
County of Oranae
Subscribed and sworn to (or affirmed) before me on this 25 day of Feb. , 202Q by
Abraham Jaewoo Jeon , proved to me on the basis of satisfactory evidence to be the person(s)
who appeared before me
NISON NIM
5 Notary Public -California
Orange County
Commission X 149l196
My Comm. Expires Jul 1L, 20T3
Notary Public Signature Notary Public Seal
II M. 1
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf
of the Contractor, state that all qualified applicants will receive consideration for employment
without regard to race, color, religion, sex, or national origin.
The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
The Contractor shall furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant
thereto, and will permit access to his/her books, records, and accounts by the administering
agency and the Secretary of Labor for purposes of investigation, to ascertain compliance with
such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible for
further Government contracts or federally assisted construction contracts in accordance with
procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as otherwise
provided by law.
I91'
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless
exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section
204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding
upon each subcontract or purchase order as the administering agency may direct as means of
enforcing such provisions, including sanctions for noncompliance; provided, however, that in
the event the Contractor becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as a result of such direction by the administering agency, the
Contractor may request that the United States enter into such litigation to protect the interests
of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation of the Chapter.
Signed:
Title: President
Firm: HYM Engineering, Inc.
Date: 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
1. Apply to the joint apprenticeship committee administering the apprenticeship standards of the
craft or trade in the area of the site of the public work for a certificate approving the contractor
under the apprenticeship standards for the employment and training of apprentices in the area
or industry affected.
2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
3. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like amount to the California Apprenticeship Council.
Signed:
Title: President
Firm: HYM Engineering, Inc.
Date: 2/26/2020
rIJ-
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
STATEMENT REGARDING "ANTI -KICKBACK" REQUIREMENTS
The undersigned is submitting this proposal for performing by contract the work required by these
bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repair of public work, to give up any part of the compensation to
which he/she is otherwise entitled.
Signed:
Title: President
Firm: HYM Engineering, Inc.
Date: 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
PUBLIC CONTRACT CODE SECTION 10162 OUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented from
bidding on, or completing a federal, state, or local government project because of a violation of
law or a safety regulation?
Yes No X
If the answer is yes, explain the circumstances in the following space
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
BIDDER'S STATEMENT REGARDING REQUIRED FEDERAL CONTRACT PROVISIONS
(FORM FHWA-1273)
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, agrees to comply with the required Federal Contract Provision (Form FHWA-
1273) as shown in the appendix of the Special Provisions of this project.
Signed
Title President
Firm HYM Engineering, Inc.
Date 2/26/2020
I
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
The bidder HYM Engineering, Inc.
proposed subcontractor Y ALC- (pups Cr, l�g1 hereby
certifies that he has , has not x , participated in a previous contract or subcontract subject
to the equal opportunity clauses, as required by Executive Orders 10925, 11114, or 11246, and
that, where required, he has filed with the Joint Reporting Committee, the Director of the Office
of Federal Contract Compliance, a Federal Government contracting or administering agency, or
the former President's Committee on Equal Employment Opportunity, all reports due under the
applicable filling requirements.
Note: The above certification is required by the Equal Employment Opportunity Regulations of
the Secretary of Labor (41 CFR 60-1.7(b) (1)), and must be submitted by bidders and
proposed subcontractors only in connection with contracts and subcontracts which are
subject to the equal opportunity clause. Contracts and subcontracts which are exempt
from the equal opportunity clause are set forth in 41 CFR 60-1.5. (Generally only
contracts or subcontracts of $10,000 or under are exempt.)
Currently, Standard Form 100 (EEO-1) is the only report required by the Executive
Orders or their implementing regulations.
Proposed prime contractors and subcontractors who have participated in a previous contract or
subcontract subject to the Executive Orders and have not filed the required reports should note
that 41 CFR 60-1.7(b) (1) prevents the award of contracts and subcontracts unless such
contractor submits a report covering the delinquent period or such other period specified by the
Federal Highway Administration or by the Director, Office of Federal Contract Compliance,
U.S. Department of Labor.
Signed
Title President
Firm HYM Engineering, Inc.
Date 2/26/2020
W,-
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
PUBLIC CONTRACT CODE SECTION 10285.1 STATEMENT
In conformance with Public Contract Code Section 10285.1 (Chapter 376, Stats. 1985), the
bidder hereby declares under penalty of perjury under the laws of the State of California that the
bidder has _ , has not x been convicted within the preceding three years of any offenses
referred to in that section, including any charge of fraud, bribery, collusion, conspiracy, or any
other act in violation of any state or Federal antitrust law in connection with the bidding upon,
award of, or performance of, any public works contract, as defined in Public Contract Code
Section 1101, with any public entity, as defined in Public Contract Code Section 1100, including
the Regents of the University of California or the Trustees of the California State University.
The term "bidder" is understood to include any partner, member, officer, director, responsible
managing officer, or responsible managing employee thereof, as referred to in Section 10285.1.
Note: The bidder must place a check mark after "has" or "has not" in one of the blank spaces
provided. The above Statement is part of the Proposal. Signing this Proposal on the
signature portion thereof shall also constitute signature of this Statement. Bidders are
cautioned that making a false certification may subject the certifier to criminal
prosecution.
Signed
Title President
Firm HYM Engineering, Inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
PUBLIC CONTRACT CODE SECTION 10232 STATEMENT
In conformance with Public Contract Code Section 10232, the Contractor, hereby states under
penalty of perjury, that no more than one final unappealable finding of contempt of court by a
federal court has been issued against the Contractor within the immediately preceding two year
period because of the Contractor's failure to comply with an order of a federal court which orders
the Contractor to comply with an order of the National Labor Relations Board.
Note: The above Statement and Questionnaire are part of the Proposal. Signing this
Proposal on the signature portion thereof shall also constitute signature of this
Statement and Questionnaire.
Bidders are cautioned that making a false certification may subject the certifier to
criminal prosecution.
Signed
Title President
Firm HYM Engineering, Inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
TITLE 49, CODE OF FEDERAL REGULATION, PART 29 DEBARMENT AND SUSPENSION
CERTIFICATION
The bidder under penalty of perjury, certifies that except as noted below, he/she or any person
associated therewith in the capacity of owner, partner, director, officer, manager:
is not currently under suspension, debarment, voluntary exclusion, or determination of
ineligibility by any federal agency;
has not suspended, debarred, voluntarily excluded, or determined ineligible by any federal
agency within past three years;
has not been indicted, convicted, or had a civil judgment rendered against it by a court of
competent jurisdiction in any matter involving fraud or official misconduct within the past 3
years.
If there are any exceptions to this certification, insert the exceptions in the following space.
