1 COOPERATIVE AGREEMENT NO. C-3-3023
2 BETWEEN
3 ORANGE COUNTY TRANSPORTATION AUTHORITY groi
4 AND
5 CITIES OF ANAHEIM, FOUNTAIN VALLEY, FULLERTON, GARDEN GROVE,AND SANTA ANA
6 FOR
7 HARBOR BOULEVARD INNOVATIVE CORRIDOR PROJECTS
8 THIS COOPERATIVE AGREEMENT (Agreement), is effective this day of
9 , 2024 ("Effective Date"), by and between the Orange County Transportation
10 Authority, 550 South Main Street, P.O. Box 14184, Orange California 92863-1584, a public corporation
11 of the State of California(herein referred to as"AUTHORITY")and the cities of Anaheim, Fountain Valley,
12 Fullerton, Garden Grove, and Santa Ana(hereinafter referred to as"PARTICIPATING AGENCIES")each
13 individually known as"Party" and collectively known as "Parties".
14 RECITALS:
15 WHEREAS, the AUTHORITY in cooperation with the PARTICIPATING AGENCIES submitted a
16 Strengthening Mobility and Revolutionizing Transportation ("SMART") Grants Program application on
17 November 18, 2022, Regional Early Action Planning ("REAP 2.0") application on May 9, 2023, and a
18 Transit and Intercity Rail Capital Program ("TIRCP") Cycle 6 application on February 10, 2023, for the
19 evaluation, study, and implementation of transit signal priority and technology enhancements of
20 signalized intersections along the AUTHORITY's Bravo! Route 543, between the Santa Ana Bus Base in
21 the City of Santa Ana and the Fullerton Transportation Center in the City of Fullerton, (hereinafter,
22 "PROJECT"); and
23 WHEREAS, the AUTHORITY's Board of Directors authorized the acceptance of the SMART,
24 REAP 2.0, and TIRCP funding awards on July 24, 2023; and
25 WHEREAS, the AUTHORITY intends to secure additional funding for PROEJCT as needed; and
26 /
Page 1 of 15
Distributed 9/12/2024
Accounting
CAMM
FPA
PM A Yang,J Trujillo
Vendor✓
CAMM M Bornman
1 COOPERATIVE AGREEMENT NO. C-3-3023
2 BETWEEN
3 ORANGE COUNTY TRANSPORTATION AUTHORITY
4 AND
5 CITIES OF ANAHEIM, FOUNTAIN VALLEY, FULLERTON, GARDEN GROVE,AND SANTA ANA
6 FOR
7 HARBOR BOULEVARD INNOVATIVE CORRIDOR PROJECTS
8 THIS COOPERATIVE AGREEMENT (Agreement), is effective this 9th day of
g September , 2024 ("Effective Date"), by and between the Orange County Transportation
10 Authority, 550 South Main Street, P.O. Box 14184, Orange California 92863-1584, a public corporation
11 of the State of California(herein referred to as"AUTHORITY")and the cities of Anaheim, Fountain Valley,
12 Fullerton, Garden Grove, and Santa Ana(hereinafter referred to as"PARTICIPATING AGENCIES")each
13 individually known as"Party" and collectively known as "Parties".
