AGREEMENT FOR ENGINEERING
SERVICES WITH METCALF & EDDY
CONTINUED TO
FILE NUMBER
RECOMMENDED ACTION
Direct the City Attorney to prepare and authorize the City Manager and
the Clerk of the Council to execute an agreement with Metcalf & Eddy in
the amount of $152,513 plus a contingency of $15,000 for a total project
amount not to exceed $167,513 for design of the West Pump Station
Facilities Upgrade Project.
DISCUSSION
In October 2004, the City was awarded an Environmental Protection Agency
(EPA) federal grant for improvements to the City's West Pump Station
Facility, (Exhibit 1). The improvements will consist of constructing a
pump building, replacing the booster pumps, motors, and appurtenances,
and installing all new electrical equipment and instrumentation.
Requests for Proposal to prepare plans, specifications and cost estimates
were sent to six engineering firms . Five responses were received and
evaluated on technical merit by a four-member selection committee. Two
of the firms received passing scores of 70 or higher. Listed below are
the scores and proposed fees of these two firms.
FIRM
Metcalf & Eddy
Lee & Ro Inc.
SCORE
88
82
FEE
$152,513
$179,912
Staff recommends that Metcalf & Eddy be retained for this project. They
were the top ranked firm based on technical merit and submitted the
lowest cost proposal. Their proposal demonstrated that the firm has
extensive experience with similar projects, a good understanding of the
project goals and objectives, and a strong project team.
25F-1
Agreement for Engineering Services
With Metcalf & Eddy
April 4, 2005
Page 2
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
FISCAL IMPACT
The Federal EPA grant provides funding for 55% of the design and
construction costs. The City will be responsible for the remaining 45%.
Funds are available in the Water Enterprise Capital Construction Fund
(account no. 66-579-6635).
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez
Executive Director I~
Finance & Mgmt. Services Agency;w
.-I
JGR/SW/RFCA04-04/AgreeforEngSrvcMetcalf&Eddy.JGR
25F-2
-' ,
J
4
x~~'\
()'-\s
()s0- (,~ L
(,t>-~ ~
22
.
WESH.lINSTER
22
WESTMINISTER AVE
...
""
>-
Vl
5:!
iil
>-
Vl
~
>
1ST
ST
El
tl
:;,
~
z
~ ~
5. =
~ iil
~ l PRO..J LOCATION
~ (WEST PUMP ST A liON ANO RESERVOIR)
z
McFADDEN AVE
PROJECT LOCATION
~
NTS
NOT TO SCALE
EXHIBIT 1
P\.E1JC IORKS ACO<<:V
City Council Title:
Agenda Date
April 4, 2005
AGREEMENT FOR ENGINEERING
SERVICES WITH METCALF AND EDDY
25F-4