HomeMy WebLinkAboutRESO 2020-27_1702 N MAIN Resolution No. 2020-27
Page 1 of 8
LS 8.24.20
RESOLUTION NO. 2020-27
A RESOLUTION OF THE PLANNING COMMISSION OF
THE CITY OF SANTA ANA APPROVING VARIANCE NO.
2020-01 AS CONDITIONED TO ALLOW A REDUCTION IN
REQUIRED SETBACKS AT 1702 NORTH MAIN STREET
BE IT RESOLVED BY THE PLANNING COMMISSION OF THE CITY OF
SANTA ANA AS FOLLOWS:
Section 1. The Planning Commission of the City of Santa Ana hereby finds,
determines and declares as follows:
A. Leslie Gentile, representing Farmers and Merchants Bank (“Applicant”), is
requesting approval of Variance No. 2020-01 as conditioned, to allow for a
reduction in required setbacks at 1702 North Main Street.
B. Santa Ana Municipal Code (SAMC) Sections 41-368, 41-369 and 41-372
require a front yard and side yard setback of not less than 15 feet, and a
15-foot minimum landscape setback from front and street-side yards.
C. In 2004, the City Council approved several original entitlements to allow
the construction of the One Broadway Plaza tower at 1109 North
Broadway with additional entitlement modifications approved in 2020. The
certified environmental impact report (EIR) identified a mitigation measure
requiring the dedication of land at the subject site (1702 North Main
Street) for a southbound right-turn lane at the Main and 17th intersection.
D. The future improvements for the southbound right-turn lane would result in
the widening of Main Street, the construction of new sidewalk, curb, gutter,
pavement, and the relocation of the traffic signal along the Main Street
and 17th Street frontages. It would also result in a loss of approximately
1,800 square feet to the subject site.
E. The Applicant is proposing a 19-foot setback from Main Street, which will
be further reduced to 8 feet due to an 11-foot dedication for a southbound
right-turn lane at the interaction of 17th Street and Main Street. In addition,
the Applicant is proposing an 8-foot setback from 17th Street.
F. Pursuant to SAMC Section 41-638, the Planning Commission is
authorized to review and approve the variance for this project as set forth
by the Santa Ana Municipal Code.
G. On August 24, 2020, the Planning Commission held a duly noticed public
hearing for Variance No. 2020-01.
H. The Planning Commission of the City of Santa Ana has considered the
information and determines that the following findings, which must be
Resolution No. 2020-27
Page 2 of 8
established in order to grant Variance No. 2020-01, for a reduction in
required setbacks as required by SAMC Section 41-638:
1. That because of special circumstances applicable to the subject
property, including size, shape, topography, location or
surroundings, the strict application of the zoning ordinance is found
to deprive the subject property of privileges not otherwise at
variance with the intent and purpose of the provisions of this
Chapter.
There are special circumstances related to the existing size
of the property. The property is located at the northwest
corner of Main and 17th streets and contains 19,708 square
feet. Due to an 11-foot dedication for a future southbound
right-turn lane there would be a loss of approximately 1,800
square feet to the existing property size. In order to meet the
City’s minimum standards to ensure safe and efficient onsite
circulation, the project necessitates the building be placed
closer to the intersection, resulting in a loss of approximately
seven (7) feet of setback on Main Street and 17th Street.
Without the reduction in setbacks, the project would need to
be redesigned, resulting in: a loss of over half of its off-street
parking spaces; a reduction in drive-aisle lane widths,
creating onsite circulation hazards; and/or a smaller building
footprint, reducing the building’s interior floor area. The
parcel’s compact size and the 11-foot dedication
requirement justify the Applicant’s request for a landscape
setback variance. Further, the City’s Citywide Design
Guidelines encourage new buildings to be located closer to
streets in an effort to improve urban design and promote
pedestrian activity. Specifically, Chapter 9 (Commercial
Design Guidelines), Section 9.3.2 encourages buildings to
be placed closer to street frontages, with parking areas
behind. Placing the proposed building closer to the
intersection of Main and 17th necessitates approval of the
setback reduction in order to meet this design guideline.
2. That the granting of a variance is necessary for the preservation
and enjoyment of one (1) or more substantial property rights.
Granting this variance is necessary for the preservation and
enjoyment of substantial property rights. In order to facilitate
construction of a safe and efficient site that meets the City’s
access, circulation, and parking codes, a reduction in
setbacks is required. Finally, the reduction enables the
building to be located closer to the nearby street frontages,
assisting with the project meeting City design guidelines that
encourage buildings placed closer to streets.
Resolution No. 2020-27
Page 3 of 8
3. That the granting of a variance will not be materially detrimental to
the public welfare or injurious to surrounding property.
