HomeMy WebLinkAboutCA, STATE, TRANSPORTATION (CALTRANS) - 2007A-2007-295
..,
PROGRAM SUPPLEMENT NO. N118
to
ADMINISTERING AGENCY-STATE AGREEMENT
FOR FEDERAL-AID PROJECTS NO. 12-5063R
Date :March 19, 2008
Location : 12-ORA-O-SA
Project Number:HSIPL-5063(118)
E.A. Number:l2-931941
This Program Supplement hereby incorporates the Administering Agency-State Agreement for Federal Aid which was entered into
between the Administering Agency and the State on 01/12/07 and is subject to all the ternls and conditions thereof. This Program
Supplement is executed in accordance with Article I of the aforementioned Master Agreement under authority of Resolution No.
approved by the Administering Agency on 3 J SrO~ (See copy attached).
2~6~-G'~3
The Administering Agency further stipulates that as a condition to the payment by State of any fiords derived from sources noted
below obligated to this project, the Administering Agency accepts and will comply with the Special covenants or Remarks setforth
on the following pages.
PROJECT LOCATION:
Intersection of Harbor Boulevard and Kent Avenue
TYPE OF WORK: New signals
Estimated Cost
$26,400.00
CITY OF SANTA ANA
By
Date
Attest `` ,. ~.;' L 1
Title ~~~
LENGTH: 0.1 (MILES)
Federal Funds Matching Funds
LS30 $23,760.00 LOCAL OTHER
$2,640.00 $0.00 $0.00
STATE OF CALIFORNIA
r Department of Transp rtation
~~ ~ ~~ ~~
.~ ~ By ~/
_ ~1 Chief, Office of Project Implementation
`°
~~ f-' I -1 Divisio/n/~of Local Assistance
~ ~~~~` Date
n ~
I hereby certify upon my pers nal knowledge that budgeted funds are available for this encumbrance:
~ ~
Accounting Officer '1''~-- ~ Date $23,760.00
Chapter Statutes Item Year Program BC Category Fund Source AMOUNT
171 2007 2660-102-890 2007-2008 20.30.010.550 C 262042 892-F 23,760.00
Program Supplement 12-5063R-N118- ISTEA Page 1 of 3
12-0RA-O-SA' .
03/19/2008
HSIPL-5063(118)
SPECIAL COVENANTS OR REMARKS
1. ADMINISTERING AGENCY agrees that it will only proceed with work
authorized for specific phase(s) with an "Authorization to
Proceed" and will not proceed with future phase(s) of this
project prior to receiving an "Authorization to Proceed" from the
STATE for that phase(s) unless no further State or Federal funds
are needed for those future phase(s).
2. Any State and Federal funds that may have been encumbered for
this project are only available for disbursement for a period of
five (5) years and seven (7) years, respectively, from the start
of the fiscal year(s) that those funds were appropriated within
the State Budget Act. All project funds not liquidated within
these periods will revert unless an executed Cooperative Work
Agreement extending these dates is requested and is approved by
the California Department of Finance per Government Code Section
16304. The exact date of each fund reversion will be reflected
in the approved finance letter(s) issued for this project.
Notwithstanding the unliquidated sums of project specific State
and Federal funding remaining and available to fund project work,
any invoice for reimbursement that is not submitted to the
Department on or before 60 days after that applicable fixed fund
reversion date will not be paid from that fiscal year's
encumbered funds because all of these unexpended funds will be
irrevocably reverted by the Department's Division of Accounting
on that date.
Pursuant to a directive from the State Controller's Office and
the Department of Finance, the last date to submit invoices for
reimbursed work in each fiscal year is May 15th in order for
payment to be made out of those then current appropriations.
Project work performed and invoiced after May 15th will be
reimbursed only out of available funding that might be encumbered
in the subsequent fiscal year, and then only when those funds are
actually allocated and encumbered as authorized by the California
Transportation Commission and the Department's Accounting Office.