Exceptions will not necessarily result in denial of award, but will be considered in determining
bidder's responsibility. For any exception noted above, indicate below to whom it applies, initialing
agency, and dates of action.
Note: Providing false information may result in criminal prosecution or administrative sanctions.
The above certification is part of the Proposal. Signing this Proposal on the signature portion thereof
shall also constitute signature of this Certification.
Signed
Title President
Fire, HYM Engineering, Inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
NON -LOBBYING CERTIFICATION FOR FEDERAL AID CONTRACTS
The prospective participant certifies, by signing and submitting this bid or proposal, to the best of
his or her knowledge and belief, that:
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the
undersigned, to any person for influence or attempting to influence an officer or
employee of Congress, or an employee of a Member of Congress in connection
with the awarding of any Federal contract, the making of any Federal grant, the
making of any Federal loan, the entering into of any cooperative agreement, and the
extension, continuation, renewal, amendment or modification of any Federal
contract, grant, loan, or cooperative agreement.
(2) If any funds other than Federal appropriate funds have been paid or will be paid to
any person for influencing or attempting to influence an officer or employee of any
Federal agency, a Member of Congress, an officer or employee of Congress, or an
employee of a Member of Congress in connection with this Federal contract, grant,
loan, or cooperative agreement, the undersigned shall complete and submit Standard
Form-LLL, "Disclosure of Lobbying Activities," in accordance with its instructions.
This certification is a material representation of fact upon which reliance was placed when
this transaction was made or entered into. Submission of this certification is a prerequisite for
making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person
who fails to file the required certification shall be subject to a civil penalty of not less than $10,000
and not more than $100,000 for each such failure.
The prospective participant also agrees by submitting his or her bid or proposal that he or
she shall require that the language of this certification be included in all lower tier subcontracts,
which exceed $100,000 and that all such sub -recipients shall certify and disclose accordingly.
Signed
Title President
Firm HYM Engineering, Inc.
Date 2/26/2020
• Standard Forni LLL may be obtained from Caltrans and FHWA offices.
r�-
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
DISCLOSURE OF LOBBYING ACTIVITIES
DISCLOSURE OF LOBBYING ACTIVITIES Apploredby ONa
Complete this form to disclose lobbying activities pursuant to 31 U.S.G. 1352 034510W
Mee reverse for cublic burden disclosure-1
C Type of Federal Action_
2. Status of Federal Action:
3. Report Type -
Fa a_ contract
®a. bidlotferlapplication
®a. initial filing
b_ grant
b. initial award
b. material change
c. cooperative agreement
c. post -award
For Material Change Only:
d. loan
year quarter
e. ban guarantee
dare of last report
f, loan insurance
4_ Name and Address of Reporting Entity:
5. N Reporting Entily in No. 4 is a Subawardee, Enter Name
EI prate ❑ swswaruea
and Address of Prime:
Tier , ifknown:
N/A
Congressional District, if known:
Congressional District, if krlO
6. Federal DepartmenflAgency:
7. Federal Program NamelDescription:
N/A
N/A
CFDA Number, if applicable:
S_ Federal Action Number, if known: N/A
9. Award Amount, if known: N/A
$
10. a_ Name and Address of Lobbying Enffty b. Individuals Perforating Services (including address if
(if individual• last name• fast name, ml): different from No. 10a)
(last name, fast name, Ml):
N/A N/A
'�CarA Canaa luamn a SF4I" j"Rassfillm
1 t. Amount of Payment (check all that apply):
13. Type of Payment (check all Mat apply):
s N/A ❑ actual ❑ w—1
❑ a ratatner
N/A
12. Font of Payment I check aA that apply}
❑ C. clNm Wca
❑ a ca m N/A
Elon d cltngaut I-
❑ 0.1M1IINt: apedry: nature
❑ c. tladarretl
value
❑ T. other: specry:
14. Brief Description of Services Performed or to be Performed and Datefs) of Service, including otbcer(s),
employeefs), or Member(s) contacted, for Payment Indicated in Item 11:
N/A
amm conll s X
15. Continuation SheetIs I IND
16_ "e�"'a�° say. r ram r .maea he m s u ac ..s
hMT. Yip ama. d BbrNg dYap 6 . e1�Y � M f"t
Signature:
Print Name: Abraham Jeon
Title: President
wanr.n r h.,.ate"r c.p�...w.ry r r err P
Telephone No_ 714-523-2372
Date:2 26 202
Federal Use Only:
AullccUacW lava RepoaMal,
sweat/ Farm uu- Pt . 7
W:
, USMA
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
INSTRUCTIONS FOR COMPLETION OF SF-LL, DISCLOSURE OF LOBBYING
ACTIVITIES
INSTRUCTIONS FOR COMPLETION OF SII DISCLOSURE OF LOBBYING ACTIVITIES
Tinto mscrosae mrrn shal be mnpleled by the rep«tlng emby, aTemLr s tlurardee or p Tne Federal rempenC at the Inalatl«i «receipt a a eorereei FemerJ
aMo n, «a n lrnLage m a pnEv" fling, PX%t m Me 31 U.S.C. SeCUbn 1352. Tile ding or a iCrin Is requiredta eami payment« agrCLYalertlm nose
palmenttr any lbbeyng entflyw. Irrlwang a almalplrig to tmuenue an dincerWM;IIDyeed any agency,. a Mffnber or Ca9. an amlCer a efirpmyeea
COngms6,« an empldyeea a Membef Of CCngM In banEV• do MM a MWM Federal adorn. Use me SFLLtf. CdnbnllalmnSnM txradubdla rmvmadcntt
the space an Me lbrrn Is rzdeq w Campiete as neat& Tat apply la bom Te Intaa like and nn8enal deinge nepnrt Rely m are nlplemeMrg gtklance
pnbilmled by Me OIM1ce a Managetnent aM eudget mr adOnmlai Inmrnralan.
1. menliry ale 1Jpe a COIEretl Federd acaon mr r6ticd lobbying xdvtty o almbr Has been rmmred m a111nBlde ale burcpne m a cduvrd Federd agnrL
2. foerdly ere gams a the [Liles FetlHal admlL
3, genafy me apprgdae das[caacn a iNs report. tt t1Ys o a idloalp rep«[ cdused ay a rnaeedaotial¢ n ale IrrldrrnallIXr PreMiaely M1poled, 2mer
action,
yeaanm gierrerIn wTK119he vurlrKR omclezed. mar the data or melastprewousysubmmed rep«[by 11t6n artlng scary rot 1Ns oauded Fc[mr'a
aa1LYl.
a. Enter ale btI frame, address, cey. Stale am2p Mcea ale feponngenvty. Inonme Cagreseenia Distinct a innbn. Giect. are apprbpnalemassmratlm
a ale lepaan9 erratytut decxF,a�arr n fb, a expeet6n De, a price «sabaaardrLaplen[.Ilyentnydleter a ale 6ioaarmdee, a g., fie nrat.wbawadee
a In¢ p1h»e o. Te n6t ter. 5[tM#Y� [dame C1rt are rid Inlaetl m SmbCdntad6. 6cExjdrltb a16 O]nildw armada finder grave.
