Item # 15
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
June 20, 2023
TOPIC: Main Street Rehabilitation Project
AGENDA TITLE
Award a Construction Contract to All American Asphalt in the Amount of $2,014,055 for
the Main Street Rehabilitation from MacArthur Boulevard to Dyer Road and St. Gertrude
Place at Orange Avenue Project, with an Estimated Project Delivery Cost of $2,417,000
(Project No. 22-6988)(Project No. 23-6482) (General and Non -General Fund)
RECOMMENDED ACTION
1. Approve an amendment to the Fiscal Year 2022-23 Capital Improvement Program
to include $250,000 of funding in the General Fund for the Main Street
Rehabilitation from MacArthur Boulevard to Dyer Road and St. Gertrude Place at
Orange Avenue Project.
2. Authorize budget reallocation of $361,000 in unspent Roadway Maintenance and
Rehabilitation Account (SB-1) from the Euclid Rehabilitation from South City Limits
to McFadden Improvement (No. 20-6961) Project to construction funds for the Main
Street Rehabilitation from Macarthur Boulevard to Dyer Road and St. Gertrude
Place at Orange Avenue Project (No. 22-6988) to complete the project funding
requirement.
3. Award a construction contract to All American Asphalt, the lowest responsible
bidder, in accordance with the base bid in the amount of $2,014,055, for
construction of the Main Street Rehabilitation from MacArthur Boulevard to Dyer
Road and St. Gertrude Place at Orange Avenue Project, for the term beginning
June 20, 2023, and ending upon project completion, and authorize the City
Manager to execute the contract subject to non -substantive changes approved by
the City Manager and the City Attorney.
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$2,417,000, which includes $2,014,055 for the construction contract, $201,406 for
contract administration, inspection and testing, and a $201,539 project contingency
for unanticipated or unforeseen work.
Main Street Rehabilitation Project
June 20, 2023
Page 2
5. Determine that the recommended actions are exempt from further review in
accordance with the California Environmental Quality Act as Categorical Exemption
Environmental Review No. ER-2023-57 was filed for the project.
DISCUSSION
The City's Pavement Management Program identified Main Street Rehabilitation from
MacArthur Boulevard to Dyer Road and St. Gertrude Place at Orange Avenue Project
as a high priority for street rehabilitation (Exhibit 1). Based on the adopted Pavement
Management Program, the pavement has deteriorated due to weather, age, and wear -
and -tear from heavy usage vehicles. The improvements include the removal and
replacement of failed asphalt pavement and the replacement of damaged concrete
curb, gutters, sidewalks, and curb ramps, and installation of traffic loops, traffic stripes,
pavement markings, curb extensions, and underground collapsed drain culvert at the
intersection of St. Gertrude Place and Orange Avenue. Once completed, these
improvements will enhance the ride quality and visual appearance of the street, and
comply with the Americans with Disabilities standards.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, the City notified a total of 859
regional vendors via PlanetBids, many of which are Santa Ana based. Four vendors
requested bidding documents, and a total of four bids were received. No bids were
received from Santa Ana contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on April 17, 2023 and April 24, 2023. The project was also advertised in
PlanetBids from April 17, 2023 through May 2, 2023. Bids were received electronically
via PlanetBids on May 2, 2023.
Bid Results Summary
Rank
Bidder's Name
Location
Base Bid
1
All American Asphalt
Corona, CA
$2,014,055
2
R.J. Noble Company
Orange, CA
$2,162,340
3
Excel Paving Co.
Long Beach, CA
$2,486,175
4
Hardy & Harper, Inc.
Lake Forest, CA
$2,539,000
A total of four bids were received, and all were deemed responsive. All American
Asphalt, Inc. submitted the lowest responsive base bid in the amount of $2,014,055
(Exhibit 2). As specified in the bid documents, the lowest bid shall be determined on the
basis of the Base Bid. Based on the bid analysis and a contractor's reference check,
Main Street Rehabilitation Project
June 20, 2023
Page 3
staff recommends awarding the construction contract to All American Asphalt, in the
amount of the base bid totaling $2,014,055 (Exhibit 3).
All American Asphalt has worked on various projects for the City of Santa Ana
throughout the last several years. The most recent project is Local Street Preventative
Maintenance FY 2021-22.
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen
conditions. Construction administration and inspection includes construction
management, inspection of the contractor's work to ensure contract compliance,
workmanship, quality, and materials testing. As indicated in the Cost Analysis (Exhibit 4)
and as summarized in the table below, the estimated total construction delivery cost of
the project is $2,417,000.