3. The ADMINISTERING AGENCY will advertise, award and administer
this project in accordance with the current published Local
Assistance Procedures Manual.
4. Award information shall be submitted by the ADMINISTERING AGENCY
Program Supplement 12-S063R-NllB- ISTEA
Page 2 of 3
12-0RA-O-8A
.'
03/19/2008
HSIPL-5063(118)
SPECIAL COVENANTS OR REMARKS
to the District Local Assistance Engineer within 60 days after
the project contract award. A copy of the award package shall
also be included with the submittal of the ADMINISTERING AGENCY's
first invoice for the construction contract to:
Department of Transportation
Division of Accounting
Local Programs Accounting Branch, MS #33
P. O. Box 942874
Sacramento, CA 94274-0001.
Failure to do so will cause a delay in the State processing
invoices for the construction phase. Please refer to Section
15.7 "Award Package" of the Local Assistance Procedures Manual.
5. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at
least once every six months commencing after the funds are
encumbered for each phase by the execution of this Project
Program Supplement Agreement, or by STATE's approval of an
applicable Finance Letter. STATE reserves the right to suspend
future authorizations/obligations, and invoice payments for any
on-going or future federal-aid project by ADMINISTERING AGENCY if
PROJECT costs have not been invoiced by ADMINISTERING AGENCY for
a six-month period.
If no costs have been invoiced for a six-month period,
ADMINISTERING AGENCY agrees to submit for each phase a written
explanation of the absence of PROJECT activity along with target
billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents
that collectively constitute a "Report of Expenditures" within
one hundred eighty (180) days of PROJECT completion. Failure of
ADMINISTERING AGENCY to submit a "Final Report of Expenditures"
within 180 days of PROJECT completion will result in STATE
imposing sanctions upon ADMINISTERING AGENCY in accordance with
the current Local Assistance Procedures Manual.
Program Supplement12-S063R-Nl18- ISTEA
Page 3 of 3
r ^s
t ~
F
PROGRAM SUPPLEMENT NO. N120
to
ADMINISTERING AGENCY-STATE AGREEMENT
FOR FEDERAL-AID PROJECTS NO. 12-5063R
LENGTH: 0.1 (MILES)
This Program Supplement hereby incorporates the Administering Agency-State Agreement for Federal Aid which was entered into
between the Administering Agency and the State on 01/12/07 and is subject to all the terms and conditions thereof. This Pro ram
Supplement is executed in accordance with Article I of the aforementioned Master Agreement under authority of Resolution No.
g
J..__CO~ - UZ;''y ,approved by the Administering Agency on
The Administering Agency further stipulates that as a conditio , ~ ~~~ ~ (See copy attached).
below obligated to this project, the Administering Agency accepts and wa 1i complyStivath the Specialcovenants or Remarks setforth
on the following pages.
PROJECT LOCATION:
Intersection of Hazard Avenue and Rosita Street
TYPE OF WORK: New signals and ADA ramps
Estimated Cost
Federal Funds
LU20 $31,000.00
$31,000.00
CITY OF SANTA ANA
By a
Date ,:
Attest ~_I -'~
Title ~, ~-I
~`~! ~ ~ C
i hereby certify upon m P
y p_rso al
Accounting Officer
Chapter Statutes
Item
171 2007 2660-102-890
Date: March 17, 2008
Location: ]2_pR,o,_0-SA
Project Number:SR2SF-5063(122)
E.A. Number:l2-931944
Matching Funds
LOCAL
OTHER
$0.00 $0.00
$0.00
STATE OF CALIFORNIA
~ Department of Transp tation
~~ ~
By ~ i r
C=_ Chief, Office of Project Implementation
~( i?r Division of Local Assistance
~ ` ///
i ~~' Date
knowledge that budgeted funds are avairlable for this encumbrance:
Date c~ ~ (~
Year Program
BC Category Fund Source
2007-2008 20.30.010.535 C 262040
892-F
Program Supplement 12-5063R-N120- ISTEA
'4-2007.295
$31,000.00
-----_
AMOUNT
31,000.00
Page 1 of 4
12-0RA-0-SA
S~2SF-5063(122)
03/25/2008
SPECIAL COVENANTS OR REMARKS
1. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
2. Award information shall be submitted by the ADMINISTERING AGENCY to the District
Local Assistance Engineer within 60 days after the project contract award. A copy of the
award package shall also be included with the submittal of the ADMINISTERING
AGENCY's first invoice for the construction contract to:
Department of Transportation
Division of Accounting
Local Programs Accounting Branch, MS #33
P. O. Box 942874
Sacramento, CA 94274-0001.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Please refer to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual.
3. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
4. Any State and Federal funds that may have been encumbered for this project are only
available for disbursement for a period of five (5) years and seven (7) years, respectively,
from the start of the fiscal year(s) that those funds were appropriated within the State
Budget Act. All project funds not liquidated within these periods will revert unless an
executed Cooperative Work Agreement extending these dates is requested and is
approved by the California Department of Finance per Government Code Section 16304.
The exact date of each fund reversion will be reflected in the approved finance letter(s)
issued for this project.
Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement that is not
submitted to the Department on or before 60 days after that applicable fixed fund
reversion date will not be paid from that fiscal year's encumbered funds because all of
these unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on that date.
Pursuant to a directive from the State Controller's Office and the Department of Finance,
the last date to submit invoices for reimbursed work in each fiscal year is May 15th in
order for payment to be made out of those then current appropriations. Project work
performed and invoiced after May 15th will be reimbursed only out of available funding
that might be encumbered in the subsequent fiscal year, and then only when those funds
Program Supplement 12-5063R-N120-ISTEA
Page 2 of 3
12-0RA-0-SA
~R2SF-5063(122)
..
03/25/2008
SPECIAL COVENANTS OR REMARKS
are actually allocated and encumbered as authorized by the California Transportation
Commission and the Department's Accounting Office.
5. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once every
six months commencing after the funds are encumbered for each phase by the execution
of this Project Program Supplement Agreement, or by STATE's approval of an applicable
Finance Letter. STATE reserves the right to suspend future authorizations/obligations,
and invoice payments for anyon-going or future federal-aid project by ADMINISTERING
AGENCY if PROJECT costs have not been invoiced by ADMINISTERING AGENCY for a
six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING AGENCY in accordance with the current Local
Assistance Procedures Manual.
Program Supplement 12-5063R-N120-ISTEA
Page 3 of 3
A-2007-295
~,, t Date :March 17, 2008
Location :12-ORA-O-SA
PROGRAM SUPPLEMENT NO. N119
to Project N,imber:SR2SF-5063(121)
ADMINISTERING AGENCY-STATE AGREEMENT E.A. Number:l2-931943
FOR FEDERAL-AID PROJECTS NO. 12-5063R
enc State Agreement for Federal Aid which was entered into
lenient hereby incorporates the Administering Ag Y-
erin A ency and the State on 01/12!07 and entioned Master Ages and conditions thereof. This rograt
This Program Supp reement under authority of Resolution No.
between the Admmist g g (See copy attached).
Supplement is executed in accordance with Article I of erica onem y /s~~
n -~ ., ,approved by the Administering Ag y
LC~~ y ~ `--'_S a merit by State of any fiinds derived from sources noted
A enc further stipulates that as a condition to the p y
The Administering g y acce is and will comply with the Special covenants or Remarks setforth
below obligated to this project, the Administering Agency p
on the following pages.
PROJECT LOCATION:
Intersection of McFadden Avenue and Newhope Street
...tnmv . (l. l (MILES
TYPE of WORK: Left-turn signal with protected/permissive phasing
Estimated Cost
$15,000.00
CITY OF SANTA ANA
By
!~
f
Date ~ ~ -~
r
Attest ~~~~
Title ~ (~..
