HomeMy WebLinkAboutItem 13 - Approve Amendment to CIP and Appropriation Adjustment, Award Construction ContractPublic Works Agency
https://www.santa-ana.org/pw/
Item # 13
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
January 19, 2021
TOPIC: Approve Amendment to CIP and Appropriation Adjustment, Award Construction
Contract
AGENDA TITLE:
Approve an appropriation adjustment, approve an amendment to the Fiscal Year 2020-
21 Capital Improvement Program, and award a construction contract to Stephen Doreck
Equipment Rentals, Inc. in the amount of $1,126,670 for the Valley Adams Neighborhood
Water Main Improvements Phase 2 Project with an estimated total delivery cost of
$1,577,338 (Project No. 21-6457) (Non -General Fund)
RECOMMENDED ACTION
1. Approve an appropriation adjustment to recognize $1,577,338 in the Water Fund,
Public Works Water Revenue, Prior Year Carryforward revenue account and
appropriate the same amount to the Acquisition & Construction, Water Utility Capital
Projects, Water Capital Project expenditure account.
2. Approve an amendment to the Fiscal Year 2020-21 Capital Improvement Program
to include $1,577,338 in construction funds for the Valley Adams Neighborhood
Water Main Improvements Phase 2 project.
3. Award a construction contract to Stephen Doreck Equipment Rentals, Inc., the
lowest responsible bidder, in accordance with the base bid in the amount of
$1,126,670, for construction of the Valley Adams Neighborhood Water Main
Improvements Phase 2 Project, for the term beginning January 19, 2020 and ending
upon project completion, and authorize the City Manager to execute the contract
subject to nonsubstantive changes approved by the City Manager and the City
Attorney.
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$1,577,338, which includes $1,126,670 for the construction contract, $225,334 for
contract administration, inspection and testing; and a $225,334 project contingency
for unanticipated or unforeseen work.
DISCUSSION
Approve Amendment to CIP and Appropriation Adjustment, Award Construction Contract
{{meeting.date format="MMMM dd, yyyy"}}
Page 2
Public Works Water Resources staff monitors the condition of water main pipelines by
assessing critical factors such as history of breaks, pipe size, alignment, location, and
system redundancy to determine replacement priorities. The existing 6-inch diameter
cast iron water main in the Valley Adams Neighborhood, which was installed in the 1960s,
has been experiencing a number of significant breaks and leaks, and has been identified
for priority replacement (Exhibit 1). The proposed appropriation adjustment and Capital
Improvement Projects amendment provide for the replacement of these deteriorated and
undersized water facilities (Exhibit 2).
The water system improvements will include approximately 2,900 linear feet of new 8-
inch polyvinyl chloride water main, fire hydrants, water services, appurtenances, asphalt
concrete pavement, and traffic striping. Once completed, water service reliability and
general service quality will improve significantly. In addition, the potential for disruption
due to water main breaks will be substantially reduced.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was
advertised in the Orange County Register newspaper on September 18 and September
19, 2020. The project was also advertised in PlanetBids from September 17, 2020
through October 22, 2020. Bids were received electronically via PlanetBids on October
22, 2020.
A total of 263 vendors, including vendors in the City of Santa Ana, were notified of the
project via PlanetBids. Forty-seven vendors requested bidding documents and nine
responsive bids were received. Bids were not received from any Santa Ana contractors.
Stephen Doreck Equipment Rentals, Inc. submitted the lowest responsive bid in the
amount of $1,126,670 (Exhibit 3). Based on the bid analysis and a contractor's reference
check, staff recommends awarding the construction contract to Stephen Doreck
Equipment Rentals, Inc., in the amount bid (Exhibit 4).
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
Stephen Doreck Equipment Rentals,
Pico Rivera
$
Inc.
1,126,670.00
2
Excel Paving Co.
Long Beach
$
1,146,906.00
3
Colich & Sons L.P.