Project Item
Total
Construction Contract
$2,014,055
Construction Administration, Inspection, Testing
$201,406
Contingencies
$201,539
Total Construction Delivery Cost
$2,417,000
In order to account for the widespread price increases in construction material, Staff
recommends reallocating $250,000 from Miscellaneous Stormdrain Repairs
Improvements FY 2022-23 (No. 23-6458) and $361,000 in unspent Road Maintenance
and Rehabilitation Account (SB-1) funds from Euclid Rehabilitation, South City Limit to
McFadden, Project (No. 20-6961).
Approval of this item will amend the FY 2022-23 Capital Improvement Program to
include the Main Street Rehabilitation from Macarthur Boulevard to Dyer Road and St.
Gertrude Place at Orange Avenue Project (Exhibit 5).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2023-57 was filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis, the total construction delivery cost of the project is
$2,417,000 which includes construction, contract administration, inspection, testing, and
an authorized contingency. During construction, if necessary, funds may be reallocated
between Construction Administration, Inspection, Testing and/or
Contingencies. Contingency may be increased to a maximum limit of 25% of the
Main Street Rehabilitation Project
June 20, 2023
Page 4
Construction Contract. The total construction delivery cost will not be exceeded without
Council Authorization. Monies will be reallocated from Project No. 20-6961 and No. 23-
6458 to fund this agreement. Project No. 22-6988 and Project No. 23-6482 are the
numbers assigned to the funding for tracking of all expenditures to deliver the
construction of this project.
The following table summarizes the funds budgeted and available for expenditure to
deliver construction of this project. Any remaining balances not expended at the end of
the fiscal year will be presented to City Council for approval of carryovers to FY 23-24.
Accounting Unit
Fund
Accounting Unit -
r
Year ea
- Account No.
Description
Account No.
Amount
(Project No.)
Description
Existing Budget(Excluding Design En ineerin
2022-23
05917665-66220
Select Street
HUTA Gas Tax —
$1,556,000
(22-6988)
Construction
RMRA, Improvements
Other Than Buildings
ADDITIONAL BUDGET/BUDGET REALLOCATION
2022-23
05717640-66220
Federal Clean
Federal Clean Water
$250,000
(From Proj. 23-
Water
Protection Enterprise -
6458 to 23-6482)
Protection
Improvements Other
Enterprise
Than Building
2022-23
01117620-66220
General Fund
PW-Traffic/
$250,000
(22-6988)
Transportation -
Service Enhancement
2022-23
05917665-66220
Select Street
HUTA Gas Tax —
(From Proj. 20-
Construction
RMRA, Improvements
$361,000
6961 to 22-6988)
Other Than Buildings
Total
$2,417,000
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Cost Analysis
5. CIP Project Sheet
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Kristine Ridge, City Manager
Exhibit 1
SANTAANA Project No. 22-6988.
ua1 Main Street Rehabilitation from MaCarthur Blvd. to
PUBLIC W7j I Dyer Road and St. Gertrude Place at Orange Ave.
i20m0MM
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation *
1,788
CY
$
$
209.00
373,692.0
2
Asphalt Concrete *
1,825
TN
$
$
171.00
312,075.0
3
Cold Mill (1.5")
238,100
SF
$
$
.30
71,430.0
4
Asphalt Rubber Hot Mix (ARHM) *
3,300
TN
$
$
141.00
465,300.0
5
PCC Sidewalk (T=4")
7,500
SF
$
$
12.00
90,000.00
6
Crushed Miscellaneous Base
800
TN
$
$
(CMB)*
40.00
32,000.00
7
PCC Driveway Approach (T=8")
600
SF
$
$
21.22
12,732.00
8
PCC Curb Ramp
1,300
SF
$ 33.72
$
43,836.00
9
PCC Curb and Gutter (Type A-2-
1,150
LF
$
80.00
$
92,000.0
8)*
10
PCC Curb and Gutter (Type A-2-
1,030
LF
$ 80.00
$
6)*
82,400.00
11
Cross-Gutter(T=9")
2,900
SF
$ 25.00
$ 72,500.00
12
Root Shave*
3
EA
$
$
1,000.00
3,000.00
Adjust Water Valve Frame and
36
EA
$
$
[_13
Cover
951.00
34,236.00
P-1 of P-17
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
Item
Description
Qty
Unit
Unit Price
Amount
14
Furnish and Install Water Meter
4
EA
$
$
Frame and Cover
1,048.00
4,192.00
15
Adjust Manhole Frame and Cover
16
EA
$
$
1,048.00
16,768.0
16
Adjust Manhole Frame and Cover
9
EA
$
$
(O.C.S.D.)
1,720.00
15,480.00
17
Adjust Manhole Frame and Cover
I
EA
$
$
(I.R.W.D.)