Matching Funds
Federal Funds OTHER
$15,000.00 LOCAL $0.00
LU20 $0.00 $0.00
STATE OF CALIFORNIA rtation
~ Department of Transp
~~ 1 r.
/~ ~~ G ~ ~ By
i~ ~ ect Implementation
,Chief, Office of Proj
~.~ I yf/~~~ ~ Division of Local Assistance
// GGG
i ,
~ ` 7' ~ ~~ i ~ .~ Date
_~ q
,~~'~ vr~r'_ ~,~ ~ s~ ~~~~' ,
that budgeted funds are available foz; his encumbrance:
I hereby certify upon my
Accounting Officer ~v
Item Year
Chapter Statutes
171 2007 2660-102-890 2007-2008
Date % i .d
gC Category
_y~ gram
20.30.010.535 C 262040
Fund Source
_~
892-F
$15,000.00
~~
AMOUNT
15,000.00
page 1 of 5
Program Supplement 12-5063R-N119- ISTEA
12-0RA-0-SA
'.
}3R2SF:.5063(121)
03/25/2008
SPECIAL COVENANTS OR REMARKS
1. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
2. Award information shall be submitted by the ADMINISTERING AGENCY to the District
Local Assistance Engineer within 60 days after the project contract award. A copy of the
award package shall also be included with the submittal of the ADMINISTERING
AGENCY's first invoice for the construction contract to:
Department of Transportation
Division of Accounting
Local Programs Accounting Branch, MS #33
P. O. Box 942874
Sacramento, CA 94274-0001.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Please refer to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual.
3. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
4. Any State and Federal funds that may have been encumbered for this project are only
available for disbursement for a period of five (5) years and seven (7) years, respectively,
from the start of the fiscal year(s) that those funds were appropriated within the State
Budget Act. All project funds not liquidated within these periods will revert unless an
executed Cooperative Work Agreement extending these dates is requested and is
approved by the California Department of Finance per Government Code Section 16304.
The exact date of each fund reversion will be reflected in the approved finance letter(s)
issued for this project.
Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement that is not
submitted to the Department on or before 60 days after that applicable fixed fund
reversion date will not be paid from that fiscal year's encumbered funds because all of
these unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on that date.
Pursuant to a directive from the State Controller's Office and the Department of Finance,
the last date to submit invoices for reimbursed work in each fiscal year is May 15th in
order for payment to be made out of those then current appropriations. Project work
performed and invoiced after May 15th will be reimbursed only out of available funding
that might be encumbered in the subsequent fiscal year, and then only when those funds
Program Supplement 12-5063R-N119- ISTEA
Page 2 of 3
12-0RA-0-SA
I
c.SR2SP~5063(121 )
03/25/2008
SPECIAL COVENANTS OR REMARKS
are actually allocated and encumbered as authorized by the California Transportation
Commission and the Department's Accounting Office.
5. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once every
six months commencing after the funds are encumbered for each phase by the execution
of this Project Program Supplement Agreement, or by STATE's approval of an applicable
Finance Letter. STATE reserves the right to suspend future authorizations/obligations,
and invoice payments for anyon-going or future federal-aid project by ADMINISTERING
AGENCY if PROJECT costs have not been invoiced by ADMINISTERING AGENCY for a
six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING AGENCY in accordance with the current Local
Assistance Procedures Manual.
Program Supplement 12-5063R-N119- ISTEA
Page 3 of 3
A-2007-295
PROGRAM SUPPLEMENT NO. N121
to
ADMINISTERING AGENCY-STATE AGREEMENT
FOR FEDERAL-AID PROJECTS N0. 12-5063R
Date: March 17, 2008
Location : 12-ORA-O-SA
Project Number:SR2SF-5063(123)
E.A. Number:l2-931945
This Program Supplement hereby incorporates the Administering Agency-State Agreement for Federal Aid which was entered into
between the Administering Agency and the State on 01/12/07 and is subject to atl the teens and conditions thereof. This Program
Supplement is executed in accordance with Article I of the aforementioned Master Agreement under authority of Resolution No.