Granting this variance will not be detrimental to the public or
surrounding properties. The Public Works Agency reviewed
the proposed plans and did not identify concerns regarding
the location of onsite circulation (drive aisles) and parking
areas. The design of the driveways, drive aisles and parking
areas are safe and practical and will not be detrimental to
the public welfare or surrounding property.
4. That the granting of a variance will not adversely affect the General
Plan of the city.
The variance for a setback reduction will not adversely affect
the General Plan. The project is located in a General
Commercial (GC) General Plan land use designation, which
allows for commercial uses such as retail, service and banks
and financial institutions. The project is consistent with several
goals and policies of the General Plan, including the Economic
Development Element, Land Use Element, and Urban Design
Element. Land Use Element Goal 1 promotes a balance of
land uses to address basic community needs. Policy 1.10,
encourages the location of commercial centers at arterial
roadway intersections in commercial districts. The project will
provide for a new commercial building on two arterial streets.
Land Use Element Goal 2 promotes land uses that enhance
the City’s economic and fiscal viability. Policy 2.9, supports
developments that create a business environment that is safe
and attractive. The Condition of Approval for property
maintenance will maintain a safe and attractive environment
in the community. Economic Development Element Goal 2
maintains and enhances the diversity of the City’s economi c
base. Policy 2.3 encourages the development of mutually
beneficial and supportive business clusters within the
community. The project will provide a banking and financial
establishment in an area that does not currently have one,
thereby providing much needed community benefit. Urban
Design Element Goal 1 improves the physical appearance of
the City through development of districts that project a sense
of place, positive community image and quality environment.
Specifically, Policy 1.5 enhances architectural forms,
textures, colors, and materials for all projects. The project
will feature contemporary architecture with high quality
materials, and feature a “brand wall” along the north
elevation enhancing the building’s contemporary design and
street presence. The building’s south elevation will be
enhanced with a floor-to-ceiling glass curtain wall system
Resolution No. 2020-27
Page 4 of 8
providing an overall enhanced design along the Main and
17th intersection.
Section 2. In accordance with the California Environmental Quality Act and the
CEQA Guidelines, the project is exempt from further review per Section 15303 of the
Guidelines. The Class 3 exemption applies to up to four commercial buildings not
exceeding a cumulative total of 10,000 square feet in floor area on sites zoned for such
use, if not involving the use of significant amounts of hazardous substances where all
necessary public services and facilities are available and the surrounding area is not
environmentally sensitive.
The proposed project is a single building under 6,000 square feet in size, not
anticipated to use significant amount of hazardous substances, is not located within an
environmentally sensitive area, and will have access to all necessary public services
and facilities made available through the City of Santa and Orange County Fire
Authority (OCFA). As a result, Categorical Exemption, Environmental Review No. 2020-
25 will be filed for this project.
Section 3. The Applicant shall indemnify, protect, defend and hold the City
and/or any of its officials, officers, employees, agents, departments, agencies,
authorized volunteers, and instrumentalities thereof, harmless from any and all claims,
demands, lawsuits, writs of mandamus, referendum, and other proceedings (whether
legal, equitable, declaratory, administrative or adjudicatory in nature), and alternative
dispute resolution procedures (including, but not limited to arbitrations, mediations, and
such other procedures), judgments, orders, and decisions (collectively “Actions”),
brought against the City and/or any of its officials, officers, employees, agents,
departments, agencies, and instrumentalities thereof, that challenge, attack, or seek to
modify, set aside, void, or annul, any action of, or any permit or approval issued by the
City and/or any of its officials, officers, employees, agents, departments, agencies, and
instrumentalities thereof (including actions approved by the voters of the City) for or
concerning the project, whether such Actions are brought under the Ralph M. Brown
Act, California Environmental Quality Act, the Planning and Zoning Law, the Subdivision
Map Act, Code of Civil Procedure sections 1085 or 1094.5, or any other federal, state or
local constitution, statute, law, ordinance, charter, rule, regulation, or any decision of a
court of competent jurisdiction. It is expressly agreed that the City shall have the right to
approve, which approval will not be unreasonably withheld, the legal counsel providing
the City’s defense, and that Applicant shall reimburse the City for any costs and
expenses directly and necessarily incurred by the City in the course of the defense.
City shall promptly notify the Applicant of any Action brought and City shall cooperate
with Applicant in the defense of the Action.
Section 4. The Planning Commission of the City of Santa Ana, after conducting
the public hearing, hereby approves Variance No. 2020-01 to allow for a reduction in
required setbacks, as conditioned in Exhibit A, attached hereto and incorporated as
though fully set forth herein. This decision is based upon the evidence submitted at the
above said hearing, which includes, but is not limited to: the Request for Planning
Commission Action dated August 24, 2020, and exhibits attached thereto; and the public
testimony, written and oral, all of which are incorporated herein by this reference.