Gardena
$1,174,495.00
4
All Cities Engineering, Inc.
Jurupa Valley
$1,200,345.00
5
CHI Construction
Anaheim
$1,215,700.00
Approve Amendment to CIP and Appropriation Adjustment, Award Construction Contract
{{meeting.date format="MMMM dd, yyyy"}}
Page 3
RANK
BIDDER'S NAME
LOCATION
BASE BID
6
J.A. Salazar
La Habra
$1,225,523.80
7
Lonerock, Inc.
Irvine
$1,399,430.00
8
TE Roberts, Inc.
Orange
$1,486,860.00
9
Christensen Brothers General
Engineering
Apple Valley
$1,705,930.00
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen conditions.
Construction administration and inspection includes construction management;
implementation of the City's Community Workforce Agreement requirements; inspection
of the contractor's work to ensure contract compliance, workmanship, and quality; and
materials testing. As indicated in the Cost Analysis (Exhibit 5) and as summarized in the
table below, the estimated total construction delivery cost of the project is $1,577,338.
Project Item
Total
Construction Contract
$1,126,670
Construction Administration, Inspection, Testing
$225,334
Contingencies
$225,334
TOTAL CONSTRUCTION DELIVERY COST
$1,577,338
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2020-100 was filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project is $1,577,338, which includes construction, contract administration, inspection,
testing, design engineering, and an authorized contingency of $225,334. Approval of the
Appropriation Adjustment will recognize $1,577,338 in Public Works Water Revenue,
Prior Year Carryforward revenue account (No. 06017002-50001) and appropriate the
same amount into the Acquisition & Construction Fund, Water Utility Capital Projects,
Water Capital Project expenditure account (No. 06617647-66301). All funds are
scheduled for expenditure in Fiscal Year 2020-21.
Approve Amendment to CIP and Appropriation Adjustment, Award Construction Contract
{{meeting.date format="MMMM dd, yyyy"}}
Page 4
The following table summarizes the funds budgeted for expenditure to deliver
construction of this project.
Accounting
Accounting Unit -
Fiscal
Unit - Account
Fund
Account No.
Amount
Year
No.
Description
Project No.)Description
20
06617647-
Acquisition &
Water Utility Capital
21
66301
Construction
Projects, Water Capital
$1,577,338
21-6457
Project
Total
$1,577,338
EXHIBIT(S)
1. Location Map
2. Amended 20/21 CIP Sheet
3. Bid Proposal
4. Construction Contract
5. Cost Analysis
Submitted By:
Nabil Saba, Executive Dir Public Works
Approved By: Kristine Ridge, City Manager
C:minln r n n11
EXHIBIT 1
NOT TO SCALE
PROJECT LOCATION
SANTA ANA JC, 10N
CITY COUNCIL PROJECT 21-6457
PfuA AGENDA DATE VALLEY ADAMS NEIGHBORHOOD (PHASE 2) ( '� 1
FU�WOWSAGENV /�1 WATER MAIN IMPROVEMENTS
EXHIBIT 5
PROJECT TITLE:
Valley Adams Neighborhood Water
Main Improvements Project - Phase
2
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
IA/afar Imnrrniamanf z
LOCATION MAP A
N
CITY OF SANTA ANA FY20/21 CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Replacement of deteriorating 6" cast iron water main with
approximately 2,900 linear feet of new 8-inch polyvinyl chloride
water main, fire hydrants, water services, appurtenances, asphalt
concrete pavement, and traffic striping
F
OJECT NEED:
lacement of failing water mains and appurtenances to ensure
tem reliability and to protect water quality.