ZpL"1 ._ ~ Z ;~, approved by the Administering Agency on ~ S I ~ ~~ +~ (See copy attached).
The Administering Agency further stipulates that as a condition to the payment by State of any funds derived from sources noted
below obligated to this project, the Administering Agency accepts and will comply with the Special covenants or Remarks setforth
on the following pages.
PROJECT LOCATION:
Hazard Avenue east of Gates Street at R. F. Hazard Elementary School
TYPE OF WORK: New signals and sidewalk
LENGTH: 0.1 (MILES)
Estimated Cost Federal Funds Matching Funds
$30,400.00 LU20 $30,400.00 LOCAL
$0.00
$0.00 OTHER
$0.00
CITY OF SANTA ANA ) STATE OF CALIFORNIA
/ ~/ Department of Transportation
B °f 1 '~ ~ ' ~ i0 ~~7 B ) ,
Y ~ ~ Y ~~(;~~~! i
Date// ~ ~~ G 'Chief, Office of Project Implementation
Division of Local Assistance
_~
~_- ~ 7
Attest: t i~,~ '~,~ ~ ~"
,, / ~, Date
Title , >i, f (~~ ,~i~ ~~lC ;SZ ~ `1 i ,, 5
2 hereby certify upon my pera al knowledge that budgeted funds are available for this encumbrance:
Accounting Office Date J ~ $30,400.00
Chapter Statutes Item Year Program BC Category Fund Source AMOUNT
171 2007 2660-102-890 2007-2008 20.30.010.535 C 262040 892-F 30,400.00
Program Supplement 12-5063R-N121- ISTEA Page 1 of 4
12-0RA-0-SA
SR2SF'-5063(123)
03/25/2008
"
SPECIAL COVENANTS OR REMARKS
1. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
2. Award information shall be submitted by the ADMINISTERING AGENCY to the District
Local Assistance Engineer within 60 days after the project contract award. A copy of the
award package shall also be included with the submittal of the ADMINISTERING
AGENCY's first invoice for the construction contract to:
Department of Transportation
Division of Accounting
Local Programs Accounting Branch, MS #33
P. O. Box 942874
Sacramento, CA 94274-0001.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Please refer to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual.
3. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
4. Any State and Federal funds that may have been encumbered for this project are only
available for disbursement for a period of five (5) years and seven (7) years, respectively,
from the start of the fiscal year(s) that those funds were appropriated within the State
Budget Act. All project funds not liquidated within these periods will revert unless an
executed Cooperative Work Agreement extending these dates is requested and is
approved by the California Department of Finance per Government Code Section 16304.
The exact date of each fund reversion will be reflected in the approved finance letter(s)
issued for this project.
Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement that is not
submitted to the Department on or before 60 days after that applicable fixed fund
reversion date will not be paid from that fiscal year's encumbered funds because all of
these unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on that date.
Pursuant to a directive from the State Controller's Office and the Department of Finance,
the last date to submit invoices for reimbursed work in each fiscal year is May 15th in
order for payment to be made out of those then current appropriations. Project work
performed and invoiced after May 15th will be reimbursed only out of available funding
that might be encumbered in the subsequent fiscal year, and then only when those funds
Program Supplement 12-5063R-N121-ISTEA
Page 2 of 3
12-0RA-0-SA
SR2SF-5063(123)
03/25/2008
SPECIAL COVENANTS OR REMARKS
are actually allocated and encumbered as authorized by the California Transportation
Commission and the Department's Accounting Office.
5. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once every
six months commencing after the funds are encumbered for each phase by the execution
of this Project Program Supplement Agreement, or by STATE's approval of an applicable
Finance Letter. STATE reserves the right to suspend future authorizations/obligations,
and invoice payments for anyon-going or future federal-aid project by ADMINISTERING
AGENCY if PROJECT costs have not been invoiced by ADMINISTERING AGENCY for a
six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING AGENCY in accordance with the current Local
Assistance Procedures Manual.
