Item # 13
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
March 21, 2023
TOPIC: Time Extension of Measure M2 CTFP Grant Funds
AGENDA TITLE
Approve Submittal of Request for Time Extension of the Measure M2 Comprehensive
Transportation Funding Program for Fairview Avenue Improvements from 9th Street to
16th Street and Fairview Street Improvements from Monte Carlo Drive to Trask Avenue
(Project No. 15-6827 and 23-6701) (Non-General Fund)
RECOMMENDED ACTION
Authorize the Public Works Agency to request a two-year time extension of Measure M2
Comprehensive Transportation Funding Program funding for Fairview Avenue
Improvements from 9th Street to 16th Street project (21-SNTA-ACE-3996) and for
Fairview Street Improvements from Monte Carlo Drive to Trask Avenue. (22-SNTA-
ACE-4020).
DISCUSSION
The Fairview Avenue Improvements from 9th Street to 16th Street project, and the
Fairview Street Improvements from Monte Carlo Drive to Trask Avenue project were
awarded a total of $4,546,590 in funds by the Orange County Transportation Authority
(OCTA) Measure M2 Comprehensive Transportation Funding Program (CTFP) for
Fiscal Year 2022-23. Both projects’ scopes include widening the roadway from the
existing four lanes to six lanes to provide adequate vehicular capacity within the City’s
northern limits in addition to sidewalks, wheel chair ramps, raised medians, and traffic
signal modifications.
The Fairview Avenue Improvements from 9th Street to 16th Street project is currently in
the design phase of the project. In accordance with CTFP guidelines, the construction
contract for this project must be awarded by June 30, 2023. Despite diligent efforts to
advance this project to the construction phase, additional time is required to secure
matching funds to close the funding gap due to inflation.
The Fairview Street Improvements from Monte Carlo Drive to Trask Avenue project is
currently in the design phase of the project. In accordance with CTFP guidelines, the
design contract for this project must be awarded by June 30, 2023. Despite diligent
Request for Delay for Measure M2 CTFP Funds
March 21, 2023
Page 2
3
3
0
8
efforts to finalize the design phase of this project, additional time is required to finalize
the project plans and specifications before a construction contract can be awarded.
CTFP guidelines provide a one-time, two-year extension of Measure M2 CTFP funding,
which will allow sufficient time to complete the outstanding project preparations for
construction. Approval of this request will safeguard against a potential lapse in grant
funding. The table below summarizes the request:
FISCAL IMPACT
If the Recommended Action is not approved, the City will relinquish $4,546,590 in
awarded construction grant funding that will expire.
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency
Approved By: Kristine Ridge, City Manager
Project Name Resolution for
Application
Funding
Amount
OCTA Board
Approval /
Programmed
FY
Extension
Request
Fairview Ave.
Improvements from 9th
Street to 16th Street
November 17, 2020
Res. No. 2020-084
$3,721,590 May, 2021
FY 2022-23
2-yr Time
Extension
Fairview St. Improvements
from Monte Carlo Dr. to
Trask Ave.
November 16, 2021
Res. No. 2021-068
$825,000 May, 2022
FY 2022-23
2-yr Time
Extension