5. It Te crrpnlzylm ning tie nepon In h a drebes then eons ale N1 name. a i2ess, dly. siXe and zlp come a tie prl n Fer3era
1e0p1«IL lnW ude CtlngresNmat otsmct, a li n .
5. Enter the nine or the Federd agency mabngthe as or loan dbn nnnem brddde a< Mast one drgalliatlglall¢YHaMb'rdgenbyname. b Nbvm. Fm
example, oepannnern Of Transpbraum, armed states Coast Ouam
i. Enter ME Fecl"pidJ3nl namedr 006Cnpan Mr Me cawasFecie" adbn(tem 1 k 61[lV enw ME Ul Calamg a Federd Dolmobc Assonance
SCFIMA nunbrf Jar grins, mopelatNe agreement; m &n and man caorvnlh r .
8. Enter ale Host 2ppmplato FederN manarying nizn a aMataxsr« the Federal acfon mmdacdm Hem 1 1p ¢. Request [ Proposal {RFP) n per,
nwtawn mr am jlm6 [unmet; grant annourcemem nutrta . ME aontraa, grant, m man a m mm,,,, me appIw lmrtgroposatoorrbd rssrGbr
asslgr d by ME Federal agency][dude preRxec, e.g.,'RFP-DE l'
a. Fbf a CmMERa Federal adorn vnere here has OEM an aaad« loan CClnrtll tby me FEOeral agency, enter me Federal annnrn d are arvarmloan
C«mabnenl for ale Prime enMy mefntlem n Hem a « S
10_ I,a) mla me NI name, admrms, dty. Stme, and alp c*ae a Bhe mbbyng entry, engaged by one repbtlrg enbq Imenaaeci in nem a m mfl 1 the ob'renm
Feaera adorn.
(b) F11h'i me NI names mme In&Almalts}pe nag seraccs, and Irrdtxle awl airiness it dbrerent rrorn 10(4 Enter Lab Name. FIR' Name arm!
Uwe INbal Jul).
1[. MEErye hakdbwniame 4anpaar ME bentame 1pededmmeP a paes,= appry.ttMineenai" ige retem enze[eixinr.Hller
Mypaynlannas been made (atTralt « vwe ce made {µanrreoJ. c[lert al boxes mix apply. it ors m a [simian dwge repdt sorer the mlmtlaave
scant a palms[ made a planned m be [mile.
12_Checi, me app"natebor(es). GreCe all baaesMat apply. It palTMntis name a gn an m-mw conv0 bn. specdy the nature and valor ddie YI�[rld
pay*
13. ChecR the appropriate boXee;l. Chefs an boxes Tan apply. IS duet, spedfy, n01ue.
14. Prnxwtlea spedllc afn detaleaomeeplpllona the sernces Tat me IPdmr16C tab pnafomreA, a WI. me OpeCRmm perxxm, and ate tlate(sj a any cerMice6
OnMy s) contacted
pre ME Mineral,
as , ernp aeglo). rid Mb [tie g bn o acTa ennraa wtta Fem3d OIIICL11s. menbry Ire fedNal oTkxa{s1 «
ennpbyege) arrbctem «me driar;s.L unpldyegsl a Mrtmcerye) a cmxjefi6 that were eanlx[ed.
15. Ched wtrcglta « rid a SF-LLLA. Cidllnitalbn sheens} Is aaxyled.
18. The sonny rrg dtldal airdl sign anm dabs me noon, pdrm rtr Len name. sae. arm Wiepinne nunher
Ao=cWq to the Papertort RedcabnAa as. anmendelt rim persons am regwWto resp" m a Oalleclmn a bso art oniess n[splays a Mom Wa t]dnrd
Nntrb«. The vane Wel Catbd n=W mr 1Iils memmoMn cc la.sdn IS OMB no. m3/8-W16 Putim repwbtig brsden 1« Me caeedmn a idolmaaon a'
l6tn'la emm "ffage 30 a nae6 Per Rspdn In4alOrlg ame Tar Rweang mebr[bimns. seamMg emsong mi;& d raes4 gang and maintaining the data
rMcdem and completing aM reviewing Te cLr m of Irnpmmlon. Send (drrrnFTm F gaimi g ire burmen estimate « any airs mped a To Ebeecean a
bROrTatlM, nPidmng iniggel a ns lbl mm[C1g no g n, lO Me Olace a maragementaW @ddjeL Palo r � PTMECt (d]a&dMfi), W36rVrgron,
DC 20503.
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EXHIBIT 15-G CONSTRUCTION CONTRACT DBE COMMITMENT
1. Local Agency: City of Santa Ana 2. Contract DBE Goal:
3. Project Description: Hazard Avenue Protected Bike Lanes
4. Project Location:
n Euclid Street to Harbor Bc
5. Bidder's Name: HYM Enalneerinp Inc. 6. Prime Certified DBE: 0 7. Bid Amount:
8. Total Dollar Amount for ALL Subcontractors:
9. Total Number of ALL Subcontractors:
z
10. Bid
Item
Number
11. Description of Work, Service, or Materials
Supplied
12. DBE
Certification
Number
13. DBE Contact Information
(Must be certified on the dale bids are opened)
14. DBE
Dollar
Amount
1119,
6~& work
38719
APAWMJ&u,,l
(� 16&
-rofpc Loop,
38033
ltj� -Jah ge4 01 714-,�04Ai
A4 goo
Local Agency to Complete this Section
$ /�
21. Local Agency Contract Number:
22. Federal -Aid Project Number: CML 5063 (182)
23. Bid Opening Date: February 26, 2020
15. TOTAL CLAIMED DBE PARTICIPATION
D2 .y
24. Contract Award Date:
IMPORTANT: Identify all DBE firms being claimed for credit,
regardless of tier. Names of the First Tier DBE Subcontractors and
25. Award Amount:
_
their respective item(s) of work listed above must be consistent,
where applicable with the names and Items of the work in the
"Subcontractor List" submitted with your bid. Written confirmation of
each listed DBE Is required.
Local Agency certifies that all DBE certifications are valid and information on
this form is complete and accurate.