14 RECITALS:
15 WHEREAS, the AUTHORITY in cooperation with the PARTICIPATING AGENCIES submitted a
16 Strengthening Mobility and Revolutionizing Transportation ("SMART") Grants Program application on
17 November 18, 2022, Regional Early Action Planning ("REAP 2.0") application on May 9, 2023, and a
18 Transit and Intercity Rail Capital Program ("TIRCP") Cycle 6 application on February 10, 2023, for the
19 evaluation, study, and implementation of transit signal priority and technology enhancements of
20 signalized intersections along the AUTHORITY's Bravo! Route 543, between the Santa Ana Bus Base in
21 the City of Santa Ana and the Fullerton Transportation Center in the City of Fullerton, (hereinafter,
22 "PROJECT"); and
23 WHEREAS, the AUTHORITY's Board of Directors authorized the acceptance of the SMART,
24 REAP 2.0, and TIRCP funding awards on July 24, 2023; and
25 WHEREAS,the AUTHORITY intends to secure additional funding for PROEJCT as needed; and
26 /
Page 1-of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 WHEREAS, the AUTHORITY intends to issue procurements to award contracts for the study,
2 and implementation of the PROJECT; and
3 WHEREAS, the PROJECT will include approximately sixty (60) traffic signalized intersections
4 along the 12-mile Harbor Boulevard Bravo! Route 543 corridor as identified in the SMART, REAP 2.0,
5 and TIRCP applications (hereinafter, "APPLICATIONS"); and
6 WHEREAS, based on the AUTHORITY's Board of Directors approval of grant awards, the
7 AUTHORITY agrees to implement the PROJECT per the APPLICATIONS; and
8 WHEREAS, the PROJECT will include an innovative Transit Signal Priority(TSP) solution and
9 Intelligent Transportation System (ITS) elements as identified in the APPLICATIONS and other
10 associated systems (hereinafter collectively referred to as "ITS ELEMENTS"), that will be evaluated,
11 constructed, and/or installed and implemented as part of the PROJECT; and
12 WHEREAS, the AUTHORITY agrees to work with PARTICIPATING AGENCIES to coordinate
13 the inclusion of other ITS ELEMENTS that should be installed before or at the same time as the
14 construction of the PROJECT that the Parties deemed necessary for the essential operation of the
15 Harbor Boulevard corridor; and
16 WHEREAS, the AUTHORITY and each respective Party shall provide
17 in-house resources (staff hours) to provide various services in support of the PROJECT; and
18 WHEREAS, the AUTHORITY and the PARTICIPATING AGENCIES desire to enter into this
19 Agreement to implement the PROJECT; and
20 WHEREAS, this Agreement defines the specific terms, conditions, and funding responsibilities
21 between the AUTHORITY and the PARTICIPATING AGENCIES for the implementation of the
22 PROJECT; and
23 WHEREAS, the City of Anaheim's City Council approved this Agreement on the N/A day of
24 N/A 20 N/A
25 WHEREAS, the City of Fountain Valley's City Council approved this Agreement on the N/A
26 day of N/A , 20 N/A
Page 2 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 WHEREAS, the City of Fullerton's City Council approved this Agreement on the 18th day
2 of June 2024
3 WHEREAS, the City of Garden Grove's City Council approved this Agreement on the 28th
4 day of May 20 24
5 WHEREAS, the City of Santa Ana's City Council approved this Agreement on the 4th day
6 of June 2024 .
7 NOW, THEREFORE, it is mutually understood and agreed by the AUTHORITY and the
8 PARTICIPATING AGENCIES as follows:
9 ARTICLE 1. COMPLETE AGREEMENT
10 A. This Agreement, including any attachments incorporated herein and made applicable by
11 reference, constitutes the complete and exclusive statement of the term(s) and conditions(s) of this
12 Agreement between the AUTHORITY and PARTICIPATING AGENCIES and it supersedes all prior
13 representations, understandings, and communications. The invalidity in whole or in part of any term or
14 condition of this Agreement shall not affect the validity of other term(s)or conditions(s)of this Agreement.
15 The above referenced Recitals are true and correct and are incorporated by reference herein.
16 B. The AUTHORITY's failure to insist on any instance(s) of PARTICIPATING AGENCIES'
17 performance of any term(s) or condition(s) of this Agreement shall not be construed as a waiver or
18 relinquishment of the AUTHORITY's right to such performance or to future performance of such term(s)
19 or condition(s), and PARTICIPATING AGENCIES' obligation in respect thereto shall continue in full force
20 and effect. Changes to any portion of this Agreement shall not be binding upon the AUTHORITY except
21 when specifically confirmed in writing by an authorized representative of the AUTHORITY by way of a
22 written amendment to this Agreement and issued in accordance with the provisions of this Agreement.
23 C. PARTICIPATING AGENCIES' failure to insist on any instance(s) of the AUTHORITY's
24 performance of any term(s) or condition(s) of this Agreement shall not be construed as a waiver or
25 relinquishment of PARTICIPATING AGENCIES' right to such performance or to future performance of
26 such term(s) or condition(s), and the AUTHORITY's obligation in respect thereto shall continue in full
Page 3 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 force and effect. Changes to any portion of this Agreement shall not be binding upon PARTICIPATING
2 AGENCIES except when specifically confirmed in writing by an authorized representative of
3 PARTICIPATING AGENCIES by way of a written amendment to this Agreement and issued in
4 accordance with the provisions of this Agreement.