Program Supplement 12-5063R-N121-ISTEA
Page 3 of 3
"'
.I..
A-2Q07 -295
.~ "..~,,,.
RESOLUTION NO. 2007-023
2/13/07 res
A RESOLUTION OF THE CITY COUNCil OF THE CITY OF
SANTA ANA AUTHORIZING THE EXECUTIVE DIRECTOR
OF THE PUBLIC WORKS AGENCY TO EXECUTE THE
REVISED ADMINISTERING AGENCY-FEDERAL MASTER
AGREEMENT WITH THE STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION TO REIMBURSE
THE CITY OF SANTA ANA FOR FEDERALLY FUNDED
PROJECTS
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA, AS
FOLLOWS:
Section 1: The City Council of the City of Santa Ana hereby finds, determines and
declares as follows:
A. The City of Santa Ana {"City"} has an existing Administering Agency-
Federal Master Agreement No. 12-5603 ("Agreement") with the 'Califomia
Department of Transportation ("CaITrans"). This Agreement provides for the
City's reimbursement of federally funded projects.
B. CalTrans presented the City with a revised Administering Agency-Federal
Master Agreement No. 12-5603 on January 12,2007. This Agreement'has been
revised to incorporate various changes in regulations and policies.
Section 2: The City Council hereby authorizes the Executive Director of the Public
Works Agency to execute all program supplement agreements required by the revised
Administering Agency-Federal Master Agreement No. 12-5603R.
Section 3: This Resolution shall take effect immediately upon its adoption by the
City Council, and the Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
ADOPTED this 5th day of March. 2007.
Resolution No. 2007-023
Page 1 of2
....
I"
c
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
By: r!r{'- tt:. ~~
Lisa E. Storck
Assistant City Attorney
AYES Councilmembers Alvarez, Benavides. Bustamante. Martinez.
Pulido. Sarmiento, Tinaiero (7)
NOES: Council members None (0)
ABSTAIN: Councilmembers None (0)
NOT PRESENT: Councilmembers None (0)
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEALY, Clerk of the Council, do hereby attest to and certify the
attached Resolution No. 2007-023 to be the original resolution adopted by the City
Council of the City of Santa Ana on March 5, 2007.
Date:
31;3/1J 7
I I
.-
./..
.'/'
~
.- ~
G;
(
~
. atricia E. Heply
Clerk of the Co~ncil
City of Santa Ana,
f-'-"~.F~:-:~=3C;;lG DOCU.r,~EjlT IS A FULL. TRUE & CORRECT COpy OF l
LVfi-!E 2:'.:G:;li\L ON FiLE if! THIS OFFiCE.
I ~~'i~~~~::;':O:';'\'- Cl :H.E 'f1.~...~ J "'2DO---!
- . ~- -. - .. - _.'.5;.... Qk--- .
BY -W.. _ ~__'C~ .. -.-.- .-----------..----1
. -. .", 1- --I t'" "",'rl .....,.., - .., ,..... f ".' 1\
r' CLEh,i\ 0,- in::. vl,;ui;>...;:L, ell ( Lf S,:.!.,;;.!\. t:~;H\ ...
Resolution No. 2007-023
Page 2 of 2
~-'
(-,-
~
A-2007-295
3/1/07Ies
RESOLUTION NO. 2007-030
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA SUPPORTING FEDERAL FUNDING OF
PROJECTS AND AUTHORIZING THE EXECUTIVE
DIRECTOR OF THE PUBLIC WORKS AGENCY TO
SUBMIT THE PROJECTS FOR FUNDING UNDER THE
HIGHWAY SAFETY IMPROVEMENT PROGRAM
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines
and declares as follows:
A. The Highway Safety Improvement Program (HSIP), codified as Section 148 of
Title 23, United States Code {23 U.S.C. section 148)is a core program as a result of the
passage of the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A
Legacy for Users.
