Public Road Improvement 12104/00
Estimated Costs
Form Approved-A VP Law
Improvements to Existing Public Road At Grade Crossing
For Main Street, DOT 761253H
M.P. 520.20, Santa Ana Industrial Lead, Los Nietos Subdivision
Santa Ana, California
TIDS AGREEMENT, executed in duplicate this I;l.. day of tlel-:200s' by
and between UNION PACIFIC RAILROAD COMPANY, a Delaware corporation (hereinafter the
"Railroad"), and CITY OF SANTA ANA, a municipal corporation of the State of California
(hereinafter the "Political Body"), WITNESSETH:
RECITALS:
The Political Body has requested the Railroad to improve the existing Main Street crossing,
at grade, along, over and across the Railroad's track and right of way at Mile Post 520.20, Santa
Ana Industrial Lead, Los Nietos Subdivision, DOT No. 761253H, in City of Santa Ana, Orange
County, California to which the Railroad is agreeable, but solely upon terms and conditions
hereinafter set forth.
AGREEMENT:
NOW THEREFORE, in consideration of the premises and of the promises and conditions
hereinafter set forth, the parties hereto agree as follows:
1. The Railroad shall furnish all labor, material, equipment and supervision for, and
shall (a) remove the existing asphalt crossing, (b) install a 128 ft. precast concrete crossing, (c) field
weld rail, (d) relay track at crossing with 136/# rail, (e) renew the crossties, and (0 surface the track
with new ballast, all at the intersection of the Railroad's Santa Ana Industrial Lead with Main
Street at Mile Post 520.20 in Santa Ana, Orange County, California.
2. The Political Body agrees to reimburse the Railroad for fifty percent (50"/0) of
Railroad's aetual labor and material costs assodated with the work and materials described in
Section 1 above. The Railroad estimates such cost to be One Hundred Twenty Six Thousand Seven
Hundred and Twenty Three Dollars ($126,723.00), as set forth in Estimate of Material and Force
Account dated June 17,2005 marked Exhibit A, hereto attached. and hereby made a part hereof.
During the performance of such work the Railroad will provide progressive billing to Political Body
based on Railroad's actual costs. Actual costs to the Railroad shall include customary additives to
materials, services and labor provided by the Railroad. Within 120 Days after Railroad has
completed its work, the Railroad will submit a final billing to Political Body for any balance owed.
Political Body shall pay the Railroad within thirty (30) days of its receipt of all bills submitted by
the Railroad.
3. The Railroad, at its cost, shall maintain the crossing between the track tie ends. If,
in the future, the Political Body elects to have the surfacing material between the track tie ends
replaced with paving or some surfacing material other than concrete crossing, the Railroad, at the
Political Body's expense, shall install such replacement surfacing.
4. The Political Body, at its sole cost and expense, shall provide traffic control,
barricades, and all detour signing for the crossing work, provide all labor, material and equipment
to install concrete or asphalt street approaches, and if required, will install advanced warning signs,
and pavement markings in compliance and conformance with the Manual on Uniform Traffic
Control Devices.
C:~_~I:Jl1\M;l'~ta\W~ANA."""""'" 1
Public Road Improvement 12/04/00
Estimated Costs
Form Approved-A VP Law
5. If Political Body's contractor(s) is/are performing any work described in Section 4
above, then the Political Body shall require its contractor(s) to execute the Railroad's standard and
current form of Contractor's Right of Entry Agreement. Political Body acknowledges receipt of a
copy of the Contractor's Right of Entry Agreement and understanding of its terms, provisions, and
requirements, and will inform its contractor(s) of the need to execute the Agreement. Under no
circumstances will the Political Body's contractor(s) be allowed onto the Railroad's premises
without first executing the Contractor's Right of Entry Agreement.
6. Fiber optic cable systems may be buried on the Railroad's property. Protection of
the fiher optic cable systems is of extreme importance since any break could disrupt service to users
resulting in business interruption and loss of revenue and profits. Political Body or its contractor(s)
shall telephone the Railroad during normal business hours (7:00 a.m. to 9:00 p.m., Central Time,
Monday through Friday, except holidays) at 1-800-336-9193 (also a 24-hour number, 7 day number
for emergency calls) to determine if fiber optic cable is buried anywhere on the Railroad's premises
to be used by the Political Body or its contractor(s). If it is, Political Body or its contactor(s) will
telephone the telecommunications company(ies) involved, arrange for a cable locator, and make
arrangements for relocation or other protection of the fiber optic cable prior to beginning any work
on the Railroad's premises.
7. The Political Body, for itself and for its successors and assigns, hereby waives any
right of assessment against the Railroad, as an adjacent property owner, for any and all
improvements made under this agreement.
8. Covenants herein shall inure to or bind each party's successors and assigns;
provided, no right of the Political Body shall be transferred or assigned, either voluntarily or
involuntarily, except by express written agreement acceptable to the Railroad.
9. The Political Body shall, when returning this agreement to the Railroad (signed),
cause same to be accompanied by such Order, Resolution, or Ordinance of the governing body of
the Political Body, passed and approved as by law prescribed, and duly certified, evidencing the
authority of the person executing this agreement on hehalf of the Political Body with the power so
to do, and which also will certify that funds have been appropriated and are available for the
payment of any sums herein agreed to be paid by Political Body.