5 ARTICLE 2. SCOPE OF AGREEMENT
6 This Agreement specifies the roles and responsibilities of the Parties as they pertain to the
7 subjects and projects addressed herein. Both the AUTHORITY and PARTICIPATING AGENCIES agree
8 that each will cooperate and coordinate with the other in all activities covered by this Agreement and any
9 other supplemental agreements that may be required to facilitate purposes thereof.
10 ARTICLE 3. RESPONSIBILITIES OF AUTHORITY
11 The AUTHORITY, as the lead agency, agrees to the following responsibilities for the
12 implementation of the PROJECT:
13 A. The AUTHORITY shall implement the PROJECT based on the intent of the usage in the
14 APPLICATIONS in accordance with the policies and procedures contained in the SMART, REAP, and
15 TIRCP grant program guidelines.
16 B. The AUTHORITY shall coordinate with the PARTICIPATING AGENCIES to ensure the
17 multi-phased implementation of the PROJECT includes input from the owning and operating agencies.
18 C. The AUTHORITY shall provide oversight to maintain inter-jurisdictional traffic signal
19 operational integrity between PROJECT and other similar type projects not older than three (3)years.
20 D. The AUTHORITY, or agents of the AUTHORITY, under this Agreement and upon
21 closeout of PROJECT, may perform a technical and/or field review to ensure that the grant program
22 guidelines, policies, and procedures were followed. Such a review may be performed within one hundred
23 and eighty(180)days after the PROJECT grant period is complete.
24 /
25 /
26 /
Page4of15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 E. The AUTHORITY, or agents of the AUTHORITY, shall manage, procure, implement, and
2 complete all aspects of the PROJECT as identified in the APPLICATIONS, including filing all
3 documentation necessary to comply with the requirements of the SMART, REAP, and TIRCP guidelines
4 and funding reporting.
5 F. The AUTHORITY, or its agents, shall collect all data necessary to deliver the PROJECT,
6 as specified in the APPLICATIONS.
7 G. The AUTHORITY, or its agents, shall coordinate outreach activities with
8 PARTICIPATING AGENCIES for the PROJECT.
9 H. The AUTHORITY, or its agents, shall study, evaluate, and recommend TSP and ITS
10 ELEMENTS best suited for the desired operation by each Party.
11 I. The AUTHORITY, or its agents, shall provide construction management oversight during
12 the construction of the PROJECT.
13 J. The AUTHORITY, or its agents, shall prepare the PROJECT reports, plans,and materials
14 that will be shared with PARTICIPATING AGENCIES and other PROJECT stakeholders.
15 ARTICLE 5. RESPONSIBILITIES OF THE PARTICIPATING AGENCIES
16 The PARTICIPATING AGENCIES agree to the following responsibilities for implementation
17 and funding of the PROJECT:
18 A. The PARTICIPATING AGENCIES shall provide a technical representative to
19 participate as a member of the PROJECT's Project Development Team (PDT).
20 B. The PARTICIPATING AGENCIES shall authorize the AUTHORITY to manage,
21 procure, and implement all aspects of the PROJECT.
22 C. The PARTICIPATING AGENCIES shall participate and support the PROJECT
23 implementation within the timeframe outlined in the APPLICATION and consistent with the SMART,
24 REAP, and TIRCP guidelines adopted by the AUTHORITY.
25 /
26 D. The PARTICIPATING AGENCIES shall provide AUTHORITY, or its agents all current
Page 5 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 intersection as-built drawings, all current intersections controller assembly plans as provided by the
2 manufacturer and modified by Party since original installation, local field master, local controller, and
3 Advanced Traffic Management System timing plans, TSP timing preferences, and other ITS related
4 data upon request.
5 E. PARTICIPATING AGENCIES shall waive all fees associated with any local agency
6 permits that may be required from the consultants, subconsultants, and/or service or equipment
7 providers hired by AUTHORITY for the PROJECT.
