SUPPLEMENTAL AGREEMENT, made this V%�
day of 1987, between
THE ATCHISON, TOPEKA AND SANTA FE RAILWAY COMPANY a
Delaware Corporation, hereinafter designated
"Santa Fe" and the CITY OF SANTA ANA, a California
municipal corporation, hereinafter designated "City".
R E C I T A L S
By Agreement dated December 14, 1983, identified as Santa Fe Secretary's
Contract No. 168991, the parties hereto agreed to the construction and
maintenance of a public transportation center .in the City of Santa Ana.
Exhibit "A", attached to and made a part of said agreement, was a print of
Drawing C.E.C.L. No. 20-41279 --- 1 dated February 4, 1982, and last revised
May 11, 1983.
Santa Fe has now prepared a new Exhibit "A" drawing which reflects changes
which have been agreed to by the parties during construction of said public
transportation center, and other changes which the parties desire to
accomplish to complete the project.
Exhibit "B" dated April 20, 1982, revised October 26, 1982, attached to
and made a part of said agreement, was an estimate of cost of work to be
performed by Santa Fe in connection with said public transportation center.
Santa Fe has now prepared a new Exhibit "B" which reflects the estimated
cost of all work accomplished to date by Santa Fe, including changes which
have been agreed to by the parties during construction of said transportation
center, and other changes which the parties desire to accomplish to complete
the project.
Santa Fe and City being willing to supplement said agreements, the parties
hereto desire to set forth their understanding and agreement.
A G R E E M. E N T
It is agreed by and between the parties as follows:
El:
1. Exhibit "A", C..E.C.L. Drawing No. 20-41279-1 dated 'February 4, 1982,
and last revised March 9, 1987, which is attached hereto and by
reference made a part hereof, is hereby substituted in the place and
instead of Exhibit "A", Drawing C.E.C.L. No. 20-41279-1, last revised
May 11, 1983, attached to and made a part of Secretary's Contract
No. 168991, with like force and effect as though originally attached
thereto and made a part thereof.
2. Exhibit "B", dated March 9, 1987, which is attached hereto and by
reference made a part hereof, is hereby substituted in the place and
instead of Exhibit "B", last revised October 2.6, 1982, attached to
and made a part of Secretary's Contract No. 168991, with like force
and effect as though originally attached thereto and made a part
thereof.
3. That as herein amended, Santa Fe Secretary's Contract No. 168993,
shall be and remain in force and effect.
x
E!
N
-2-
IN WITNESS WHEREOF THE PARTIES HERETO HAVE DULY EXECUTED THIS AGREEMENT
on the day and year first above written.
THE ATCHISON, TOPEKA AND SANTA FE
RAILWAY COMPANY
By
PPesident
Its
CITY OF SANTA ANA
BY
CITY OF SANTA ANA, CALIFORNIA
APPROVED:
David H. Grosse, Director
Department of Transportation Svcs
APPROVED AS TO FORM:
0056j
ATTEST:
Jan I
Clerk of The Council
APPROVED 0 ONTENT:
City M nAge`
-3-
EXHIBIT "B"
THE ATCHISON, TOPEKA AND SANTA FE RAILWAY COMPANY
ESTIMATE FOR
SANTA ANA INTERCITY TRANSPORTATION CENTER
Estimate of: costs by forces for: engineering, inspection and flagging,
permanent removal of garage, permanent relocation of signal facilities and
crossing warning devices at Fourth Street and Santa Ana Boulevard, and
installation of electric locks and power switch, permanent relocation of joint
signal/communication pole line, permanent relocation, construction and/or
removal of various tracks, permanent installation and removal of A.C. paving,
permanent installation of 240 track feet of rubber crossing material,
relocation of team track and unloading dock, all in connection with Santa Ana
Intercity Transportation Center. at Santa Ana, Fourth District, Los Angeles
Division.
Revised
March 9, 1987
-1-
THE ATCHISON, TOPEKA AND SANTA FE RAILWAY COMPANY - COAST LINES
EXHIBIT "B"
Summary - Estimate of Cost, Santa Ana Intercity Transportation Center
1.