B. The State of California Department of Transportation (CaITrans) issued a call
for projects for the HSIP for Federal Fiscal Year 2006/2007 and Federal Fiscal Year
2007/2008, to use federal transportation funds for construction of projects that. will
improvo traffic and pedestrian safety, such as traffic signals and signage .u.pgrades:
C. CalTrans makes grants available to local governmental agencies under "the
Program based on the results of a statewide competition.
D. Projects eligible for funding include any local agency public road, any local
public agency surface transportation facility, any local agency publicly-owned bicycle or
pedestrian pathway or trail, or any traffic calming measure on a local agency public
road.
E. The City Council of the City of Santa Ana possesses the legal authority to
nominate, finance, acquire, and construct projects that are eligible for funding under the
HSIP Program.
F. The City Council of the City of Santa Ana supports efforts to improve traffic
and pedestrian safety in the City of Santa Ana.
Section 2. The City Council of the City of Santa Ana authorizes the Executive
Director of the Public Works Agency or his designee to execute, in the name of the City
of Santa Ana, all necessary documentation and applications required to be submitted to
CalTrans for the projects identified in Exhibit 1 for funding under the Highway Safety
Improvement Program.
Resolution No. 2007-030
Page 1 of 3
<_,r
~
Section 3. This Resolution shall take effect immediately upon its adoption by
the City Council, and the Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
ADOPTED this 19th day of March. 2007.
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
~.
By: . '<.. (-.~~.
Isa E. Storck
Assistant City Attorney
. AYES:
Councilmembers Alvarez. Benavides. Bustamante. Martinez.
Pulido. Sarmiento. Tinaiero (7)
NOES:
Councilmembers . None (0)
ABSTAIN: Councilmembers None (0)
NOT PRESENT: Councilmembers None (0)
CERTIFICATION OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEALY, Clerk of Council, do hereby attest to and certify the attached
Resolution No. 2007-030 to be the original resolution adopted by the City Council of the
City of Santa Ana on March 19.2007.
Date:
3P7~?
J' I
/.--7
J~
Patricia E. Healy
Clerk of Council
City of Santa Ana
TIj.VfDREGOiNG DOCUMENT IS A FULL. TRUE & CORRECT COpy 'OF',
IY1HE ORiGiNAL ON FILE IN THIS OFFiCE I
.. I
o TilE O;::IG1N:\L 0i~ FILE IN .
ATTEST, 2~-;C;,g--~~ ,
BY ~---I
" L .._--/
<!;
Resolution No. 2007-030
Page 2 of 3
e
Highway Safety Improvement Program
PrOject. Recommended For Grant Application
Py 2007-2008
Location rmpro~t Coat
Harbor Blvd. and !Cent Install new traffic $363,000
Ave. signal
Civic Center Drive and Install new traffic $363,000
Pacific Avenue signal
Plower Street and Santa Install left turn arrows $300,000
Ana Blvd.
Flower Street and Install left turn arrows $300.000
McFadden Avenue
Citywide Overhead regulatory $220.000
eigns
Citywide Street name signs on $297.000
arterials
Regulatory/Warning signs
Citywide on arterials and $360.000
. overhead
Flower - Guardrail and Sign.ige $400.000
Sunflower to MacArthur
Flower - Guardrail and Signage
MacArthur to Al ton $300.000
Flower - Guardrail and Signage
Al ton to Dyer $300,000
Flower - Guardrail and Signage
Dyer to Warner $400,000
-- -
Total $3,603,000
BXHIBIT 1
....'1,/
Resolution No. 2007-030
Page 3 of 3
A-2007 -295
LST 12/6f06
RESOLUTION NO. 2006-087
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA SUPPORTING STATE FUNDING OF EIGHT
PROJECTS AND AUTHORIZING THE EXECUTIVE
DIRECTOR OF THE PUBLIC WORKS AGENCY TO
SUBMIT THE PROJECTS FOR FUNDING UNDER THE
STATE'S SAFE ROUTES TO SCHOOL PROGRAM
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines
and declares as follows:
A. In 1999 the State of California enacted into Law California Streets and
Highways Code ~2333.5, which calls for Caltrans to establish and administer
a "Safe Routes to School" construction program ("Program") and to use
federal transportation funds for the construction and improvement of school
pedestrian safety such as traffic signals, school signage, in-pavement lighted
crosswalks, and traffic calming projects.