PROJECT COSTS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
Construction 1,577,338 - - - - - -
TOTAL 1,577,338 - - - - - -
SOURCE OF FUNDS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
WTR UTY CAPITAL 1,577,338 - - - - - -
PROJECTS
TOTAL 1,577,338 - - - - -
AGENCY: DIVISION: CONTACT: DATE:
Public Works Water Resources Armando Fernandez, Senior Civil Engineer 21-Dec-2020
CITY OF SANTA ANA
COMMUNITY WORKFORCE
AGREEMENT COMPLIANCE
REQUIRED
CONTRACT DOCUMENTS
FOR
PROJECT NO.21-6457
Valley Adams Neighborhood
Water Main Improvements Phase 2
PREPARED UNDER THE SUPERVISION OF:
MM
20 CIVIC CENTER PLAZA
CITY HALL - ROSS ANNEX
SANTA ANA, CA 92701
SANTA ANA
FPWA
PUMX WOWS AGENCY
Prospective bidders may obtain Bid Documents, Project Specifications and Plans via PlanetBids:
htts:llwww. ianetbids.coml ortaU ortal.cfm?Com an io= 137
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Stephen Doreck Equiment Rentals Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Mobilization / Demobilization (no
I
LS
$
$
more than 5% total bid)
QIO
�� QQ,
2
8" Class 305 AWWA C900 P.V.C.
2900
LF
$
$
Water Main
d bs.- 00
,
3
Construct 1" Water Service per City
fib
EA
$
$
Std. Plan 1401
'1 960. Ua
R tl'�$ 0.10
4
4
8" Resilient Wedge Gate Valve per
9
EA
$
$
City Std. Plan 1410
1f10AcS, 00
1 1AR15. 00
5
Fire Hydrant Assembly per City Std.
10
EA
$
$
Plan 1405
1 0� 670.
1 o b j .5-66. D
*6
1" Combination Air Vacuum Release
I
EA
$
$
Valve per City Std. Plan 1415
71Y,00. 00
7
Vertical Offset 8 Feet Deep per City
I
EA
$
$
Std. Plan 1413B
14,A so-0
o o
*8
Vertical Offset per City Std. Plan
5
EA
$
$
1413A or 1413B (As Needed)
31$ S0.
1 q, �, o 0
9
CCTV Inspection of Existing Sewer
2650
LF
$
$
Mains
`T. 0 0
1016 00. 00
10
CCTV Inspection of Existing Sewer
69
EA
$
$
Laterals
lqi�" , 0 0
B� ,� ,01
I I
Cold Mill (T = 1")
95400
SF
$
$
'A0
12
PCC Cross -Gutter Replacement
1400
SF
$
$
(1,00
A3 9100.00
13
PCC Curb & Gutter
60
LF
$
60.00
$
31b00.Q°
it/
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 2I-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
Item
Description
Qty
Unit
Unit Price
Amount
14
PCC Driveway Approach per City Std.
Plan 1112
225
SF
$
15-o 0
$
3' 3 7S_- Oo
15
4" PCC Sidewalk per City Std. Plan
150
SF
$
l o.00
$
1 00. 00
1104
16
Type "A" Culvert Per City Std. Plan
1
EA
j iIDCi.
$�/ 000.00
17
Unclassified Excavation
65
CY
$
$ 257 00
18
Asphalt Rubber Hot Mix (ARHM)
600
TN
$
oo
$
01000.0
19
Asphalt Rubber Aggregate Membrane
10600
SY
$
$.#0
$
v�96o01
-
20
Adjust Manhole Frame and Cover to
Finished Grade
12
EA
$
]1100.0
$
3,a00- 00
*21
Potholing (As -Needed)
10
EA
$
7 j'a�,1�
$
7/5'DO. nd
22
Striping And Pavement Markings
1
LS
$ �p�.
��o'jf
$ ��4,0
19,
23
Traffic Control and Traffic Control
Plans
1
LS
$
35, 00.00
$ -,
3 S, a40. V 0
24
As-Builts
1
LS
$
031000.
$
ts,ao6 °$
P'
P-2 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
TOTAL BASE BID a 670. 00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION O_F_IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within number fifty -five -five (55) working days after the commencement date stated in
the Notice to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $1,300 per calendar day.