1,720.00
1,720.00
18
Furnish and Install New #6 Pull
10
EA
$
$
Box
1,240.00
12,400.00
19
Adjust Water Vault Frame and
3
EA
$
$
Cover
5,400.00
16,200.00
20
Construct Parkway Culvert
3
EA
$
$
(Type B) *
1,400.00
4,200.00
21
Construct Parkway Culvert
1
EA
$
(Type A)
200.00
8,200.00
22
Furnish and Install Traffic Loops
57
EA
$
$
Type D f
511.00
29,127.00
23
Furnish and Install Traffic Loops
118
EA
$
$
Type E t
430.00
50,740.00
24
Adjust Survey Monument Frame
3
EA
$
$
and Cover
806.00
2,418.00
25
Project Advertisement Sign
I
EA
$
$
2,472.00
2,472.00
26
Construction Permit
1
LS
$9,708
$9,708
27
Signing and Striping
I
LS
$
$
51,467.00
51,467.00
28
Remove Existing Culvert (St.
I
LS
$
$
Gertrude Pl. & Orange Ave.)
31,000.00
31,000.00
29
As -Built Plans
1
LS
$5,000
$5,000
TOTAL BASE BID
$ 1,946,293.00
Item
Description
Qty
Unit
Unit Price
Amount
Bid
Rubberized Emulsion Aggregate
34
TN
$
$
Alternative
Slurry (REAS) TYPE 1I
1,993.00
67,762.00
One
P-2 of P-17
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
Total Base Bid + Bid Alternative One $ 2 014,055.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within six 60 working days, after the commencement date stated in the Notice
to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $5,000 per calendar day.
Name of Firm All American Asphalt
Signature of BIDDER
Title Michael Farkas, Secreta
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 of P-l7
EXHIBIT 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 22-6988 IN STREET REHABILITATION FROM MACARTHUR BOULEVARD TO DYER
ROAD & ST. GERTRUDE PLACE AT ORANGE AVENUE
This CONSTRUCTION CONTRACT is made and entered into this 201 day June 2023 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California (hereinafter "CITY"), and MI. American_Asphal�
(hereinafter "CONTRACTOR').
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Main Street Rehabilitation From Macarthur Boulevard to Dyee ''
Road & St. Gertrude Place at Orange Avenue Project (h re einafter referred to as the "WORK OF
IMPROVEMENT") identified in and in accordance with the Contract Documents prepared by the
City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not,to exceed Two Million, Fourteen Thousand and Fift�
Five Dollars($2z01405 OS 0 , as set forth and identified in the BID PROPOSAL, which is attached
hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit prices) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
rev. 09/01/2017 Page 1 of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website .
at: http://www.santa-ana.org/pwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (1000/0)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) ' Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
JENNIFER L. HALL
City Clerk
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
LI-A
JOSE MONTOYA
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
All American Asphalt
NAME: Michael Farkas
TITLE: Secretary
Page 3 of 3
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
docnment to which this certificate is attached. and not the truthfiilness. nccuracv. or validity of that document.
State of California
County of
Riverside
on June 2, 2023 before me, Kenona Nazari, Notary Public
Date Here Insert name and Title of the Officer
personally appeared Michael Farkas
Name(s) of Signet(ns
who proved to me on the basis of satisfactory evidence to be the
person(s) whose name(s) is/are subscribed to the within instrument
and acknowledged to me that he/she/theyexecuted the same in
his/hheil; authorized capacity(ies), and that by histhert4hei
signature(s) on the instrument the person(s), or the entity upon behalf
of which the person(s) acted, executed the instrument.
KENCINA NAZARI
Notary Public • California
I certify under PENALTY OF PERJURY under the laws of the State of
Riverside County n
*my
California that the fo 'ng paragraph is true and correct.
Commission ° 2318601
Comm. Expires Jan 10, 2024
WITNESS my and a official seal.