08-24-2020
Resolution No. 2020-27
Page 6 of 8
EXHIBIT A
Conditions of Approval for Variance No. 2020-01
Variance No. 2020-01 to allow a reduction in required setbacks is approved subject to
compliance, to the reasonable satisfaction of the Planning Manager, with applicable
sections of the Santa Ana Municipal Code, the California Administrative Code, the
California Building Standards Code, and all other applicable regulations. In addition, they
shall meet the following conditions of approval:
The Applicant must comply with each and every condition listed below prior to exercising
the rights conferred by this variance.
The Applicant must remain in compliance with all conditions listed below throughout the
life of the variance. Failure to comply with each and every condition may result in the
revocation of the variance.
1. All proposed site improvements must conform to the Site Plan Review (DP No. 2020-
02) and the staff report exhibits which are incorporated herein by reference.
2. Any amendment to this variance must be submitted to the Planning Division for review.
At that time, staff will determine if administrative relief is available or the variance must
be amended.
3. Prior to the issuance of a building permit, a full landscape and irrigation plan is to be
submitted for review and approval. The landscape plan shall: (1) conform to the
commercial landscape standards, Citywide Design Guidelines, and the City’s Water
Efficient Landscape Ordinance, and (2) contain regularly-spaced vines installed along
the entire lengths of the new perimeter wall and the trash enclosure so as to form a
natural graffiti deterrent.
4. The Applicant shall be responsible for maintaining the premises free of graffiti. All
graffiti shall be removed within 24 hours of occurrence.
5. The Applicant shall implement a local art program where local artist’s work is displayed
on the subject property, either within the exterior or interior of the new building. The
applicant shall work with the City’s Art & Culture Office to identify local artist, and
receive recommendations on establishing a process for selecting and displaying such
local art work. Displayed art work shall include, but not be limited to, drawings,
paintings, sculptures, ceramics, printmaking, installations, or decorative arts.
6. A Property Maintenance Agreement must be recorded against the property. The
agreement will be subject to review and applicability by the Planning and Building
Agency, the Community Development Agency, the Public Works Agency, and the
City Attorney to ensure that the property and all improvements located thereupon
are properly maintained, Developer (and the owner of the property upon which the
authorized use and/or authorized improvements are located if different from the
Applicant) shall execute a maintenance agreement with the City of Santa Ana which
Resolution No. 2020-27
Page 7 of 8
shall be recorded against the property and which shall be in a form reasonably
satisfactory to the City Attorney. The maintenance agreement shall contain
covenants, conditions and restrictions relating to the following:
(a) Compliance with operational conditions applicable during any period(s) of
construction or major repair (e.g., proper screening and securing of the
construction site; implementation of proper erosion control, dust control and
noise mitigation measure; adherence to approved project phasing etc.);
(b) Compliance with ongoing operational conditions, requirements and
restrictions, as applicable (including but not limited to hours of operation, security
requirements, the proper storage and disposal of trash and debris, enforcement
of the parking management plan, and/or restrictions on certain uses,
(c) Ongoing compliance with approved design and construction parameters,
signage parameters and restrictions as well as landscape designs, as applicable;
(d) Ongoing maintenance, repair and upkeep of the property and all
improvements located thereupon (including but not limited to controls on the
proliferation of trash and debris about the property; the proper and timely removal
of graffiti; the timely maintenance, repair and upkeep of damaged, vandalized
and/or weathered buildings, structures and/or improvements; the timely
maintenance, repair and upkeep of exterior paint, parking striping, lighting and
irrigation fixtures, walls and fencing, publicly accessible bathrooms and bathroom
fixtures, landscaping and related landscape improvements and the like, as
applicable);
(e) If Developer and the owner of the property are different (e.g., if the Applicant
is a tenant or licensee of the property or any portion thereof), both the Applicant
and the owner of the property shall be signatories to the maintenance agreement
and both shall be jointly and severally liable for compliance with its terms.
(f) The maintenance agreement shall further provide that any party responsible
for complying with its terms shall not assign its ownership interest in the property
or any interest in any lease, sublease, license or sublicense, unless the
prospective assignee agrees in writing to assume all of the duties, obligations
and responsibilities set forth under the maintenance agreement.
(g) The maintenance agreement shall contain provisions relating to the
enforcement of its conditions by the City and shall also contain provisions
authorizing the City to recover costs and expenses which the City may incur
arising out of any enforcement and/or remediation efforts which the City may
undertake in order to cure any deficiency in maintenance, repair or upkeep or to
enforce any restrictions or conditions upon the use of the property. The
maintenance agreement shall further provide that any unreimbursed costs and/or
expenses incurred by the City to cure a deficiency in maintenance or to enforce
use restrictions shall become a lien upon the property in an amount equivalent to
the actual costs and/or expense incurred by the City.
Resolution No. 2020-27
Page 8 of 8
(h) The execution and recordation of the maintenance agreement shall be a
condition precedent to the issuance of final approval for any construction permit
related to this entitlement.