Name of Firm
Signature of BIl
Title Vice President
(If an individual, so state. If a firm or co -partnership, state the firm naive and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 ofP-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles )
On October 22, 2020 before me, Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(q) whose name(t) is/#Vq
subscribed to the within instrument and acknowledged to me that hel004W executed the same in
his/,Ogg/y"f authorized capacity(o#), and that by his/Nf/their signature(4) on the instrument the
person(4), or the entity upon behalf of which the person(j) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
cr r SYLVIA V. 51ri1EN —,,'!I S
Notary Public - California
SI nature i ' Los Angeles County
9 (Seal) Commission 9 2257818
My comm. Expires Oct 8, 2022
Sylvia6b.entes (Notary Public)
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
BIDDER'S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the
Council with her signature and official seal noting hereon the action of approval of the Council,
signed by the Public Works Agency Executive Director or his/her duly authorized agent, and
signed by the City Attorney, denoting his approval of the form of this document, and its
execution, and when it or an exact copy of it has been either delivered to BIDDER or deposited
with the United States Postal Service properly addressed to the BIDDER with the correct postage
affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of
damages actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or
BIDDER'S bond substituted in Iieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation
under the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Firm Stephen Doreck Equiment RWals Inc.
Signature of BIDDER
Title Vice President
-Pablo Viramontes
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-4 of P-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles )
On October 22, 2020 before me, Sylvia Sifuentes(Notary Public
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(4) whose name(p) is/No
subscribed to the within instrument and acknowledged to me that he11H#/#Wy executed the same in
his/)79r/�"f authorized capacity(*#), and that by his/lfx/their signature(q) on the instrument the
person(q), or the entity upon behalf of which the person(§f) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature
Sylvia if en s (Notary Public)
SYLVIA V. SIFUENTES
a =� Natary Public - California
LOSAngelesCounty
Commission # 2257818
(Seal) My COMM, Expires oct 8, 2023
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
CONTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she
and all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: Stephen Doreck Equiment Rentals Inc.
Business Address: 9075 Telegraph Road, Pico Rivera, CA 90660
Business E-Mail Address: Pablo@dQ-reckconstruction.com
doreckconstruction.com
Telephone: 562.949.4949
State Contractor's License No. and Class: 665471-A
License Expiration Date: 02/2812022
State Dept. of Industrial Relations (DIR)
Registration No.: 1000011335
State Dept. of Industrial Relations IR)
Registration Expi, n,Date: , 06/30/23
Signed:
Title: Vice President
-Pablo Viramontes
P-5 of P-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles )
On October 22, 2020 before me, Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(j) whose name(p) is/Avg
subscribed to the within instrument and acknowledged to me that he1$H#/#Wy executed the same in
hisf,f4yof authorized capacity(op), and that by his/Nf/their signature(q) on the instrument the
person(q), or the entity upon behalf of which the person(q) acted, executed the instrument.
certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal. t, SYLVIAV. SIFUENTES
Notary Public - California
x Los Angeles County
Commission # 2257818
Ay Comm. Expires Oct 8, 2fl22
Signatur � (Seal)
Sylvi e es (Notary Public}
State of California Back to DIR>> (https:l/www.dir,ca.gov/)
s� Department of Industrial Relations
(https:li, r.ca.gov/)
...Rana,«§ •-• - .
Contractor Information Registration History
Legal Entity Name Effective Date Expiration Date
STEPHEN DORECK EQUIPMENT RENTALS, INC.