2/26/2020
26. Local Agency Representative's Signature 27. Date
16. Preparer's Signature 17. Date
Abraham Jeon 714-523-2372
28. Local Agency Representative's Name 29. Phone
18. Preparer's Name 19. Phone
President
30. Local Agency Representative's Title
20. Preparer's Title
DiSiRiou iON; i. ungmai - Local Agency
2. Copy - Caltrans District Local Assistance Engineer (DLAE). Fallure to submit to DLAE within 30 days of contract
execution may result in de -obligation of federal funds on contract.
3. Include additional copy with award package.
ADA Notice: For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-
6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95B14.
141
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
INSTRUCTIONS - CONSTRUCTION CONTRACT DBE COMMITMENT
CONTRACTOR SECTION
1. Local Agency - Enter the name of the local agency that is administering the contract.
2. Contract DBE Goal - Enter the contract DBE goal percentage as it appears on the project advertisement.
3. Project Location - Enter the project location(s) as it appears on the project advertisement.
4. Project Description - Enter the project description as it appears on the project advertisement (Bridge Rehab,
Seismic Rehab, Overlay, Widening, etc).
5. Bidder's Name - Enter the contractor's firm name.
6. Prime Certified DBE - Check box if prime contractor is a certified DBE.
7. Bid Amount - Enter the total contract bid dollar amount for the prime contractor.
8. Total Dollar Amount for ALL Subcontractors — Enter the total dollar amount for all subcontracted contractors.
SUM = (DBEs + all Non -DBEs). Do not include the prime contractor information in this count.
9. Total number of ALL subcontractors — Enter the total number of all subcontracted contractors. SUM = (DBEs
+ all Non -DBEs). Do not include the prime contractor information in this count.
10. Bid Item Number - Enter bid item number for work, services, or materials supplied to be provided.
11. Description of Work, Services, or Materials Supplied - Enter description of work, services, or materials to be
provided. Indicate all work to be performed by DBEs including work performed by the prime contractor's own
forces, if the prime is a DBE. If 100% of the item is not to be performed or furnished by the DBE, describe the exact
portion to be performed or furnished by the DBE. See LAPM Chapter 9 to determine how to count the participation
of DBE firms.
12. DBE Certification Number - Enter the DBE's Certification Identification Number. All DBEs must be certified
on the date bids are opened.
13. DBE Contact Information - Enter the name, address, and phone number of all DBE subcontracted contractors.
Also, enter the prime contractor's name and phone number, if the prime is a DBE.
14. DBE Dollar Amount - Enter the subcontracted dollar amount of the work to be performed or service to be
provided. Include the prime contractor if the prime is a DBE. See LAPM Chapter 9 for how to count full/partial
participation.
15. Total Claimed DBE Participation - $: Enter the total dollar amounts entered in the "DBE Dollar Amount"
column. %: Enter the total DBE participation claimed ("Total Claimed DBE Participation Dollars" divided by item
"Bid Amount"). If the total % claimed is less than item "Contract DBE Goal," an adequately documented Good
Faith Effort (GFE) is required (see Exhibit 15-H DBE Information - Good Faith Efforts of the LAPM).
16. Preparer's Signature - The person completing the DBE commitment form on behalf of the contractor's firm
must sign their name.
17. Date - Enter the date the DBE commitment form is signed by the contractor's preparer.
18. Preparer's Name - Enter the name of the person preparing and signing the contractor's DBE commitment form.
19. Phone - Enter the area code and phone number of the person signing the contractor's DBE commitment form.
20. Preparer's Title - Enter the position/title of the person signing the contractor's DBE commitment form.
LOCAL AGENCY SECTION
21. Local Agency Contract Number - Enter the Local Agency contract number or identifier.
22. Federal -Aid Project Number - Enter the Federal -Aid Project Number(s).
23. Bid Opening Date - Enter the date contract bids were opened.
24. Contract Award Date - Enter the date the contract was executed.
25. Award Amount — Enter the contract award amount as stated in the executed contract.
26. Local Agency Representative's Signature - The person completing this section of the form for the Local
Agency must sign their name to certify that the information in this and the Contractor Section of this form is
complete and accurate.
27. Date - Enter the date the DBE commitment form is signed by the Local Agency Representative.
28. Local Agency Representative's Name - Enter the name of the Local Agency Representative certifying the
contractor's DBE commitment form.
29. Phone - Enter the area code and phone number of the person signing the contractor's DBE commitment form.
30. Local Agency Representative Title - Enter the position/title of the Local Agency Representative certifying the
contractor's DBE commitment form.
? of A
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EXHIBIT 15-H DBE INFORMATION — GOOD FAITH EFFORTS
DBE INFORMATION - GOOD FAITH EFFORTS
Federal -aid Project No. �CML 5063 (182) Bid Opening Date February 26, 2020
The City of Santa Ana established a Disadvantaged Business Enterprise (DBE) goal of 16 % for this
contract. The information provided herein shows the required good faith efforts to meet or exceed the DBE
contract goal.
Proposers or bidders submit the following information to document their good faith efforts within five (5)
business days from bid opening. Proposers and bidders are recommended to submit the following information
even if the Exhibit 10-01: Consultant Proposal DBE Commitments or Exhibit 15-G: Construction Contract DBE
Commitment indicate that the proposer or bidder has met the DBE goal. This form protects the proposer's or
bidder's eligibility for award of the contract if the administering agency determines that the bidder failed to meet
the goal for various reasons, e.g., a DBE firm was not certified at bid opening, or the bidder made a mathematical
error.
The following items are listed in the Section entitled "Submission of DBE Commitment" of the Special
Provisions, please attach additional sheets as needed:
A. The names and dates of each publication in which a request for DBE participation for this
project was placed by the bidder (please attach copies of advertisements or proofs of
publication):
Dates of
B. The names and dates of written notices sent to certified DBEs soliciting bids for this project
and the dates and methods used for following up initial solicitations to determine with
certainty whether the DBEs were interested (please attach copies of solicitations, telephone
records, fax confirmations, etc.):
Names of DBEs Solicited Date of Initial Follow Up Methods and Dates
Solicitation
California Professional Engineering, Inc. 2/25/2020 email and phone 2/26/2020
Traffic Loops Crackfilling, Inc. email and phone /2020
tr -
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
C. The items of work made available to DBE firms including those unbundled contract work
items into economically feasible units to facilitate DBE participation. It is the bidder's
responsibility to demonstrate that sufficient work to facilitate DBE participation in order to
met or exceed the DBE contract goal.
Items of Work Bidder Normally Breakdown of Amount Percentage
Performs Item (Y/N) Items ($) Of
Contract
Concrete Y 1,2}� z�� y�6���v 29y-
i�
E.