Engineering, Inspection and Flagging
(Perm)
55,391
2.
Communications
(Perm)
28,531
3.
Signal
(Perm)
535,966
4.
Track
(Perm)
625,116
5.
Loading
Dock
(Perm)
16,466
6.
Paving
(Perm)
120,000
7.
Remove
- Garage Building
(Perm)
3,000
Add for Contingencies
130,894
Estimated Cost of Labor and Material
1,515,365
Auditing and Billing
4,738
Equipment Rental and
Depreciation
72,415
Transportation of Equipment
7,500
Credit for Material Recovered:
Signal 3,000
Less Cost to Return to Stock - 120
2,880
- 2,880
Estimated Cost of Work to be
Performed by Santa Fe Forces and
Paid for by the City of Santa Ana 1,597,137
-2-
1. Engineering Inspection and Flagginq
Salaries
Expenses
Vacation, Paid Holiday
Retirement and Unemployment Tax
Health and Welfare Benefits and Croup
Life Insurance
Workman's Comp. and Liab. Ins.
Excise Tax
Estimated Cost of Engineering and Inspection
2. Communication (Perm.)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
Labor
Salaries
Expenses
Vacation, Paid Holiday
Retirement and Unemployment Tax
Health and Welfare Benefits and Group
Life Insurance
Workman's Comp. and Liab. Ins.
Excise Tax
Estimated Cost of Labor
Estimated Cost of Labor and Material (Perm.)
3. Signal (Perm.)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
Labor
Salaries
Expenses
Vacation, Paid Holiday
Retirement and Unemployment Tax
Health and Welfare Benefits and Group
Life Insurance
Workman's Comp. and Liab. Ins.
Excise Tax
Estimated Cost of Labor
Estimated Cost of Labor and Material (Perm.)
33,383
3,704
3,589
8,583
1,749
4,006
377
6,337
317
321
380
55,391
7,355
13,251
677
1,421
3,41.9
663
1,590
155
21,176
28,531
316,602
15,830
3,804
18,996
96,811
26,169
10,407
28,654
4,841
11,617
2,235
355,232
180,734
535,966
-3-
4. Track (Intl. Rubber Crossings)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
Labor
Salaries
Expenses
Vacation, Paid Holiday
Retirement and Unemployment Tax
Health and Welfare Benefits and Group
Life Insurance
Workman's Comp. and Liab. Ins.
Excise Tax
Estimated Cost of Labor
Estimated Cost of Labor and Material (Perm.)
5. Loading Dock (Perm.)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
Labor
Salaries
Expenses
Vacation, Paid Holiday
Retirement and Unemployment Tax
Health and Welfare Benefits and Group
Life Insurance
Workman's Comp. and Liab. Ins.
Excise Tax
Estimated Cost of Labor
Estimated Cost of Labor. and Material (Perm.)
6. Paving (incl. removing 2 trees) (Perm.)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
341,382
17,069
17,069
20,483
137,449
15,490
14,776
35,159
7,683
16,494
2,062
9,464
473
461
568
2,769
1, 21.8
298
714
138
332
31
48,110
2,405
193
2,887
396,003
229,113
10,966
5,500
53,595
625,116
1.6, 466
-4 -
Paving (Incl. removing 2 trees) (Perm.) (cont'd)
Labor
Salaries 26,094
Expenses 2,609
Vacation, Paid Holiday 2,805
Retirement and Unemployment Tax 6,732
Health and Welfare Benefits and Group
Life Insurance 1,305
Workman's Comp. and Liab. Ins. 3,131
Excise Tax 309
Estimated Cost of Labor
66,405
Estimated Cost of Labor and Material (Perm.)
120,000
7. Remove Garage Building (Perm.)
Material
Handling at Storehouse
Transportation to Site of Job
Use Taxes
Estimated Cost of Material
Labor
Salaries
1,863
Expenses
117
Vacation, Paid Holiday
200
Retirement and Unemployment Tax
482
Health and Welfare Benefits and Group
Life Insurance
93
Workman's Comp. and Liab. Ins.
223
Excise Tax
22
Estimated Cost of Labor
3,000
Estimated Cost of Labor and Material (Perm.)
3,000