07112/18
06/30/19
Legal Entity Type
Corporation
06/22/17
06/30/18
Status
Active
07107/16
06/30/17
Registration Number
08109/15
06/30/16
1000011335
Registration effective date
02/23115
06730/15
07/01/20
Registration expiration date
07/01/19
06/30/20
06/30/23
Mailing, Address
07/01/20
06/30/23
9075 TELEGRAPH ROAD PICO RIVERA 90660 CA...
Physical Address
9075 TELEGRAPH ROAD PICO RIVERA 90660 CA...
Email Address
pa blo@du reckconstructio n.co m
Trade Name/DBA
DORECK CONSTRUCTION
STEPHEN DORECK EQUIPMENT RENTALS, INC.
License Numbers)
CSLB:665471
CSLB:665471
Legal Entity Information
Corporation Entity Number:
2982502
Federal Employment Identification Number:
208858954
President Name:
CATHERINE R. DORECK
Vice President Name:
STEPHEN L. DORECK
Treasurer Name:
PABLO VIRAMONTES
Secretary Name:
PABLO VIRAMONTES
CEO Name:
CATHERINE R. DORECK
Agency for Service:
Agent of Service Name: STEPHEN L. DORECK
Agent of Service Mailing Address: 8026 E. TARMA STREET LONG REACH 90808 CA united States
Worker's Compensation
Do you lease employees through Professional Employer Organization (PEO)?: No
Please provide your current worker's compensation insurance information below:
PEO PEO PEO
PEO information Name Phone Email
Insured by Carrier
Policy Holder Name; STEPHEN DORECK EQUIPMENT F
Insurance Carrier: TRAVELERS INDEMNITY COMPAi
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well
as California Code of Regulations, Title S, Section 16,000, et seq., ("Prevailing Wage Laws"),
which require the payment of prevailing wage rates and the performance of other requirements
on "public works" and "maintenance" projects. Since the services are being performed as part of
an applicable "public works" or "maintenance" project, as defined by the Prevailing Wage Laws,
and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such
Prevailing Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at
the commencement of this Agreement. Contractor shall make copies of the prevailing rates of
per diem wages for each craft, classification or type of worker needed to execute the services
available to interested parties upon request, and shall post copies at the Contractor's principal
place of business and at the project site.
Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees
and agents free and harmless from any claim or liability arising out of any failure or alleged
failure to comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct
l-44mc of Firm
Signature of BI1
Title Vice President
(if an individual, so state)
P-6 of P-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles _)
On October 22, 2020 before me, Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(j) whose name( isloff
subscribed to the within instrument and acknowledged to me that he1jH#1y executed the same in
his1hgf1yW authorized capacity(oq), and that by hisllhqrltheir signature(j) on the instrument the
person(q), or the entity upon behalf of which the person(F/) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal. �-
ry 5YLVIAV. SIFUENTE5
Notary Public - Ca€ifornia
Los Angeles County
Commission # 7257810
My Comm. Expires Oct 8, 2022J
Signatur (Seal)
Syl ' fu rates (Notary Public)
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
1. City of Lomita 24300 Narbonne Ave Lomita CA 90717
Name and Address of Owner.
Tom Shabazi 310.325.7110
Name and Telephone Number of person familiar with project.
1,699,398.00 Water Main Replacement
Contract Amount Type of Work
03/2014
Date Completed
2. City of Manhattan Beach
Name and Address of owner. _
Edward Kao 310,802.5358
Name and Telephone Number of person familiar with project.
2,188,070.00 Water Main Replacement 07/2016
Contract Amount Type of Work Date Completed
3. City of Alhambra
Name and Address of owner.
Dennis Allen 626,570.3274
Name and Telephone Number of person familiar with project.
1,357,828.50
Contract Amount
Replacement of 4" and 14" Watermains 07/2017
Type of Work Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
CSBA - Commercial Surety Bond Agency - 1411 N. Batavia St Suite 201 Orange Ca
Arturo Ayala Ph:714) 516-1232 fx:714-516-9563
P-10 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
I. City of El Segundo 350 Main Street el Segundo CA 90245
Name and Address of Owner.
Lifan Xu 310.524.2368
Name and Telephone Number of person familiar with project.