F
The names, addresses and phone numbers of rejected DBE firms, the reasons for the bidder's
rejection of the DBEs, the firms selected for that work (please attach copies of quotes from
the firms involved), and the price difference for each DBE if the selected firm is not a DBE:
Names, addresses and phone numbers of rejected DBEs and the reasons for the bidder's
rejection of the DBEs:
jyobe-
Names, addresses and phone numbers of firms selected for the work above:
Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining
information related to the plans, specifications and requirements for the work which was
provided to DBEs:
HYM sent email and send plan and specs.
email again to know bidding status
Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining
bonding, lines of credit or insurance, necessary equipment, supplies, materials, or related
assistance or services, excluding supplies and equipment the DBE subcontractor purchases or
leases from the prime contractor or its affiliate:
NnnP
0
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
H. The names of agencies, organizations or groups contacted to provide assistance in contacting,
recruiting and using DBE firms (please attach copies of requests to agencies and any
responses received, i.e., lists, Internet page download, etc.):
Name of Method/Date of Results
Agency/Organization Contact
Caltrans District 12 Internet/2/25/2020 no need response
b Qc2I12Q wA ran get
H. Any additional data to support a demonstration of good faith efforts:
NOTE: USE ADDITIONAL SHEETS OF PAPER IF NECESSARY.
alikim-44
Rialjen'+�p p
2280 South Lilac Ave
Bloomington Ca 92316
Phone: (909) 746-0356 Fax: (909) 746-0354
Contractors License No. 374600
DIR Registration No. 1000000306
A General Engineering
C-13 Fence, Wire, wood
C-32 Highway Improvement
Quotation Union Contractor / No minority Status
TO:
For the intended use of the General Contractor
Phone: ( )
Contact:
Fax: ( ) -
Current Date: 2/26/2020
BidDate: 2/26/2020
JobName: Hazard Ave Protected Bike Lanes
Location: Santa Ana Bid#: 47003 0
Contract#: Job#
Working Days:
Liquidated Damages
02
White Turn Lane Line
295 LF
1.000
$295.00
03
12" White Thermo
180 SF
4.000
$720.00
04
Double Yellow Thermo
655 LF
1.000
$655.00
05
Two Way Left Turn Lane Thermo
5050 LF
1.000
$5,050.00
07
6" White Bike Lane Thermo
6200 LF
0.750
$4,650.00
08
6" Dashed Bike Lane Thermo
3370 LF
0.750
$2,527.50
09
Install 6" White Chevrons
230 LF
2.500
$575.00
10
Install Thermo Legends and Arrows
16 EA
85.000
$1,360,00
11
Remove Conflicting Striping
11250 LF
0.750
$8,437.50
11A
Remove Legends
17 EA
75.000
$1,275.00
12
Bike Lane Legend Detail A Green MMA
34 EA
850.000
$28,900.00
13
Merging Area Detail B Green MMA
4000 SF
9.850
$39,400.00
14
Bike Sharrow Panel Green MMA Detail C
20 EA
425.000
$8,500.00
15
Curb Marking
1394 LF
2.250
$3,136.50
18
12" White Thermo
1370 SF
4.000
$5,480.00
19
Furnish & Install New Sign & Pole
27 EA
300.000
$8,100.00
20
Furnish & Instal New Sign Only
26 EA
205.000
$5,330.00
21
Furnish & Install New Signs Back to Back
17 EA
205.000
$3,485.00
22
Remove Existing Sign
12 EA
15.000
$180.00
23
Remove Existing Sign & Pole
13 EA
25.000
$325.00
Subtotal $128,381.50
Rialto Office
2280 South Lilac Ave
Bloomington Ca 92316
Phone: (909) 746-0356 Fax: (909) 746-0354
Quotation
Contractors License No. 374600
DIR Registration No. 1000000306
A General Engineering
C-13 Fence, Wire, wood
C-32 Highway Improvement
Union Contractor / No minority Status
. EXCLUDE: Maintenance of temporary delineation is. temporary paint, temporary tape, channelizers, etc...
. ALL Bid items shall NOT be adjusted or removed without written/ or verbal permission.
. EXCLUDE: Lead Compliance Plan
. Retainage percentage on monthly progress payments to be no greater than the percentage retained by the Owner on its
payment to the Contractor. If Owner reduces the retainage percentages on payments to the Contractor, the Contractor shall
likewise reduce the retainage percentage on payment to Chrisp Company. Full retention to be released no later than thirty,
(30) Days after completion of Chrisp Companys work. Excessive or delinquent retainage will be subject to the highest
interest rate allowed by law.
. Chrisp Company shall be reimbursed the full amount for bonds upon submission to General Contractor. Retention shall not
be held from bond reimbursement.
THIS QUOTATION IS BASED ON A STANDARD MONDAY THROUGH FRIDAY WORKWEEK. ADDITIONAL COSTS WILL
OCCUR FOR WORK PERFORMED ON WEEKENDS
CHRISP COMPANY WILL USE EXISTING EMPLOYEE POOL TO PERFORM ALL WORK ON THIS PROJECT. IF THERE ARE
ANY HIRING GOALS FOR THIS PROJECT THIS WILL BE EXCLUDED
. General Contractor to Provide Clean Water Source At No Cost to Chrisp Company. Must be Located On Jobsite.
Traffic Loops Crackfilling, Inc.
946 S. Emerald Street, Anaheim CA 92804 • Tel: (714) 520 4026 Fax: (714) 520 4027
License No. 652956 • Class C-10 & C-32 • SBE No. 0016691 • DBE & UDBE No. 38033 • Union Contractor
DIR Registration No. 1000003794 • Expiration Date: 06/30/2022
Email Traffieloops@sbcglobal.net or Estimating@ticine-ca.com
Date:
2/19/2020
Attn:
Estimator
Owner:
City of Santa Ana
Quotation
Project: Hazard Avenue Protected Bike Lanes, Project No. 18-6903, Federal Project No. CML 5063(182)
Bid Date: 02/26/2020 @ 2:00 PM
BID ITEM
DESCRIPTION
CITY.
UNIT
UNIT PRICE
ITEM TOTAL
6
Furnish and Install 2" PVC conduit and Stub -Out per
plan
150
LF
72.00
10,800.00
17
Furnish and Install Type E Traffic Loop Detector
29
EA
375.00
10,875.00
18
Furnish and Install Type D Traffic Loop Detector
13
EA
450.00
5,850.00
19
Furnish and Install Type Q Traffic Loop Detector
7
EA
500.00
3,500.00
Quote is valid for 180 days from the date of this proposal. TOTAL BID AMOUNT: $ 31,025.00
-By accepting our quote you agree to the Terms & Conditions shown on Page 2.
