Item # 20
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
June 1, 2021
TOPIC: Resolution for Fiscal Year 2021-2022 Senate Bill 1 Projects
AGENDA TITLE
Adopt a Resolution for Fiscal Year 2021-2022 Senate Bill 1 Local Streets and Roads
Projects in the estimated amount of $6,436,447 for Capital Improvement Projects (Non-
General Fund)
RECOMMENDED ACTION
Adopt a resolution affirming the Fiscal Year 2021-2022 SB-1 Projects List and anticipated
funding in the amount of $6,436,447, which is required to be submitted to the California
Transportation Commission for budgeting the Fiscal Year 2021-22 Capital Improvement
Program, as necessary for City eligibility to receive Road Maintenance and Rehabilitation
Account Funding.
DISCUSSION
Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes
of 2017), was passed by the Legislature and signed into law by the Governor in April 2017
to address basic road maintenance, rehabilitation, and critical safety needs on both the
state highway and the local streets systems. The funding guidelines specify that before
local agencies can receive their apportionment of Road Maintenance and Rehabilitation
Account (RMRA) funds in a given fiscal year, the adoption of a resolution with a list of
proposed projects is required (Exhibit 1).
Each RMRA-funded project must be specifically differentiated from the Highway Users
Tax Account funding, and project nominations must include a project description, specific
location, proposed schedule for its completion, and the estimated useful life. The
proposed projects are being incorporated into the FY 2021-22 Capital Improvement
Program Budget (Exhibit 2). The City is expected to receive an estimated $6,436,447 in
FY 2021-22 from RMRA funds and staff recommends the adoption of the resolution in
order to maintain eligibility.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with the action.
Resolution for Fiscal Year 21-22 Senate Bill 1 Projects
June 1, 2021
Page 2
1
7
5
5
FISCAL IMPACT
Pursuant to the California Transportation Commission’s Annual Reporting Guidelines for
Local Streets and Roads Funding, staff has identified five CIP projects to be funded with
anticipated FY 2021-22 RMRA revenues in the table shown below. The proposed FY
2021-22 CIP budget was prepared using the California Department of Finance RMRA
May 2021 estimate of $6,436,447.
Fiscal Year 2021/22 - SB1 Road Repair and Accountability Act Project List
PROJECT LOCATION DESCRIPTION COST
MAIN ST MACARTHUR BLVD TO DYER RD ROAD REHABILITATION $1,680,000
WESTMINSTER AV NEWHOPE ST TO HARBOR
BLVD
ROAD REHABILITATION $1,335,892
BRISTOL ST SANTA CLARA ST TO MEMORY
LN
ROAD REHABILITATION $940,000
GRAND AVE WARNER AVE TO EDINGER AVE ROAD REHABILITATION $1,668,221
GARNSEY BUSINESS
DISTRICT
VARIOUS LOCAL NON-
RESIDENTIAL STREETS
ROAD REHABILITATION $812,334
Grand Total: $6,436,447
EXHIBIT(S)
1. Resolution and Proposed FY 2021-2022 List of Projects
2. FY 2021-22 RMRA CIP Project Sheets
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency
Approved By: Kristine Ridge, City Manager
Resolution No. 2021-XXX
Page 1 of 5
RESOLUTION NO. 2021-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA ADOPTING A LIST OF PROJECTS TO BE
FUNDED BY SB 1: THE ROAD REPAIR AND
ACCOUNTABILITY ACT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines and
declares as follows:
A.Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017, was
passed by the Legislature and signed into law by the Governor in April 2017 in order to
address the significant multi-modal transportation funding shortfalls statewide.
B.SB 1 includes accountability and transparency provisions that will ensure
the residents of the City of Santa Ana are aware of the projects proposed for funding in
our community and which projects have been completed each fiscal year.
C.The City of Santa Ana must establish a list of all projects to receive funding
from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which
must include a description and the location of each proposed project, a proposed
schedule for the project’s completion, and the estimated useful life of the improvement.
D.The City will receive an estimated $6,, in RMRA funding in Fiscal
Year 2021-22 from SB 1.
E.This is the third year in which the City of Santa Ana is receiving SB 1 funding
and will enable the City to continue essential road maintenance and rehabilitation
projects, safety improvements, repairing and replacing aging bridges, and increasing
access and mobility options for the traveling public that would not have otherwise been
possible without SB 1.
F.The City used a Pavement Management System to develop the SB 1 project
list to ensure revenues are being used on the most high-priority and cost-effective projects
that also meet the priorities of the community for transportation investment.