680,745.00 Water Improvements
Contract Amount
Type of Work
2. City of Whittier 13230 Penn St, Whittier, CA 90602
Name and Address of owner.
1/2018
Date Completed
Raul Flore._562.567,9525
Name and Telephone Number of person familiar wi
990,245.00 th project.Main Line Replacement
t03/2020
Contract Amount
Type of Work
City of Covina 125 E College St, Covina, CA 91723
Name and Address of owner.
Rafael Fajardo 626.384,5489
Name and Telephone Number of person familiar with project.
2,603,255
Contract Amount
Date Completed
Water Main Replacement 03/2020
Type of Work
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
CSBA - Commercial Surety Bond Agency - 1411 N. Batavia St Suite 201 Orange Ca
Arturo Ayala Ph:714 ) 516-1232 Fx:714-516-9563
P-11 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
A. The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
B. The Contractor shall, in all solicitations or advertisements for employees placed by or on
behalf of the Contractor, state that all qualified applicants will receive consideration for
employment without regard to race, color, religion, sex, or national origin.
C. The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
D. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
E. The Contractor shall furnish all information and reports required by Executive Order 11246
of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or
pursuant thereto, and will permit access to his/her books, records, and accounts by the
administering agency and the Secretary of Labor for purposes of investigation, to ascertain
compliance with such rules, regulations, and orders.
F. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible
for further Government contracts or federally assisted construction contracts in accordance
with procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as
otherwise provided by law.
P-13 ofP-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
G. The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order
unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to
Section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be
binding upon each subcontract or purchase order as the administering agency may direct as
means of enforcing such provisions, including sanctions for noncompliance; provided,
however, that in the event the Contractor becomes involved in, or is threatened with,
litigation with a subcontractor or vendor as a result of such direction by the administering
agency, the Contractor may request that the United States enter into such litigation to protect
the interests of the United States.
H. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works vio ting this Section is subject to all the penalties imposed for a
violation of the Vr
.
Sig-ned: -Pablo Viramvntes
Title: Vice President
Firm: Stephen Doreck Equiment Rentals Inc.
Date; 10/22/2020
P-14 of P-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles
On October 22, 2020 before me, Sylvia Sifuentes(Notary Public
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(j) whose name() is/Avg
subscribed to the within instrument and acknowledged to me that he/$,Fg#IW executed the same in
his/) gg/t"f authorized capacity(j0#), and that by his/IVRt /their signature(j) on the instrument the
person(q), or the entity upon behalf of which the person(q) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Sig nature
Sylvi ge s (Notary Public)
i SYLV#A V, SIFUENTES
NOtafyPublic- Calfforn#a
�y Los Angeles County A
Commission ff 2257818
My Comm. Expires Oct 8, 2022
(Seal)
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
A. Apply to the joint apprenticeship committee administering the apprenticeship standards of
the craft or trade in the area of the site of the public work for a certificate approving the
contractor under the apprenticeship standards for the employment and training of apprentices
in the area or industry affected.
B. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
C. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like amo t to the lif is Apprenticeship Council.
Signed: -Pablo Viramontes
Title: Vice President
Firm: Stephen Doreck Equiment Rentals Inc.
Date: 10/22/2020
P-15 of P-1 S
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles
On October 22, 2020 before me, Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(4) whose name(A) islAvg
subscribed to the within instrument and acknowledged to me that he/%,4#/W## executed the same in
his/hflr/�"f authorized capacity("), and that by his/Nfltheir signature(q) on the instrument the
person(q), or the entity upon behalf of which the person( acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
OP>, SYLVIAV. STUENTES
- Notary Pubdc - California
Los Angeles County A
Commission 9 2257818
° S i g n a t {Seal) My Comm. Expires Oct 8, 2022
u �� , A
Syl ' 'fu tes (Notary Public)
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
STATEMENT REGARDING "ANTI -KICKBACK" REQUIREMENTS
The undersigned is submitting this proposal for performing by contract the work required by
these bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repai of public work, to give up any part of the compensation to
which he/she is of i enti
Signed: -Pablo Viramontes
Title: Vice President
Firm: Stephen Doreck Equiment Rentals Inc.