Our quote includes:
1- Lay out, saw cut, wash, blow, dry, seal, and megg
2- Loop saw cut shall be filled with Hot Melt Sealant
3- Insurance coverage up to $1 million, general aggregate
up to $2 million, umbrella up to $2 million
4- One move -in (We charge $1,200.00 per additional
move -in)
5- Traffic control for TLC operations only
Our quote excludes:
1- General Excess Liability for $5 million (If needed,
cost for extra protection is $3,000.00)
2- Bond fee (If required, Prime Contractor to pay bond
rate of 2%), permit fee, utilities fee, advance sign
posting of any kind, or notifying residents
3- Weekend work
4- Traffic control plans
5- Concrete, asphalt patch
All inclusions and exclusions are to be incorporated into our contract. If either party becomes involved in litigation or
arbitration arising out of this contract, the court or arbitration panel shall award attorney's fees and costs to the prevailing
party.
Please call Mai -Lan Nguyen at (714) 520-4026 if you have any questions or need more information.
s � ,
Traffic Loops Crackfilling, Inc.
946 S. Emerald Street, Anaheim CA 92904 • Tel: (714) 520 4026 Fax: (714) 520 4027
General Terms and Conditions:
-Quote is valid for 180 days from the date of this proposal.
-In case of discrepancy between the unit price and the total set forth for a unit basis item, the unit price shall prevail.®
-10 days notice required for scheduling.
•24 hours notice required for rescheduling.
-Site must be ready with cat -track, permanent striping, grinding, asphalt, approvals, etc. prior to loop installation.
-Access to the job site must be furnished by Contractor, the general contractor, lessee or other party ordering work.
-Additional charges may incur for the following:
a) Site is not ready (for TLC's scope of work) the day of scheduled work or delays
b) Extra move -ins
c) When minimum move -in requirements are not met (if noted in quote)
-All changes to the original scope of work or proposed extra work must be directed by the Contractor in writing prior to Traffic Loop Crackfilling, Inc. (TLC) before
performing this work. No extra work or additional work will be performed without written authorization.
-This quote will not be valid if there are any changes or deletions of any item post bid and will need revised pricing.
-Total bid must be accepted (must use all line items) unless otherwise noted or agreed to. If you need revised pricing for only a portion of the work, contact Estimator.
-TLC will not be impacted by Liquidated Damages assessed by the Contractor / Agency due to an inadequate amount of time to complete TLC operations.
-Contractorto provide monthly progress payments for all completed work in accordance with the bid pricing schedule. Monthly payments must be received in full by
TLC no later than 10 calendar days after the Contractor receives payment from Owner for our completed work.
-Retention % is to be withheld only as per the Owner's requirements.
-Contractor hereby agrees that time shall be of the essence In regard to all payments provided for herein, and if any payment is not made when due, Contractor
agrees to pay all collection costs and expenses including costs of suit and any related attorney's fees and costs and also hereby waives the benefit of any statute of
limitation that would prohibit an action of TLC to enforce the terms and conditions of this Contract including but not limited to any right to
recovery of attorneys fees and costs. The laws of the State of California shall control all aspects of this contract except as to lien matters, which will be governed by
the laws of the state where the subject property is located.
-TLC requires a written contract, purchase order or signed quote prior to the start of work.
-The language and terms used in this exhibit supersede any conflicting terms in the Subcontract Agreement.
If you are the apparent low, please inform CPL within 48 horns. Long lead materials apply.
CALIFORNIA PROFESSIONAL ENGINEERING, INC.
I
Estimate Number
Project Name: Hazard Ave
Project #: 18-6903
Agency: CITY OF SANTA ANA
Bid Due Date: 212612020
19062 San Jose Avenue, La Puente, CA 91748
License # 793907 Exp: 04/30/2021
Classifications: A, C-30, C-20
LSBE Certified LA County #54567 Exp: 11/30/2020
SBE Certified DGS #54567 Exp: 11/30/2020
SMBE/DBE/UDBE Certified Caltrans #31277
DIR #1000377609 Exp, 06/30/2020
Union Signatory Laborer's Local and IBEW
Bid Due Time: 2:00 PM
Conditions Set Forth:
1. Estimate based on one (1) mobilization unless noted otherwise. Additional mobilization at $3,500.00/ea.
2. If loop work: stubout must be existing & marked if not called out to be replaced per plans. Cat -tracking shall be approved prior. Should loop
quantities be decreased, a minimum mobilization of $4,500.00 shall supersede.
3. One work day based on eight (8) standard consecutive work hours per day. At least 3-weeks notification required; subject to scheduling availability.
4. Quote valid for thirty (30) days. CPE reserves the right to revise our quotation as necessary.
5. Should HKA be the acting consultant/inspectors on behalf of the Agency, CPE reserves the right to withdraw our bid.
CPE ispleasedtoprovide this esainatefor the intendeduseofthe Contractor(ofirrnish laborand/ormaterialin strict accordance with the plans andspce orations asfollows:
Item #
6
16A
16B
16C
Description:
Furnish and install 2" PVC conduit and stub -out
per plan
Furnish and install type E traffic loop detector
(with DLC)
Furnish and install type D traffic loop detector
(with DLC)
Furnish and install type Q traffic loop detector
(with DLC)
UOM: I Qty:
LF
150
EA
29
EA
13
EA
7
Unit Price:
100.00
265.00
275.00
300.00
Subtotal:
15,000.00
7,685.00
3,575.00
2,100.00
Exclusions: Bond & Bond Premium; Overtime and/or Nighttime Rates; All Permits; All Training Requirements; Signage; Lane Closure Request, Traffic
Control, and TCP; Light Towers; CMS boards; Shoring; Water; Sidewalk & Surface Concrete; Regulatory Signs; Hauling Dirt, Debris, & Concrete
Foundation Away; Handicap Ramps; Repaving Street; Repaving Potholes; Saw Cutting; USA Marking Removals; Irrigation Work; Dewatering; Striping;
Survey; Fencing; Cold/Hot Mix; Temp. Asphalt; Inspection Fees; Testing; Temporary Loops; Temporary Signal; Compaction Testing, and/or High
Voltage Line Conflicts, Unless Otherwise Noted Above. Standard Certificate of Insurance will be provided upon request. Any additional requirements
will be billed at cost.
Hot Mix Asphalt shall be provided by Contractor to CPE to backfill any potholes and/or excavations. If it is not provided and we utilize temporary Cold
Mix, CPE will not be held liable for any claims that may derive from such pothole and/or excavated location.
Terms: Unless other arrangements are made, payment is due & payable withinin 30 days upon completion; 1.5% monthly interest will apply
thereafter. Bid based on entire bill of material and services and is inseparable unless written authorization is provided by CPE.