IN WITNESS WHEREOF, the parties hereto have duly executed this Agreement as ofthe
date.M;.'"'~~rT'- UMON
,/-,/ u\; \"q 10___ By
JaJIles G. Ross Title:
E;iecutive Director
}UbliC Works Agency
TTEST:
\ . .
. /-----:7i!
.-::;: ?~-L-<-_c::..e-~-<-.
-' . (,.
.'i~ (:...-"'\>\~ Jh...\c ,-\.....:-1
Laura Stitt Shccd'y
Assistallt City Atlorncy
:YOF;2:;Gve.
Title: {~O yYt..t'~A
Pursuant to Resolution/Order
dated
hereto attached.
C:\D_.nd~131\MJ'DoamftJlIIDfi1l\W~ANA~ .,
,. .
A.E.R.
JUN 1 7 Z005
~ \1, &1
t' )1
A
DATE: 2005-06-17
ESTIMATE OF MATERIAL AND FORCE ACCOUNT WORK
BY THE
UNION PACIFIC RAILROAD
DESCRIPTION OF WORK:
RECOLLECTIBLE ROADXING PROGRAM I SANTA ANNA INDUSTRIAL LD I MP 520.20
SOUTH MAIN ST. 50-SO SPLIT BElWEEN CITY OF SANTA ANNA CA. AND UPRR.
RENEW OR REPLACE 128 TF OF NEW CONCRETE CROSSING,UNLOAD (3) CARS OF
BALLAST,SURFACE AND LINE TRACK(S) AS NOTED IN SCOPE OF WORK.
MISC SIGNAL WORK.
PIO: 49301 NIIO: 46601 MP,SUBDIV: 520.20, SANTAANA
SERVICE UNIT: 20 CITY: SANTA ANA STATE: CA
DESCRIPTION qry UNIT LABOR MATERIAL RECOLL UPRR TOTAL
--------...-- ----- -------- -------
ENGINEERING WORK
ENGINEERING 2956 1478 1478 2956
------- -------- -------- -------- --------
TOTAL ENGINEERING 2956 1478 1478 2956
SIGNAL lIlORK
LABOR ADDITIVE 235% 1730 865 865 1730
MATL STORE EXPENSE 1 1 1
SAlES TAX 2 1 1 2
SIGNAL 887 51 468 470 938
------- -------- -------- -------- --------
TOTAL SIGNAL 2617 54 1334 1337 2671
TRACK & SURFACE WORK
BALAST 3.00 CL 705 1789 1246 1248 2494
BnLPREP 900 450 450 900
CONTRACr EQUIPTMENT lOOOO 5000 5000 10000
HOMELINE FREIGIfT 900 450 450 900
lABOR ADDITIVE 235% 37625 18812 18813 37625
MATL STORE EXPENSE 786 391 395 786
C1TM 1635 2683 2158 2160 4318
RAIL 320.00 LF 2216 3958 3087 3087 6174
RDXING 128.00 TF 9728 20068 14898 14898 29796
SALES TAX 1414 706 708 1414
SAW CUT STREET APPROACH 2500 1250 1250 2500
TRK-SURF, LIN 3402 1701 1701 3402
XTIE 90.00 EA 13885 6902 10393 10394 20787
------- -------- -------- -------- --------
TOTAL TRACK & SURFACE 69196 51900 60542 60554 121096
LABOR/MATERIAL EXPENSE 74769
RECOLLECTIBLE/UPRR EXPENSE
ESTIMATED PROJECT COST
EXISTING REUSEABLE MATERIAL CREDIT
SALVAGE NONUSEABLE MATERIAL CREDIT
RECOLLECTIBLE LESS CREDITS
lHE ABOVE FIGURES ARE ESTIMATES ONLY AND SUBJECT TO FLUCTUATION. IN lHE EVENT OF
51954 -------- --------
63360 63363 --------
126723
o
o
AN INCREASE OR DECREASE IN lHE COST OR QUANTITY OF MATERIAL OR lABOR REQUIRED,
UPRR WILL BILL FOR ACTUAL CONSTRUCTION COSTS AT lHE CURRENT EFFECTIVE RATE.
R. C. Gonzales
Senior Manager Special I'roje(!s
Ph. (909) 879-6264
Rita Jones
Administration
Ph. (909) 1179-6256
.
F. C. Cheung
Manager InJustry&
Public Projects
ph. (')09) 879-6288
September 1,2005
Crossing:Public
CA : Santa Ana
Main Street
M.P. 520.20, Santa Ana Lead
DOT# 761253H
Mr. Jason Gabriel, P.E.
Sr. Civil Engineer
City of Santa Ana
Public Works Agency
20 Civil Center Plaza, M-36
Santa Ana, CA 92701
RE: Proposed Crossing Surface Improvement - Main Street
Dear Mr. Gabriel:
Attacbed for your review and execution are two original copies of agreement between Union Pacific
Railroad and City of Santa Ana covering tbe crossing surface improvement at the above referenced
crossing.
The City must sign the agreement first before we are to execute them. If satisfactory please have both
copies executed by the City and return the same for our handling.
Sincerely,
Cheung, E.
UNION PACIFIC RAILROAD Engineering Department 19100 Slover Ave. Bloomington, CA 92316 fx. (909) 879-6289