December 7, 2021
TOPIC: Local Street Curb Ramp Improvements
AGENDA TITLE:
Amendments to the FY 2021-22 Capital Improvement Program adding the Local Street
Curb Ramp Improvements FY 2021-22 Project with a budget of $554,582 in Community
Development Block Grant (CDBG) funds; Award a Construction Contract to Nobest
Incorporated in the Amount of $299,090 for the Local Street Curb Ramp Improvements
FY 2021-22 Project with an Estimated Project Delivery Cost of $554,582 (Project No. 22-
7537) (Non -General Fund)
RECOMMENDED ACTION
1. Approve an amendment to the Fiscal Year 2021-22 Capital Improvement Program
adding the Residential Street Repair Program FY 2021-22 Project with a budget of
$554,582 in Community Development Block Grant (CDBG) fund.
2. Award a construction contract to Nobest Incorporated, the lowest responsible bidder,
in accordance with the base bid in the amount of $299,090, for construction of the
Local Street Curb Ramp Improvements FY 2021-22, for the term beginning January
3, 2022 and ending upon project completion, and authorize the City Manager to
execute the contract subject to non -substantive changes approved by the City
Manager and the City Attorney.
3. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$554,582, which includes $299,090 for the construction contract, $44,863.50 for
contract administration, inspection and testing, and a $210,628.50 project contingency
for unanticipated or unforeseen work.
DISCUSSION
This work includes installing ADA curb ramps at various locations in the City of Santa
Ana, adjacent to Santa Anita, Winsor Village North, Centennial Park, and New Horizon
neighborhoods (Exhibit 1). The improvements include replacement of damaged and
deteriorated concrete sidewalk, and installation of curbs, gutters, and ADA ramps. All
works referenced in the recommended action provides the total financing for the project.
Local Street Curb Ramp Improvements
December 7, 2021
Page 2
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, the City notified a total of
250 regional vendors via PlanetBids, many of which are based in Santa Ana. Thirty -Five
vendors requested bidding documents, and a total of eight bids were received. Bids were
not received from any Santa Ana contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on September 29 and October 6, of 2021. The project was also advertised in
PlanetBids from September 28, 2021 through October 26, 2021. Bids were received
electronically via PlanetBids on October 26, 2021.
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
Nobest Incorporated
Westminster
$299,090.00
2
Carter Enterprises Group
Costa Mesa
$332,960.00
3
CJ Concrete Construction,
Santa Fe
$364,580.00
Inc.
Springs
4
EBS Concrete Construction
Corona
$441,067.00
Inc.
5
PUB Construction, Inc.
Diamond Bar
$447,840.00
6
Vido Samarzich, Inc.
Rancho
Cucamonga
$475,830.00
7
CT&T Concrete Paving Inc.
Diamond Bar
$491,880.00
8
Diamond Construction &
La Habra
$596,140.00
Design
A total of 11 bids were received, and all were deemed responsive. Nobest Incorporated
submitted the lowest responsive base bid in the amount of $299,090.00 (Exhibit 3). As
specified in the bid documents, the lowest bid shall be determined on the basis of the
Base Bid. Nobest Incorporated has not performed pervious work for the City of Santa
Ana. Based on the bid analysis and a contractor's reference check, staff recommends
awarding the construction contract to Nobest Incorporated, in the amount of the base bid
totaling $299,090.00 (Exhibit 4).
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen conditions.
Construction administration and inspection includes construction management;
Local Street Curb Ramp Improvements
December 7, 2021
Page 3
implementation of the City's Community Workforce Agreement requirements; inspection
of the Contractor's work to ensure contract compliance, workmanship, and quality; and
materials testing. As indicated in the Cost Analysis (Exhibit 5) and as summarized in the
table below, the estimated total construction delivery cost of the project is $554,582. The
construction bids came in lower than anticipated. The contingency is higher to take
advantage of these lower costs and to maximize the allocation of CDBG funding as well
as to account for unknown and unanticipated conditions. This will allow additional curb
ramps to be completed beyond the anticipated scope.
Project Item
Total
Construction Contract
$299,090.00
Construction Administration, Inspection, Testing
$44,863.50
Contingencies
$210,628.50
TOTAL CONSTRUCTION DELIVERY COST IF$554,582.00
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2021-114 was filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project is $554,582 which includes construction, contract administration, inspection,
testing, and an authorized contingency. Funds for this project were appropriated in Fiscal
Year 2021-22 and are available for expenditure. Any remaining balances not expended
at the end of the fiscal year will be carried forward into FY 2022-23 for expenditure. Project
No. 22-7537 is the number assigned to the Project Plans and Specifications and the
Notice Inviting Bids.
The following table summarizes the funds budgeted and available for expenditure to
deliver construction of this project.