Date: 10/22/2020
P-16 of P-18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles
On October 22, 2020 before me, _ Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(q) whose name( is/ggf/
subscribed to the within instrument and acknowledged to me that he/M#/ y executed the same in
his/PAT/tWf authorized capacity(lop), and that by his/of/their signature(j) on the instrument the
person(q), or the entity upon behalf of which the person(q) acted, executed the instrument.
1 certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
Sylvia �ent s ( �otaryPublic)
E °rye SYLVIA V. SIFUENTES
z= 3
Notary Public - California
Las Angeles Ccunty
Commission r 2257W
�[rFGaM^'
My Cornet. Expires Oct 8, 2022
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented
from bidding on, or completing a federal, state, or local government project because of a
violation of law or a safety regulation?
Yes No X -
If the answer is yes, explain the circumstances in the following space
P-17 ofP-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
STATEMENT REGARDING COMMUNITY WORKFORCE AGREEMENT CWA
REQUIREMENTS
This is to certify that the undersigned BIDDER, and subcontractors, have read and understood
the CWA entered into by and between the City of Santa Ana, the Los Angeles/Orange Counties
Building and Construction Trades Council, and the signatory Craft Councils and Local Unions,
effective as of September 1, 2017. The CWA is available at:
hqp://www.sa,nta-ana.org/2wa/documents/CWA.pdf
The undersigned BIDDER hereby agrees to comply with all terms and conditions of the CWA,
and is capable of completing construction of the project continuously, and without interruptions
or delays. If awarded any work covered by the CWA, BIDDER will also be required to sign the
Letter of Assent that appears as Attachment A to the CWA.
The undersigned BIDDER has also reviewed the Public Works Construction Permit and required
deposit described in Section 7-5a d the Notice of Inviting Bids.
Signed: Pablo Viramontes
Title: Vice President
Firer: Stephen Doreck Equiment Rentals Inc.
Date: 10/22/2020
P-18 of P- 18
ACKNOWLEDGMENT
A notary public or other officer completing this
certificate verifies only the identity of the individual
who signed the document to which this certificate is
attached, and not the truthfulness, accuracy, or
validity of that document.
State of California
County of Los Angeles )
On October 22, 2020 before me, _ Sylvia Sifuentes (Notary Public)
(insert name and title of the officer)
personally appeared Pablo Viramontes
who proved to me on the basis of satisfactory evidence to be the person(q) whose name(p) is/Avg
subscribed to the within instrument and acknowledged to me that he/M#/t+fll y executed the same in
his/PfffltWk authorized capacity(o#), and that by his/Nf/their signature(j) on the instrument the
person(j), or the entity upon behalf of which the person(q) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signatur (Seal)
Sylviatifues (Notary Public)
°k t e SYLVIA V, SIFUENns
</°��r �,- Notary PLIMC - CalifGMia
z Los Angeles County
Commission ; 2257818
r „°'�*� My Gomm- Expires Oct 8, 2022
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
This CONSTRUCTION CONTRACT is made and entered into this 19th day of January, 2021 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and existing
under the Constitution and laws of the State of California (hereinafter "CITY'), and Stephen Doreck
Equipment Rentals, Inc. (hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Valley Adams Neighborhood Water Main Improvements Phase
2 Project (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in
accordance with the Contract Documents prepared by the City's Public Works Agency and approved
by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed One Million One Hundred Twenty -Six
Thousand Six Hundred Seventy Dollars and No Cents ($1,126,670.00), as set forth and identified in
the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
rev.09101/2017 Page I of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http://www.santa-ana.ori4/pwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred. Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the fugal contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through Iegal counsel acceptable to CITY, from and against any Iiability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
Stephen Doreck Equipment Rentals, Inc.