Acceptance
TOTAL:
20 B-43
Ph: (626) 810-1338 1 Fx: (626) 810-1322 I Email: estimatingOcpencrineerinctinc com
$28,360.00
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EXHIBIT 12-B BIDDER'S LIST OF SUBCONTRACTORS (DBE AND NON -DBE) — PART I
PART
The bidder shall list all subcontractors (both DBE and non -DBE) in accordance with Section 2-1.054 of the Standard
Specifications and per Title 49, Section 26.11 of the Code of Federal Regulations. This listing is required in
addition to listing DBE Subcontractors elsewhere in the proposal. Photocopy this form for additional firms.
Local Assistance Procedures Manual Exhibit 12-B
Bidder's List of Subcontractors (DBE and NON -DBE)
Exhibit 12-B Bidder's List of Subcontractor (DBE and Non -DBE) Part 1
As of March 1, 2015 Contractors (and sub-contmciors) wishing to bid on public works contracts shall be registered with the State Division of Industrial Relations and
certified to bid on Public Works contracts. Please register at: https:/Iwww.dir.ca.gov/Public•Works/Contractor-Registration.html
In accordance with Title 49, Section 26.11 of the Code of Federal Regulations, and Section 4104 of the Public Contract Code of the State of California, as amended, the
following information is required for each sub -contractor who will perform work amounting to noon: than one half of one percent (0.5%) of the Total Base Bid or S10,000
(whichever is greater). Photocopy this form for additional items. Federal Project Number:
Subcontractor Name and
Location
Line Item & Description
Subcontract
Amount
percentage of
Bid Item Sub-
contracted
Contractor
License Number
DBE
ty/N)
DBE Cert
Number
Annual Gross Receipts
DIR Re Number
Name:
Traffic Loops Crackfilling, Ina
- urns ns p PVC
1177n Furnish Btlnstaalll Type Ean
Traffic Loop Detector
19-Furnish B Install Type ❑
Traffic Loop Detector
19-Furnish & Install Type D
Traffic Loop Detector
$31,025.00
700%
652966
V
38933
U < ItNlllon
<$S rrdlllan
City, State:
y
Anaheim, CA
1000003794
❑ <$20 million
El <$15 million
of Firrti: fS.
Name:
1 Mlllon
City, State:
<55 mllllon
c$10 million
LJ 1s million
e of Firm: s.
Name:
<$15 ndl
City, State:
rNlgon
llon
L1 <510 million
❑ <$1S million
e of 1171a rs.
Name
❑ eSmllllon
City, State:
<SS million
410 million
LJ 41S million
Alta of Firm: rs.
Name:
❑ <$a million
City, State:
<$5 million
= <S30 million
LJ <$i5mlllion
e of Firm rs.
Name:
<S3 million
City, State:
LJ <$5 million
❑ <$10 mon
<$1S million
e of Firm: rs.
11 original -Local Agency File 21 Copy-DLAE w/ Award Package
Page I of 2
.lamarr 2019
r 1 - - I I
IN W6
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EXHIBIT 12-B BIDDER'S LIST OF SUBCONTRACTORS (DBE AND NON -DBE) - PART I
PART
The bidder shall list all subcontractors (both DBE and non -DBE) in accordance with Section 2-1.054 of the Standard
Specifications and per Title 49, Section 26,11 of the Code of Federal Regulations. This listing is required in
addition to listing DBE Subcontractors elsewhere in the proposal. Photocopy this form for additional firms.
Local Assistance Procedures. Manual
As of March 1, 2015 COuractrrs (and suh-cuittractars) wishing to bid on
clanifiodlobid on.Publie Works contracts. Pleaseregisterar.htt s: wu
4104 of the Public Contract Code oftbe State of California, as amended, the
4 to mom Wan one half of one percent ofthe Tout Base Bid or S10,WO
Federal Project Number:
5ubrontrartorNameand
Location
tine item & Description
subcontract
Amount
Ptreentege of
Old item Stub.
tnttrtaeted
Contractor
thxnmNumber
OBE
{YfN)
OBECert
Number
Annual Gross aeeeiptt
GIO Re Number
Name: r'
rt Z?u'
L
C
31 Fl y
�2$ 3�`k,rp
Y
N1400
d
N/fit
El<5l million
<Sb milhnrr
City, Stater
100=306
❑ <5lomrnrnn
. fL
Aqe df Firm:irm,400m
Namei.
LJ $l million
airy, state..❑
... <$s million
(,� z$io million
<$i$ million
Axe of Firm; rs.
Naha:
-
Ll <$i million
City, State:
<$5 million
<s10million
_
[] 41Sm1l11on
eof Pirrm n.
Namw
mt9fon
❑ty,state:
31
<$5 million
410million
❑ <$IS. million
Age of Firm; rs.
Name:
.�'�
❑ <$1 million
iaty,state:
-
million
� di3tJ million
sI
c$ismlllloo
e of Firm: •
Name:..
City, stale
1S5 million
❑ <$10 million
a$15 million
Age of Firm: 'yrs.
ursulriution: 1) uoginain.ocal++gemy File 2)CppyntAE w/Award Pacgage
rim
r r r
' I
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
PROMPT PAYMENT OF FUNDS WITHHELD TO SUBCONTRACTORS
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, certify to comply with the following:
The agency shall hold retainage from the prime contractor and shall make prompt and
regular incremental acceptances of portions, as determined by the agency, of the contract
work, and pay retainage to the prime contractor based on these acceptances. The prime
contractor, or subcontractor, shall return all monies withheld in retention from a
subcontractor within 30 days after receiving payment for work satisfactorily completed
and accepted including incremental acceptances of portions of the contract work by the
agency. Federal law (49CFR26.29) requires that any delay or postponement of payment
over 30 days may take place only for good cause and with the agency's prior written
approval. Any violation of this provision shall subject the violating prime contractor or
subcontractor to the penalties, sanctions and other remedies specified in Section 7108.5
of the Business and Professions Code. These requirements shall not be construed to limit
or impair any contractual, administrative, or judicial remedies otherwise available to the
prime contractor or subcontractor in the event of a dispute involving late payment or
nonpayment by the prime contractor, deficient subcontract performance, or
noncompliance by a subcontractor.
Signed ��—
Title President
Firm HYM Engineering, inc.
Date
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
EXHIBIT 16-B — SUBCONTRACTING REQUEST
Local Assistance Procedures Manual
Exhibit 16-B
CONTRACTORNAME HYM Engineering, Inc.
COUNTY Orange
ROUTE
BUSINEss ADDRE9s 1559 W. Commonwealth Ave.