8 F. PARTICIPATING AGENCIES shall perform all field inspections and correspondence
9 during the construction of the PROJECT for improvements in their jurisdiction.
10 G. PARTICIPATING AGENCIES shall be responsible for the continued operations and
11 maintenance of all TSP and ITS ELEMENTS approved and implemented in their jurisdiction following
12 the completion of the PROJECT.
13 ARTICLE 6. DELEGATED AUTHORITY
14 The actions required to be taken by PARTICIPATING AGENCIES in the implementation of this
15 Agreement are delegated to their respective City Manager, or City Manager's designee, and the actions
16 required to be taken by the AUTHORITY in the implementation of this Agreement are delegated to the
17 AUTHORITY's Chief Executive Officer or Chief Executive Officer's designee.
18 ARTICLE 7. AUDIT AND INSPECTION
19 AUTHORITY and PARTICIPATING AGENCIES shall maintain a complete set of records in
20 accordance with generally accepted accounting principles. Upon reasonable notice, PARTICIPATING
21 AGENCIES shall permit the authorized representatives of AUTHORITY to inspect and audit all work,
22 materials, payroll, books, accounts, and other data and records of PARTICIPATING AGENCIES for a
23 period of five (5) years after final payment, final closeout, or until any on-going audit is completed,
24 whichever is later. For purposes of audit, the date of completion of this Agreement shall be the date of
25 AUTHORITY's payment of consultant's final billing (so noted on the paid invoice) under this Agreement.
26 AUTHORITY shall have the right to reproduce any such books, records, and accounts. The above
Page 6 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 provision with respect to audits shall extend to and/or be included in contracts with PARTICIPATING
2 AGENCIES' contractor(s).
3 ARTICLE 8. INDEMNIFICATION
4 A. To the fullest extent permitted by law, PARTICIPATING AGENCIES shall defend (at
5 PARTICIPATING AGENCIES' sole cost and expense with legal counsel reasonably acceptable to
6 AUTHORITY), indemnify, protect, and hold harmless AUTHORITY, and its officers, directors,employees,
7 and agents (collectively the "Indemnified Parties"), from and against any and all liabilities, actions, suits,
8 claims, demands, losses, costs,judgments, arbitration awards, settlements, damages, demands, orders,
9 penalties, and expenses including legal costs and attorney fees (collectively"Claims"), including but not
10 limited to Claims arising from injuries to or death of persons (PARTICIPATING AGENCIES' employees
11 included),for damage to property, including property owned by AUTHORITY, or from any violation of any
12 federal, state, or local law or ordinance, alleged to be caused by the negligent acts, omissions or willful
13 misconduct of PARTICIPATING AGENCIES, its officers, directors, employees or agents in connection
14 with or arising out of the performance of this Agreement.
15 B. To the fullest extent permitted by law, AUTHORITY shall defend (at AUTHORITY's sole
16 cost and expense with legal counsel reasonably acceptable to PARTICIPATING AGENCIES), indemnify,
17 protect, and hold harmless PARTICIPATING AGENCIES, including their officers, directors, employees,
18 and agents (collectively the "Indemnified Parties"), from and against any and all liabilities, actions, suits,
19 claims, demands, losses, costs,judgments, arbitration awards, settlements, damages, demands, orders,
20 penalties, and expenses including legal costs and attorney fees (collectively"Claims"), including but not
21 limited to Claims arising from injuries to or death of persons (AUTHORITY's employees included), for
22 damage to property, including property owned by PARTICIPATING AGENCIES, or from any violation of
23 any federal, state, or local law or ordinance, alleged to be caused by the negligent acts, omissions or
24 willful misconduct of AUTHORITY, its officers,directors,employees or agents in connection with or arising
25 out of the performance of this Agreement.
26
Page 7 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 C. The indemnification and defense obligations of this Agreement shall survive its expiration
2 or termination.
3 ARTICLE 9. ADDITIONAL PROVISIONS
4 A. Term of Agreement: This Agreement shall be in full force and effect through
5 December 31, 2028.
6 B. Amendment: This Agreement may be extended or amended in writing at any time by the
7 mutual consent of all Parties. No amendment shall have any force or effect unless executed in writing by
8 all Parties.
