F~ECOMMENDED ACTION
Jl. Award a contract to R.J. Bullard Construction, Inc., the lowest
responsible bidder, in accordance with unit bid prices in the
estimated amount of $464,300 for the Santiago Creek Trail Enhancement
project.
2. Approve a Funding Analysis with a total estimated construction cost
of $581,600.
DISCUSSION
This project will address safety and security access concerns under the
Main Street Bridge and the Santa Ana Freeway (Exhibit 1), by providing
for the installation of a 10-foot high safety fence under Main Street,
re-grading, security lighting, and pavement rehabilitation under both
bridges. Re-grading and lighting under the Santa Ana Freeway will allow
for security vehicle access and the elimination of any level contours
for overnight camping. The project will also provide the necessary
regulation and interpretive signage that will compliment the natural
environment and trails through Santiago Creek. Once completed, these
improvements will enhance security and trail access, lighting, surface
drainage, safety and visual appearance of the Santiago Creek.
The Notice Inviting Bids was advertised on November 19 and 21, 2008, and
bids were opened on December 10, 2008. A summary of the bid invitations
mailed, the bids received, and the bid results follows.
Santa Ana Contractors receiving notices: 18
Contractors requesting bidding documents: 24
Bids received: 9
Bids received from Santa Ana Contractors: 0
23F-1
Contract Award for Santiago
Creek Trail Enhancement
January 5, 2009
Page 2
NAME OF BIDDER
1. R.J. Bullard Construction, Inc.
2. Elite Bobcat Service, Inc.
3. Pacific Coast Infrastructure, Inc.
4. Imperial Paving Co. Inc.
5. Hillcrest Contracting Inc.
6. Excel Paving
7. Terra Pave
8. Roadway Engineering & Contracting, Inc.
9. 4Con Engineering, Inc.
CITY BID AMOUNT
Bonsall $464,300
Corona $524,130
Yorba Linda $537,475
Santa Fe Springs $603,950
Corona $615,065
Long Beach $691,895
Whittier $699, 065
Corona $745, 570
Riverside $781,550
A total of nine bids were received and all were responsive. The lowest
bid was submitted by RJ Bullard Construction, Inc. for $464,300, which
is below the Engineer's estimate of $500,260.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, Categorical
Exemption ER No. 2005-176 has been approved and filed for the project.
FISCAL IMPACT
The funding analysis shows a total estimated construction cost of
$581,600 for the project (Exhibit 2). Funds are available in the
Transportation Enhancement Activity Fund (account no.59-551-6631}, the
Recreation Trails Grant Fund (account no. 172-251-6631), the General
Capital Outlay Fund (account no. 051-250-6631) and the Park Acquisition
and Development Fund (account no. 312-232-6631).
APPROVED AS TO FUNDS AND ACCOUNTS:
Public Works Agency
` //, / i
Gerardo Mouet ~
Executive Directo~
Parks, Recreation, and
Community Services Agency
~_
Francisco Gutierrez
Executive Director
Finance & Mgmt. Services Agency
23F-2
NORTH Pq KB Vp'
SANTA ANA
CITY COUNCIL
P W A AGENDA
DATE:
o+•«.~~ JANUARY 5, 2009
SANTIAGO
MAINPLACE
_ CONTRACT AWARD FOR
SANTIAGO CREEK BIKE TRAIL ENHANCEMENT
(PROJECT NO. 08-6018C)
FUNDING ANALYSIS
PROJECT 08-6018-C
SANTIAGO CREEK BIKE TRAIL ENHANCEMENT
Construction Contract $464,300
Contract Administration 18,800
Inspection and Testing 31,600
Survey Staking 20,470
Contingencies 46,430
TOTAL ESTIMATED CONSTRUCTION COSTS $581,600
Exhibit 2
23F-4