CONTRACTNUMBER 18-6903
CITY AND STATE Fullerton, CA
ZIP CODE 92833
FEDERAL -AID PRojECrNUMBER
CML-5063 182
A, SUBCONTRACTOR
B. BIDITEM
C. PERCENTAGEOF
D. SUB LISTED
E, CERTIFIED
F. DESCRIBE WORK
G. DOLLAR AMOUNT
(Narne,Bnsiness Addrm,Phone)
NUMBERS)
BID ITEM
AT BIDTIME
USE
WHEN LESS TITAN
BASEDONTHEBID
SUBCONTRACTED
100% OF WORK IS
AMOUNT
SUBCON'fRAcrEE�D
Yes No
Y�7
Yes No
p
Yes No
Yes No
kl S P Cain
01� U�C
Yes No
Yes No
qR w�.
eoH11
//Q 1-4
Yes No
Yes No
/S /15
❑ ❑
❑ ❑
i{% 4
Yes No
Yes No
uY 1j
❑ ❑
❑ ❑
Yes No
Yes No
❑ ❑
❑ ❑
I certify that:
• The Standard Provisions for labor set forth in the contract apply to the subcontracted work.
• If applicable, Form FHWA-1273 of the Special Provisions has been inserted in the subcontracts and should be
incorporated in any lower -tier subcontract. Written contracts have been executed for the above noted subcontracted
work.
Contractor Signature Date /7
0
This section is to be completed by the resident engineer.
1. Total of bid items
2. Contractor must perform with own forces (line 1 X contract req. %)
3. Bid items previously subcontracted (taken from previously approved 16-11)
4. Bid items subcontracted (this request)
5. Total bid items subcontracted (line 3 plus 4)
6. Balance of work contractor to perform (line 1 minus 5)
Approved
RESIDENT ENGINEEIYS SIGNATURE DATE
i opy utsmounon : Ongmai-contractor Copy- Resident Engineer Copy- OBEO- smallbusinessedvucate®dopt ca eov or fax to (916) 324-1949
Page 1 of 2
January 2018
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
Local Assistance Procedures Manual Exhibit 16-B
Subcontracting Request
INSTRUCTIONS FOR COMPLETING SUBCONTRACTING REQUEST FORM
All first -tier subcontractors must be included on a subcontractor request.
Before subcontracting work starts, the contractor will submit an original CEM-1201 for approval according to the
Standard Specifications. After approval, the RE returns the original to the contractor and complete the remaining
distribution as listed on the bottom of the form.
D. If subcontractor was listed at bid time per the Fair Practices Act, check yes, otherwise check no.
E. If subcontractor is a certified DBE contractor, check yes, otherwise check no.
F and G. When a portion of an item is subcontracted, describe the portion and show the percentage of the bid item
and value.
G. When an entire item is subcontracted, show the full bid item value.
THIS FORM IS NOT TO BE USED FOR SUBSTITUTIONS OF SUBCONTRACTORS AND UDBE, DVBE OR
SMALL BUSINESS ENTITIES.
Page 2 of 2
January 2018
gum
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, certify to comply with the following:
a. Contractor's Notification
Promptly notify the Agency's Engineer if you find either of the following conditions:
1. Physical conditions differing materially from either of the following:
• Contract documents
• Job site examination
2. Physical conditions of an unusual nature, differing materially
from those ordinarily encountered and generally recognized as
inherent in the work provided for in the Contract
Include details explaining the information you relied on and the material
differences you discovered. If you fail to promptly notify the Engineer, you waive
the differing site condition claim for the period between your discovery of the
differing site condition and your notification to the Engineer.
If you disturb the site after discovery and before the Engineer's investigation, you
waive the differing site condition claim.
b. Engineer's Investigation and Decision
Upon your notification, the Engineer investigates job site conditions and:
1. Notifies you whether to resume affected work
2. Decides whether the condition differs materially and is cause for an
adjustment of time, payment, or both
Signed
Title President
Firm HYM Engineering, inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
BIDDER'S CERTIFICATE OF COMPLIANCE REGARDING "BUY AMERICA"
REQUIREMENTS FOR STEEL OR MANUFACTURED PRODUCTS
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, certify to comply with the "Buy America" requirements of Section 165 of the
Surface Transportation Assistance Act of 1982 and as shown in the special provisions of this
project.
Signed
Title
Firm HYM Engineering, inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
NEPA COMPLIANCE FOR FEDERAL AID CONTRACTS
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, certify to comply with the Categorical Exemption/Categorical Exclusion
Determination Form including and not limited to the National Environmental Policy Act (NEPA)
requirements and environmental commitments found in the appendix of the Contract Documents
of this project.
Signed
Title President
Firm HYM Engineering, inc.
Date 2/26/2020
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-6903
HAZARD AVENUE PROTECTED BIKE LANES
FEDERAL PROJECT NO: CML-5063 (182)
TMP COMPLIANCE FOR FEDERAL AID CONTRACTS
The undersigned, is submitting this proposal for performing by contract the work required by these
bid documents, certify to comply with the Traffic Management Plan (TMP) commitments found
in the appendix of the Contract Documents of this project.
Signed
Title President
Firm HYM Engineering, inc.
Date 2/26/2020
CITY OF SANTA ANA EXHIBIT 3
CONSTRUCTION CONTRACT
PROJECT 18-6903
HAZARD AVENUE PROTECTED BIKE LANES FROM EUCLID STREET TO HARBOR BLVD
(CML-5063(182))
This CONSTRUCTION CONTRACT is made and entered into this 5s' day of May, 2020 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and
existing under the Constitution and laws of the State of California (hereinafter "CITY"), and HYM
Engineering, Inc. (hereinafter "CONTRACTOR").
WH`NESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the
satisfaction of the City Engineer of the CITY, the Hazard Avenue Protected Bike Lanes from Euclid
Street to Harbor Blvd Project (hereinafter referred to as the "WORK OF IMPROVEMENT")
identified in and in accordance with the Contract Documents prepared by the City's Public Works
Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Eight Hundred Eighty-two Thousand Nine
Hundred Nineteen Dollars and No Cents ($882,919.00), as set forth and identified in the BID
PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
rev. 09/01/2017 20B-53 Page 1 of
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
http://www.santa-ana.org/pwa/documents/CWA.pd
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
//
20 B-54 Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:� •r r•—. �^^"
J NFUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Acting Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
HYM Engineering, Inc.
NAME: b Tem
TITLE: 1 fttstofOj
20B-55
Page 3 of 3
COST ANALYSIS
PROJECT 186903; HAZARD AVE PROTECTED & CLASS III BIKE LANES
CML-5063(182)
Construction Contract $882,919
Contract Administration $87,793
Inspection and Testing $21,948
Contingencies $88,340
TOTAL ESTIMATED CONSTRUCTION COSTS
:7iT _mxl
$1,081,000