Signature
Place Notary Seal Above
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to person relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document Construction Contract Signature Page=City of Santa Ana
Document Date: June 20, 2023
Number of Pages: 3
Signer(s) Other Than Named Above:
John Montoya, Assistant City Attorney
Capacity(ies) Claimed by Signer(s)
Signer's Name: Michael Farkas
Signer's Name:
❑ Individual
❑ Individual /
X Corporate Officer — Title(s): Secretary
❑ Partner ❑ ❑ Limited ❑ General
RIGHT THUMBPRINT
❑ Attorney in Fact
❑ Trustee Top of thumb here
❑ Other:
Signer is Representing:
❑ Corporate Officer — Titl
❑ Partner ❑ ❑ Limited ❑ G neral
❑ Attorney in Fact
❑ Trustee
❑ Other:
Signer is Representing:
Exhibit A
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation *
1,788
CY
$
$
209.00
373,692.0
2
Asphalt Concrete *
1,825
TN
$
$
171.00
312,075.0
3
Cold Mill (1.5")
238,100
SF
$
$
.30
71,430.0
4
Asphalt Rubber Hot Mix (ARHM) *
3,300
TN
$
$
141.00
465,300.00
5
PCC Sidewalk (T=4")
7,500
SF
$
$
12.00
90,000.00
6
Crushed Miscellaneous Base
800
TN
$
$
(CMB)*
40.00
32,000.00
7
PCC Driveway Approach (T=8")
600
SF
$
21.22
$
12,732.00
8
PCC Curb Ramp
1,300
SF
$ 33.72
$
43,836.00
9
C Curb and Gutter (Type A-2-
PCC
1,150
LF
$ 80.00
$ 92,000.0
10
PCC Curb and Gutter (Type A-2-
1,030
LF
$ $0.00
$
6)*
82,400.00
11
Cross -Gutter (T=9")
2,900
SF
$ 25.00
$ 72,500.00
12
Root Shave*
3
EA
$
$
1,000.00
3,000.00
13
Adjust Water Valve Frame and
36
EA
$
$
Cover
1
951.00
34,236.00
P-1 of P-17
Exhibit A
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
Item
Description
Qty
Unit
Unit Price
Amount
14
Furnish and Install Water Meter
4
EA
$
$
Frame and Cover
1,048.00
4,192.00
15
Adjust Manhole Frame and. Cover
16
EA
$
$
1,048.00
16,768.0
16
Adjust Manhole Frame and Cover
9
EA
$
$
(O.C.S.D.)
1,720.00
15,480.00
17
Adjust Manhole Frame and Cover
I
EA
$
$
(I.R.W.D.)
1,720.00
1,720.00
18
Furnish and Install New #6 Pull
10
EA
$
$
Box
1,240.00
12,400.00
19
Adjust Water Vault Frame and
3
EA
$
$
Cover
5,400.00
16,200.00
20
Construct Parkway Culvert
3
EA
$
$
(Type B) *
1,400.00
4,200.00
21
Construct Parkway Culvert
1
EA
$
(Type A)
200.00
8,200.00
22
Furnish and Install Traffic Loops
57
EA
$
$
Type D 1'
511.00
29,127.00
23
Furnish and Install Traffic Loops
118
EA
$
$
Type E t
430.00
50,740.00
24
Adjust Survey Monument Frame
3
EA
$
$
and Cover
806.00
2,418.00
25
Project Advertisement Sign
1
EA
$
$
2,472.00
2,472.00
26
Construction Permit
1
LS
$9,708
$9,708
27
Signing and Striping
I
LS
$
$
51,467.00
51,467.00
28
Remove Existing Culvert (St.
1
LS
$
$
Gertrude Pl. & Orange Ave.)
31,000.00
31, 000.00
29
As -Built Plans
1
LS
$5,000
$5,000
TOTAL BASE BID
$1,946,293.00
Item
Description
Qty
Unit
Unit Price
Amount
Bid
Rubberized Emulsion Aggregate
34
TN
$
$
Alternative
Slurry (REAS) TYPE II
1,993.00
67,762.00
One
P-2 of P-17
Exhibit A
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6988
MAIN STREET REHABILITATION FROM MACARTHUR BLVD TO DYER RD
ST. GERTRUDE PLACE AT ORANGE AVENUE
Total Base Bid + Bid Alternative One $
2,014,055.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within sixty (60) working days after the commencement date stated in the Notice
to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $5,000 per calendar day_
Name of Firm All American Asphalt
Signature of BIDDER
Title Michael Farkas, Secretary
(If an individual, so state. If a firm or co partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 of P-17
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 22-6988: Main Street Rehabilitation from
MaCarthur Blvd. to Dyer Road and St. Gertrude Place at Orange Ave. Project
Construction Contract
$
2,014,055.00
Contract Administration, Inspection and Testing
$
201,406.00
Contingencies
$
201,539.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$
2,417,000.00
PROJECT TITLE:
Main Street Rehabilitation:
MacArthur to Dyer
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP k
N
CITY OF SANTA ANA FY 22/23CIP EXHIBIT 5
CAPITAL IMPROVEMENT PROJECT WORKSHEET 3
PROJECT DESCRIPTION:
Roadway reconstruction along with miscellaneous concrete repairs
to address accessibility and drainage issues along this segment of
roadway.
PROJECT NEED:
This segment of Main Street has been identified as a priority by the
City's Pavement Management System. The pavement is deteriorating
due to weather, age, and heavy usage.
PROJECT COSTS FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 FY 27128 FY 28129
Construction 611,000 - - - - - -
Engineering - -
TOTAL 611,000 - - - - - -
SOURCE OF FUNDS FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 FY 27128 FY 28129
GENERAL FUND 250,000 -
RMRA SB1 361,000 _
TOTAL 611,000 -
AGENCY: DIVISION: CONTACT: DATE:
Public Works Design Engineering Gilbert Castillo, Senior Engineer 05-Jun-2023