Accounting Unit
Fund
Accounting Unit -
r
Year ea
- Account No.
Description
Account No.
Amount
(Project No.)
Description
13518783-
Community
CDBG Program —
2021-22
66220
Development
Improvements Other
$554,582.00
(22-7537)
Block Grant
Than Buildings
Total
$554,582.00
Local Street Curb Ramp Improvements
December 7, 2021
Page 4
EXHIBIT(S)
1. Location Map
2. Amend FY2021-22 CIP Project Street
3. Bid Proposal
4. Construction Contract
5. Cost Analysis
Submitted By: Nabil Saba, Executive Dir Public Works
Approved By: Kristine Ridge, City Manager
I
SANTAANA Project No. 22-7537
PWi LOCAL STREET CURB RAMP
�J IMPROVEMENTS
PUBLIC WORKS AGENCY
�A oRAH,
o
T �
EXHIBIT 2
PROJECT TITLE:
Local Street Curb Ramp Improvements
PROJECT CATEGORY:
Street Improvements -
Curb, Gutter, Sidewalk Improvements
I (1(:ATInN MAP
CITY OF SANTA ANA FY 21/22 CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
This work includes installing ADA curb ramps at various
locations in the City of Santa Ana, adjacent to Santa
Anita, Winsor Village North, Centennial Park, and New
Horizon neighborhoods. The improvements include
replacement of damaged and deteriorated concrete
sidewalk; and installation of curbs, gutters, and ADA
ramps.
PROJECT NEED:
Concrete repair to severely damaged or missing curbs,
gutters, and wheelchair ramps
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction $ 554,582 -
TOTAL $ 554,582
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
CDBG Programs $$ 5�5�
TOTAL $ 554,582
AGENCY: DIVISION: CONTACT: DATE:
Public Works Agency Jason Gabriel, Principal Civil Engineer 15-Nov-2021
ADDENDUM NO. ONEEXHIBIT 2
CITY OF SANTA ANA PROJECT NO. 22-7537
PROPOSAL
PROJECT NO.: 22-7537
LOCAL STREET CURB RAMP IMPROVEMENTS
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Npbe* - hC.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Remove and Construct PCC Curb
13,500
SF
$
7�B
Ramp*
/
2
Remove and Construct PCC
680
SF
$ 9-0
�•
$
s/ yy64
Sidewalk (T=4")*
3
Remove and Construct PCC Curb &
450
LF
$ QD
$ 7 1?
Gutter (A-2-6)*
9
4
Remove and Construct PCC Cross
2,400
SF
$ iJ�' 0$
��q Qm
Gutter*
O�
p"/
5
Construction Permit
1
LS
$10,000
$10,000
ve
TOTAL BASE BID (Bid Items 1-5) $
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
P-1 of P-16
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-7537
ADDENDUM NO. ONE
PROJECT NO.22-7537
LOCAL STREET CURB RAMP IMPROVEMENTS
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within eighty SO working days after the commencement date stated in the Notice
to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $750 per calendar day.
Name of Firm No hP ray— --r-n
Signature of BIDDER
Title 12P e y', �/e.1 4-
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
/Mobs if Snr.
�ll /
d✓eilv- %1/o��a�af 1G _ -r>ee e ve r y
P-2 of P-16
1*10111:111EI!
CITY OF SANTA ANA
CONSTRUCTION CONTRACT AGREEMENT
PROJECT NO.: 22-7537
Local Street Curb Ramp Improvements
This CONSTRUCTION CONTRACT is made and entered into this 7`s day of December, 2021 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and existing
under the Constitution and laws of the State of California (hereinafter "CITY'), and Nobest Incorporated
(hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Local Street Curb Ramp Improvements (hereinafter referred to
as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contracts Documents
prepared by the City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Two Hundred Ninety -Nine Thousand
Ninety and No Cents ($299,090.00), as set forth and identified in the BID PROPOSAL, which is
attached hereto and incorporated herein as "Exhibit A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
1 of 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT AGREEMENT
PROJECT NO.: 22-7537
Local Street Curb Ramp Improvements
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL, (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
http://wwvv.santa-ana. oriz/t)wa/documents/C WA.
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, famish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to,
any of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
2 of 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT AGREEMENT
PROJECT NO.: 22-7537
Local Street Curb Ramp Improvements
of any of the obligations under the Contract Documents;
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST: CITY OF SANTA ANA
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:
JOHN FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
KRISTINE RIDGE
City Manager
CONTRACTOR: t.i t>815'5-r '
Company:
3 of 3
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 22-7537: Local Street Curb Ramp
Improvements
Construction Contract
$
299,090.00
Contract Administration, Inspection and Testing
$
44,863.50
Contingencies
$
210,628.50
TOTAL ESTIMATED CONSTRUCTION COSTS
1 $
554,582.00