HomeMy WebLinkAbout23A - EUCLID ST. REHABILITATION
. REQUEST FOR
. COUNCIL ACTION
.
~
CITY COUNCIL MEETING DATE:
CLERK OF COUNCIL USE ONLY:
MARCH 1,2004
TITLE:
APPROVED
CONTRACT AWARD FOR EUCLID
STREET REHABILITATION FROM
THE SOUTH CITY LIMITS TO
MCFADDEN AVENUE (PROJECT NO.
1823)
~£4~
RECOMMENDED ACTION
0 As Recommended
0 As Amended
0 Ordinance on 1" Reading
0 Ordinance on 2nd Reeding
0 Implementing Resolution
0 set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Award a contract to R. J. Noble Company, the lowest responsible
. bidder, in accordance with unit bid prices in the estimated amount of
$483,934.25 for construction of Euclid Street Rehabilitation from the
south City limits to McFadden Avenue.
2. Approve a Funding Analysis with a total estimated construction cost
of $606,700.
DISCUSSION
Euclid Street is a north-south corridor, which is designated as a major
arterial highway in the City's Circulation Element of the General Plan.
The rehabilitation of Euclid Street between the South City Limits and
McFadden Avenue has been a long-term goal (Exhibit 1).
Several other segments of Euclid Street have been rehabilitated in
previous fiscal years. This project includes pavement rehabilitation,
sidewalk repair, curb and gutter, and handicapped access improvements.
Once completed, these improvements will enhance the ride quality, surfa~e
drainage, and visual appearance of the street.
The Notice Inviting Bids was advertised on December 9 and 10, 2003 and
bids were opened on January 9, 2004. A summary of the bid invitations
mailed, the bids received, and the bid results follows.
.santa Ana Contractors receiving notices:
Contractors requesting bidding documents:
Bids received:
Bids received from Santa Ana Contractors:
9
12
4
1
23A-1
Euclid Street Rehabilitation
Project No. 1823
March 1, 2004
Page 2
NAME OF BIDDER
CITY
BID AMOUNT
$483,934.25
488,077.50
510,473.50
563,859.00
1. R. J. Noble Company
2. Hardy & Harper, Inc.
3. Sequel Contractors, Inc.
4. palp Inc., dba Excel Paving
Orange
Santa Ana
Santa Fe Springs
Long Beach
A total of 4 bids were received and all were responsive. The lowest bid
was submitted by R. J. Noble Company, for $483,934.25, which is below the
Engineer's estimate of $537,000.
ENVIRONMENTAL IMPACT
After Completion of Environmental Review ER 2003-241, a Categorical
Exemption will be filed for this project pursuant to the California
Environmental Quality Act.
FISCAL IMPACT
The Funding Analysis shows a total estimated construction cost of
$606,700 for the project (Exhibit 2). Funds are available in the Select
Street Construction Fund (account no. 59-551-6631) and in the Measure M
Street Construction Fund (account no. 32-551-6631).
Já~~
Executive Director
Public Works Agency
¡:t;/ý
TO FUNDS AND ACCOUNTS:
Agency
K: \Construc:tion\RFCA-draft\1823 2004-03-01 45 WD
23A-2
MC FADDEN AVE
.
PROJECT UMfTS:
i ~
JoLTS
Iii
I
IœNI' AVE
i
I.EHWDTAVE
EXHIBrr 1
SANTA ANA TItle: CONTRACT AWARD FOR EUCUD
, P W A t ~~ STREET AEHABIUT A T1ON FROM
, 'MARCH 1, 2004 SOUTH CITY UMITS TO MCFADDEN
--- AVENUE (PROJECT 00.1823)
K'/f'roled8I~8dlve/~
23A-3
FUNDING ANALYSIS
PROJECT 1823
EUCLID STREET REHABILITATION
FROM SOUTH CITY LIMITS TO MCFADDEN AVENUE
Construction Contract
Contract Administration
$483,934
9,373
Inspection and Testing
Survey Staking
35,000
30,000
Contingencies
48,393
TOTAL ESTIMATED CONSTRUCTION COSTS
$606,700