B. The Program mandates that Caltrans shall make grants available to local
governmental agencies under the Program based on the results of a
statewide competition.
C. Projects eligible for funding include construction projects that improve the
safety of pedestrian and/or bicycle routes to and from schools.
D. The City Council of the City of Santa Ana possesses the legal authority to
nominate, finance, acquire, and construct projects that are eligible for funding
under the Program.
E. The City Council of the City of Santa Ana supports efforts to improve
pedestrian safety in the City of Santa Ana.
Section 2. The City Council of the City of Santa Ana supports State funding of
projects in the City of Santa Ana under California's Safe Routes to School Program, and
authorizes the Executive Director of the Public Works Agency, or his/her designee, to
execute in the name of the City of Santa Ana all necessary applications required to be
submitted to Caltrans for the eight projects identified in Exhibit 1 for funding under
California's Safe Routes to School Program.
Section 3. This Resolution shall take effect immediately upon its adoption by
the City Council, and the Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
Resolution No. 2006-087
Page 1 of 3
ADOPTED this 18th day of December, 2008.
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
/,
I ':
I. :v
.'
By: "
AYES Councilmembers Alvarez. Benavides. Bustamante. Martinez,
Pulido. Tinaiero, (6)
NOES: Councilmembers None (0)
ABSTAIN: Councilmembers None (O)
NOT PRESENT: Councilmembers None (0)
CERTIFICATION OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEAL Y, Clerk of Council, do hereby attest to and certify the attached
Resolution No. 2006-087 to be the original resolution adopted by the City Council of the
City of Santa Ana on December 18. 2006. //"""
- -? - /
-~~;i..~)'/-
Patricia E. Healy
Clerk of Council
City of Santa Ana
Date:
/-4/& 7
/
~
~~------ _.p--
j ~ i:,j~ ~:~i._::;,:irl~-DoCUUr:NT IS A FUllTR'UE;COfIRECT COpy OF ~
~,E v'"G",;"l uN FILE jf'! THIS OFFiCE.
[j n:t c;';;~;r'U~L eN tl~E iN
~~::_--~ -..-. . /5,...200R'
13 r/ . ..- ~ . ~ 1
elEfu: OF THE e.J::r",,' GI'I"( 0': ~""f-'\ ;^"A
' 1 vl'H'i t' tJ~
..--~--
Resolution No. 2005-087
Page 2 of 3
SAFE ROUTES TO SCHOOL PROGRAM
PROJECTS RECOMMENDED FOR GRANT APPLICATION
FY 2006-07
Location Improvement Related School Cost
Willits/Sullivan New Traffic Signal Uncaln Elementary $412,500
Upgrade School SiQnaQe
McFadden at Newhape Left Turn Signal (E/W) Fitz Intermediate $231,550
Upgrade School Signage
Hazard efo Caddy Cir New Traffic Signal Rosita Elementary $412,500
Upgrade School Signage
Grand at Chestnut Left Turn Signal (EfW) Villa Intermediate $231,550
UpQrade School Siems
Hazard e/o Gates New Traffic Signal Hazard Elementary $412,500
Upgrade School Signage
17'h I Mabury New Traffic Signal Muir Elementary $412,500
Upgrade School Signage
Raitt & Glenwood New Traffic Signal with Carr Intermediate $453,750
Ped Countdown Signals (EfVI/) SA Valley High
Upgrade School Signs
Widen Sidewalk
Raitt / Monta Vista New Traffic Signal Monte Vista Elementary $412,500
Upgrade School Signage
Total $2,979,350
EXHIBIT 1
Resolution No 2006-087