9 C. Termination: In the event any Party defaults in the performance of their respective
10 obligations under this Agreement or breaches any of the provisions of this Agreement, a non-defaulting
11 Party(s) shall have the option to terminate this Agreement upon thirty (30) calendar days prior written
12 notice to the Party in default.
13 D. Termination for Convenience: Any Party may terminate this Agreement for its
14 convenience by providing thirty (30) calendar days prior written notice of its intent to terminate for
15 convenience to the other Party.
16 E. Parties shall comply with all applicable federal, state, and local laws, statues, ordinances,
17 and regulations of any governmental authority having jurisdiction over the PROJECT.
18 F. Legal Authority: Parties hereto consent that they are authorized to execute this
19 Agreement on behalf of said Parties and that, by so executing this Agreement, the Parties hereto are
20 formally bound to the provisions of this Agreement.
21 G. Severability: If any term, provision, covenant, or condition of this Agreement is held to be
22 invalid, void or otherwise unenforceable, to any extent, by any court of competent jurisdiction, the
23 remainder of this Agreement shall not be affected thereby, and each term, provision, covenant, or
24 condition of this Agreement shall be valid and enforceable to the fullest extent permitted by law.
25 H. Counterparts of Agreement: This Agreement may be executed and delivered in any
26 number of counterparts,each of which, when executed and delivered shall be deemed an original and all
Page 8 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 of which together shall constitute the same agreement. Electronic signatures shall be permitted.
2 I. Assignment: Neither this Agreement, nor any of the Parties' rights, obligations, duties, or
3 authority hereunder may be assigned in whole or in part by any Parties without the prior written consent
4 of the other Parties in its sole and absolute discretion. Any such attempt of assignment shall be deemed
5 void and of no force and effect. Consent to one assignment shall not be deemed consent to any
6 subsequent assignment, nor the waiver of any right to consent to such subsequent assignment.
7 J. Governing Law: The laws of the State of California and applicable local and federal laws,
8 regulations, and guidelines shall govern this Agreement.
9 K. Litigation fees: Should litigation arise out of this Agreement for the performance thereof,
10 the court shall award costs and expenses, including attorney's fees, to the prevailing Party.
11 L. Notices: Any notices, requests, or demands made between the Parties pursuant to this
12 Agreement are to be directed as follows:
13 To ANAHEIM: To AUTHORITY:
14 City of Anaheim Orange County Transportation Authority
15 200 South Anaheim Boulevard 550 South Main Street
16 Anaheim, CA 92805 P. O. Box 14184
17 Orange, CA 92863-1584
18 Attention: John Thai Attention: Megan Bornman
19 Principal Traffic Engineer Senior Contract Administrator
20 Tel: (714) 765-5202 Tel: (714) 560-5064
21 Email: JThai(c�anaheim.net E-mail: mbornmanocta.net
22
CC: Alicia Yang
23 Project Manager
24 Tel: (714) 560-5362
25 Email: ayanq(a,octa.net
26
Page 9 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 To FOUNTAIN VALLEY: To FULLERTON:
2 City of Fountain Valley City of Fullerton
3 10200 Slater Avenue 303 West Commonwealth Avenue
4 Fountain Valley, CA 92708 Fullerton, CA 92832
5 Attention: Temo Galvez Attention: Stephen Bise
6 Deputy Director of Public Works/City Engineer Director of Public Works
7 Tel: (714) 593-4517 Tel: (714) 738-6852
8 Email: temo.galvez(c�fountainvalley.orq Email: Stephen.bise(�cityoffullerton.com
9 To GARDEN GROVE: To SANTA ANA:
10 City of Garden Grove City of Santa Ana
11
11222 Acacia Parkway Traffic Engineering Section/M-43
12
Garden Grove, CA 92840 20 Civic Center Plaza
13
Santa Ana, CA 92701
14
Attention: Dai Vu Attention: Nabil Saba
15
City Traffic Engineer Executive Director of Public Works
16
Public Works Department Tel: (714) 647-5654
17
Tel: (714) 741-5189 Email: Nsaba(a7santa-ana.orq
18
Email: daiv(a�ggcity.orq
19
M. Force Majeure: Any Party shall be excused from performing its obligations under this
20
Agreement during the time and to the extent that it is prevented from performing by an unforeseeable
21
cause beyond its control, including but not limited to: any incidence of fire, flood; acts of God;
22
commandeering of material, products, plants or facilities by the federal,state or local government; national
23
fuel shortage; or a material act or omission by the other Party, when satisfactory evidence of such cause
24
is presented to the other Party, and provided further that such nonperformance is unforeseeable, beyond
25
the control and is not due to the fault or negligence of the Party not performing.