G.The funding from SB 1 will help the City maintain and rehabilitate local
streets and roads and provide resources for similar projects in the future.
EXHIBIT 1
Resolution No. 2021-XXX
Page 2 of 5
H. The 2018 California Statewide Local Streets and Roads Needs Assessment
found that the City’s streets and roads are in a good condition, and this revenue will help
enhance the overall quality of its road system and over the next decade will help to
maintain streets and roads conditions.
I. The SB 1 project list and overall investment in the City’s local streets and
roads infrastructure, with a focus on basic maintenance, safety, and investing in complete
streets, will have significant benefits statewide.
Section 2. The City of Santa Ana adopts the following list of projects planned to
be funded with Road Maintenance and Rehabilitation Account (RMRA) revenues for Fiscal
Year 2021-22.
Project Name Location Description Proposed
Project
Completion
Estimated
Useful Life
Road Projects:
MAIN ST MACARTHUR BLVD TO DYER
RD
Preventative
Maintenance/Slurry
12/31/22 10 YR
WESTMINSTER
AVE
NEWHOPE ST TO HARBOR
BLVD
Road Rehabilitation 12/31/22 20 YR
BRISTOL ST SANTA CLARA ST TO MEMORY
LN
Road Rehabilitation 12/31/22 20 YR
GRAND AVE WARNER AVE TO EDINGER
AVE
Road Rehabilitation 12/31/22 20 YR
GARNSEY
BUSINESS
DISTRICT
VARIOUS LOCAL NON-
RESIDENTIAL STREETS
Road Rehabilitation 12/31/22 20 YR
Section 3. The following previously proposed and adopted projects may also
utilize previous Fiscal Year Road Maintenance and Rehabilitation Account revenues in their
delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is
reaffirming to the public and the State its intent to fund these projects with Road
Maintenance and Rehabilitation Account Revenues:
Resolution No. 2021-XXX
Page 3 of 5
Projects Continued from FY 20-21:
Project Name Location Description Proposed
Project
Completion
Estimated
Useful Life
Road Projects:
17th Street Fairview Street to Flower Street Road Rehabilitation //2 20 YR
17th Street Bristol Street to Flower Street Road Rehabilitation //2 20 YR
Alton Main Street to Standard Avenue Road Rehabilitation //2 20 YR
Fairview Street City Limit to Segerstrom Avenue Road Rehabilitation /1/2 20 YR
MacArthur
Boulevard
Fairview Street to Raitt Street Road Rehabilitation 2/1/2 20 YR
Projects Continued from FY 19-20:
Project Name Location Description Proposed
Project
Completion
Estimated
Useful Life
Road Projects:
Euclid Street McFadden Avenue to 1st Street Road Rehabilitation //2 20 YR
Euclid Street 1st Street to Hazard Avenue Road Rehabilitation //2 20 YR
MacArthur
Boulevard
Flower Street to Main Street Road Rehabilitation 2//2 20 YR
Euclid Street City Limit to McFadden Avenue Road Rehabilitation //2 20 YR
Main Street Warner Avenue to Edinger
Avenue
Road Rehabilitation 09/20/22 20 YR
Resolution No. 2021-XXX
Page 4 of 5
Projects Continued from FY 18-19:
Project Name Location Description Proposed
Project
Completion
Estimated
Useful Life
Road Projects:
Raitt Street McFadden Avenue to Civic
Center Drive
Road Rehabilitation 20 YR
Main Street Dyer Road to Warner Avenue Road Rehabilitation //20 YR
Main Street 1st Street to Civic Center Drive Preventative
Maintenance / Slurry
12/31/ 10 YR
1st Street City Limit to Newhope Street Preventative
Maintenance / Slurry
12/31/ 10 YR
McFadden
Avenue
Fairview Street to Raitt Street Road Rehabilitation 2// 20 YR
Section 4. This Resolution shall take effect immediately upon its adoption by
the City Council, and the Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
ADOPTED this 1st day of June, 2021.
_
Vicente Sarmiento
Mayor
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
By:
John M. Funk
Sr. Assistant City Attorney
Resolution No. 2021-XXX
Page 5 of 5
AYES: Councilmembers
NOES: Councilmembers
ABSTAIN: Councilmembers
NOT PRESENT: Councilmembers _
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, Daisy Gomez, Clerk of the Council, do hereby certify the attached Resolution No. 2021 -
_____ to be the original resolution adopted by the City Council of the City of Santa Ana on
___________, 2021.
Date:
Clerk of the Council
City of Santa Ana
CITY OF SANTA ANA FY 21/22CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Roadway reconstruction along with miscellaneous concrete repairs
to address accessibility and drainage issues along this segment of
roadway.