NAME: A U ra m m4e-�5
TITLE: V C,+' for-K---75 �A+
Page 3 of 3
CITY OF SANTA ANA EXHIBIT A
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
BIDPROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Stephen Doreck Equiment Rentals Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
I
Mobilization/ Demobilization (no
1
LS
$
$
more than 5% total bid)
o
wroo$
�/ �
t�
2
8" Class 305 AWWA C900 P.V.C.
2900
LF
$
Water Main
b-1-10
LntJo0•
3
Construct 1" Water Service per City
68
EA
$
$
Std. Plan 1401
J1960. 00
Q j jja�j 0.00
4
8" Resilient Wedge Gate Valve per
9
EA
$
$
City Std. Plan 1410
Q105. 00
1$ . 00
5
Fire Hydrant Assembly per City Std.
10
EA
$
$
Plan 1405
101�+9�
r60.0
*6
1" Combination Air Vacuum Release
1
EA
$
$
Valve per City Std. Plan 1415
7tSIM. 00
7, 5-00. 0
7
Vertical Offset 8 Feet Deep per City
1
EA
$
$
Std. Plan 1413B
L 41A 5"0.0 C
0 0
'T8
Vertical Offset per City Std. Plan
5
EA
$
$
1413A or 1413B (_pis Needed)
3 $ j7'6. (V
t ql )Q• 0 {i
9
CCTV Inspection of Existing Sewer
2650
LF
$
$
Mains
Z). 00
10,600.00
10
CCTV Inspection of Existing Sewer
69
EA
$
$
Laterals
la$ . 0 0y�
_
5 .
11
Cold Mill (T — 1")
95400
SF
$
$
.A0
00
12
PCC Cross -Gutter Replacement
1400
SF
$
$
�. �0
s�3��j(�.l`�
13
PCC Curb &Gutter
60
LF
$
$
�0•D°
�
3,600.0
P-1 ofP-18
IV
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 2I-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
Item
Description
Qty
Unit
Unit Price
Amount
14
PCC Driveway Approach per City Std.
Plan1112
225
SF
$
15.00
$
3X`0Q
15
4" PCC Sidewalk per City Std. Plan
1104
150
SF
$
$
Ir Op. 00
16
Type "A" Calvert Per City Std. Plan
318
1
EA
$
(a 170Q.
$ r
f �Oj 0oo. Oft
17
Unclassified Excavation
65
CY
$
$
P�,oas: o0
18
Asphalt Rubber Hot Mix (ARAM)
600
TN
$ 4
$ 000.00
19
Asphalt Rubber Aggregate Membrane
10600
SY
$
$ 01
20
Adjust Manhole Frame and Cover to
12
EA
$
$
Finished Grade
!! i 60 o
! ?Jr ROO. 00
*21
potholing (As -Needed)
10
EA
$
$
75`0.00
22
Striping And Pavement Markings
l
LS
$
$
Pi700. Oc
Pi 100.0 0
23
Traffic Control and Traffic Control
Plans
1
LS
$
3,5 000,00
$ .,
�t 000. a o
24
As-Builts
I
LS
$
I TT 000.
$
15 DQ0• 01,
P-2 of P-18
iv
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 21-6457
VALLEY ADAMS NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
TOTAL BASE BID � i a 47,0q ® 0
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications,
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within number -five 55 workin da s after the commencement date stated in
the Notice to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $1.300 per calendar day.
Name of Firm
Signature of SI1
Title Vice President
(If an individual, so state. 1f a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 of P-18
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 21-6457: VALLEY ADAMS
NEIGHBORHOOD WATER MAIN IMPROVEMENTS PHASE 2
Construction Contract
$
1,126,670.00
Contract Administration
$
105,000.00
Inspection and Testing
$
120,334.00
Contingencies
$
225,334.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$
1,577,338.00