26
/
Page 10 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 This Agreement shall be made effective upon execution by all Parties.
2 IN WITNESS WHEREOF, the Parties hereto have caused this Agreement No. C-3-3023 to be
3 executed as of the date of the last signature below.
4 CITY OF ANAHEIM ORANGE COUNTY TRANSPORTATION AUTHORITY
5
,i/'j)t'Z (-zzArs
6 By: By:
Rudy (mami Lydia Bilynsky
Director of Public Works Department Manager, Capital Projects
8
9 ATTEST: APPROVED AS TO FORM:
10
11 By: By:
r
Theresa Bass JamesM. Donich
12 City Clerk General Counsel
13
14
APPROVED AS TO FORM:
15 Robert Fabela, City Attorney
16
17 By:
Y
B n- Mo lekj
18 Deputy Q tyYAttorney
19
20
21 Dated:
22
23
f 24
25
26
Page 11 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 This Agreement shall be made effective upon execution by all Parties.
2 IN WITNESS WHEREOF, the Parties hereto have caused this Agreement No. C-3-3023 to be
3 executed as of the date of the last signature below.
4 CITY OF FOUNTAIN VALLEY
5
6 By: Maggiug 23,2024 13.14 PDT)
Maggie Le
7 City Manager
8
9 ATTEST:
10
11 By: Rick Miller(Aug 28,2024 07:34 PDT)
Rick Miller
12 City Clerk
13
APPROVED AS TO FORM
14
15
16 By:
Colin Burns
17 City Attorney
18
19 Dated:
20
21
22
23
24
25
26
Page 12 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 This Agreement shall be made effective upon execution by all Parties.
2 IN WITNESS WHEREOF, the Parties hereto have caused this Agreement No. C-3-3023 to be
3 executed. as of the date of the last signature below.
4 CITY OF FULLERTON
5
6 By:
Eric "evi
7 City Ma ger
8
9 ATTEST:
10
11 B,
12 Lucind it'ams
City rk
13
APPR ED AS P FORM
14 1
15 ejz, "r„` cn 6c 4 "gy:Aoart.._ //
16 Richard D. Jones
17 City Attorney
18
19 Dated: DO`2i ut
20
21
22
23
24
25
26
Page 13 of 15
u
DacusIgn Envelope ID:E1481EDC-1E17-400-13BF6-3C352A53CE4A
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 This Agreement shall be made effective upon execution by all Parties.
2 IN WITNESS WHEREOF, the Parties hereto have caused this Agreement No. C-3-3023 to be
3 executed as of the date of the last signature below,
4 CITY OF GARDEN GROVE
5 e -oocuSlgned by:
6 By: —
b1 Th14C1p242E...
7 City Manager
8
9 ATTEST:
10
DocuSlgnud by:
11 By fu t,Sa ?OM/MI
12 Fe 'PtSiniffoy
City Clerk
13
14 Dated: 7/31/2024
15
16
17
18
19
20
21
22
23
24
25
26
Page 14 of 15
COOPERATIVE AGREEMENT NO. C-3-3023
HARBOR BOULEVARD CONNECTED CORRIDOR PROJECTS
1 This Agreement shall be made effective upon execution by all Parties.
2 IN WITNESS WHEREOF,the Parties hereto have caused this Agreement No. C-3-3023 to be
3 executed as of the date of the last signature below.
4 CITY OF SANTA ANA
5
7a1--/a-4-,g
Alvaro Nunez
7 Acting City Manager
8
ATTEST:
9
10 0,
11 ennifer L. H. II
12
pity Clerk-
13 APPROVED AS TO FORM
14
15 By:
16 ,.„-'Jonathan T. Martinez-7%2
Assistant City Attorney