PROJECT NEED:
This segment of Main Street has been identified as a priority by the
City's Pavement Management System. The pavement is deteriorating
due to weather, age, and heavy usage.
PROJECT TITLE:
Main Street Rehabilitation:
MacArthur to Dyer
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works CIP Engineering Mike Ortiz, Senior Civil Engineer 11-May-2021
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction 1,556,000 ------
Engineering 124,000 ------
TOTAL 1,680,000 ------
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
RMRA SB1 1,680,000 ------
TOTAL 1,680,000 ------
CITY OF SANTA ANA FY 21/22CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Roadway reconstruction along with miscellaneous concrete repairs
to address accessibility and drainage issues along this segment of
roadway.
PROJECT NEED:
This segment of Westminster Avenue has been identified as a priority
by the City's Pavement Management System. The pavement is
deteriorating due to weather, age, and heavy usage.
PROJECT TITLE:
Westminster Avenue Rehabilitation:
Newhope to Harbor
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works CIP Engineering Mike Ortiz, Senior Civil Engineer 19-May-2021
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction 1,389,000 ------
Engineering 111,000 ------
TOTAL 1,500,000 ------
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
GAS TAX 164,108 ------
RMRA SB1 1,335,892 ------
TOTAL 1,500,000 ------
CITY OF SANTA ANA FY 21/22CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruction/resurfacing of existing pavement and
replacement/installation of missing or damaged, curbs, gutters,
sidewalks, driveway approaches, and wheelchair ramps along
Bristol Street between Santa Clara Avenue and Memory Lane.
PROJECT NEED:
This segment of roadway has been identified as a high priority by the
City's Pavement Management System. The pavement is deteriorating
due to weather, age, and heavy usage. Some of the adjacent curbs,
gutters, driveway approaches, curb ramps, and sidewalks are also in
various states of disrepair and require replacement.
PROJECT TITLE:
Bristol Street Rehabilitation: Santa
Clara to Memory Lane
PROJECT CATEGORY:
Arterial Improvements
Arterial Street Rehabilitation
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works CIP Engineering Sean Thomas, Senior Civil Engineer 07-May-2021
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction 870,000 ------
Engineering 70,000 ------
TOTAL 940,000 ------
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
RMRA SB1 940,000 ------
TOTAL 940,000 ------
CITY OF SANTA ANA FY 21/22CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruction/resurfacing of existing pavement and
replacement/installation of missing or damaged, curbs, gutters,
sidewalks, driveway approaches, and wheelchair ramps within this
segment of roadway.
PROJECT NEED:
The City's Pavement Management Program has been developed to
identify total deferred maintenance requirements for the City's arterial
network and to move toward preventative maintenance. As one of the
City's arterial streets, Grand Avenue pavement rehabilitation is
identified as a high priority in the Pavement Management Program.
PROJECT TITLE:
Grand Avenue Rehabilitation:
Warner to Edinger
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works CIP Engineering Kenny Nguyen, Senior Civil Engineer 07-May-2021
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction 1,544,221 ------
Engineering 124,000 ------
TOTAL 1,668,221 ------
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
RMRA SB1 1,668,221 ------
TOTAL 1,668,221 ------
CITY OF SANTA ANA FY 21/22CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruct the local interior roadway network within the Garnsey
Business District (GBD). The area is bordered by Dyer Road to the
north, Flower Street to the east, Main Street to the west, and Warner
Avenue to the south. The street segments for this project include
Garnsey Street from Dyer Rd to Warner Ave, Central Avenue from
Garnsey St to Birch St, Birch Street from End to Warner Ave,
Central Ave from Birch St to Main St, Broadway from Central Ave to
Warner Ave.
PROJECT NEED:
The interior roadway network of GBD has been identified as a priority
by the City’s Pavement Management System. The pavement is
deteriorating due to weather, age, and heavy usage
PROJECT TITLE:
Garnsey Business District
Improvements
PROJECT CATEGORY:
Street Improvements
Neighborhood Street Rehabilitation
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works Design Engineering Kenny Nguyen, Senior Civil Engineer 19-May-2021
PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
Construction 3,943,666 ------
Engineering 391,000 ------
TOTAL 4,334,666 ------
SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28
REFUSE MAINTENANCE 3,522,332 ------
RMRA SB1 812,334 ------
TOTAL 4,334,666 ------