Priority Projects Updates Agenda Item No. 5 1Slide March 17, 2026Public Works Agency
Priority Projects Updates November 2027: Warner Street Widening•December 2026: Cypress Center (Fire Station)•December 2026: Bristol Street Widening•September 2026: Memorial Aquatic Center•September
2026: Business Area Street Improvements•July 2026: Portola Splash Pad•July 2026: Main Library•June 2026: McFadden & Standard Bikeway•June 2026: Police Training Facility•April 2026:
Santa Anita Park•April 2026: Salvador Quintana Park (Bristol Tolliver)•March 2026: Centennial Park•May 2025: El Salvador Park Improvements•Project Completion At a Glance 2Slide March
17, 2026Public Works Agency
Priority Projects Updates Warner Street Widening13.Cypress Center (Fire Station)12.Bristol Street Widening11.Memorial Aquatic Center10.ImprovementsBusiness Area Street 9.Portola Splash
Pad8.Main Library7.6.Police Training Facility5.Santa Anita Park4.Tolliver)3.Centennial Park2.El Salvador Park Improvements1.Project Locations 3Slide March 17, 2026Public Works Agency
Priority Projects Updates Completed: May 2025••Baseball field upgrades–New Restroom facilities–Scope: ••Ward 5El Salvador Park Improvements 4Slide March 17, 2026Public Works Agency
Priority Projects Updates Finishing restroom building–Finishing up landscaping–SCE Energization–Currently Ongoing:•Completion: March 2026•Total Investment: $6.2 Million•Site lighting,
security cameras, fencing–Restroom facilities, and a new parking lot–Lakeside event area, picnic areas, open green space, and a dog park–Scope: •First Approved: December 2021•Ward 1Centennial
Park Improvements 5Slide March 17, 2026Public Works Agency
Priority Projects Updates 6Slide March 17, 2026Public Works Agency
Priority Projects Updates Basketball court finish–Planting trees–Installing pavers and mulch –Currently Ongoing:•Completion: April 2026•Total Investment: $4.6 Million •Basketball court
–Pedestrian pathways, lighting, and picnic areas–New play equipment, adult fitness equipment with shade structures–Stormwater bioretention basin and stormwater harvest and reuse system–Scope:
•First Approved: January 2023•Ward 2-Salvador Quintana Park Tolliver Street Urban Greening Project-Bristol 7Slide March 17, 2026Public Works Agency
Priority Projects Updates 8Slide March 17, 2026Public Works Agency
Priority Projects Updates Punch list items–Pool renovation–Currently Ongoing:•Completion: April 2026•Total Investment: $18 Million•Parking lot–Construction of two new community buildings–New
basketball court and playground–Concrete bleacher seating and upper terraces for events–New synthetic turf soccer field with sports lighting–Scope: •First Approved: December 2022•Ward
1-Community Center Santa Anita Park Soccer Field and 9Slide March 17, 2026Public Works Agency
Priority Projects Updates 10Slide March 17, 2026Public Works Agency
Priority Projects Updates Furniture and equipment –General Site Cleanup–Installing additional power and water to new simulation house building–: Currently Ongoing•Completion: June 2026•Total
Investment: $1.0 Million•New Simulation House Building–New Classroom Buildings–Existing Building Renovation: Restrooms, Office Space, Storage.–Scope: •First Approved: May 2021•Ward
1Police Training Facility 11Slide March 17, 2026Public Works Agency
Priority Projects Updates Police Training Facility 12Slide March 17, 2026Public Works Agency
Priority Projects Updates and landscaping in other segmentsFinalizing street lights, traffic signals –McFadden between Bristol and Grand–Currently Ongoing:•Completion: June 2026•Total
Investment: $23.5 Million•Street lights and bus shelters–Traffic signal modifications, signage, and striping–Landscaping and irrigation –Roadway improvements, concrete bike lanes, curb
ramps, –Scope: •First Approved: November 2016•Wards 1, 2 & 6–Bikeway Improvements Standard Avenue and McFadden Avenue 13Slide March 17, 2026Public Works Agency
Priority Projects Updates elevator installation, metal framing, wood crown molding restoration.–and framing, drywallingbasement –exterior marble restoration, –Currently Ongoing: •Construction
Completion: July 2026•Total Investment: $23.9 Million •–Large community room equipped for public meetings–learning areassuch as Science, Technology, Engineering, and Mathematics (STEM)
New book drop locations, bookmobile parking, shared public spaces –renovation of exterior public spacesSurface parking, utility improvements, walkways, pedestrian lighting, –Scope:
••Ward 5Main Library Renovation 14Slide March 17, 2026Public Works Agency
Priority Projects Updates Main Library Renovation 15Slide March 17, 2026Public Works Agency
Priority Projects Updates Site preparation for splash pad–Building addition–Restroom renovation –: Currently Ongoing•Completion: July 2026•Total Investment: $2.5 Million•Building addition
for splash pad equipment room.–Restroom renovation.–New splash pad with water features and shade sails.–Scope:•First Approved: October 2024•Ward 6Portola Park Splash Pad 16Slide March
17, 2026Public Works Agency
Priority Projects Updates Council considerationPreparing contract for –Bids received–: Currently Ongoing•2026Completion: September •MillionTotal Investment: $1.5 •Signage & striping–Sidewalk
improvements–Pavement rehabilitation–SCOPE: •2025First Approved: June •Ward 4Business Area Street Improvements 17Slide March 17, 2026Public Works Agency
Priority Projects Updates Pool Tile work and plumbing. –Power transformer and switchgear –South building for roof installation–Currently Ongoing: •Completion: September 2026•Total Investment:
$29.3 Million •and upgraded walkwayExterior lighting, safety cameras, landscaping, irrigation, site furnishings, –pool equipment roomNew locker rooms, lifeguard and staff offices, a
community room, and a –competition), and a pool deck with seating areasNew aquatic building, two swimming pools (recreational and –Scope: •First Approved: August 2023•Ward 6Memorial
Park Aquatics Center 18Slide March 17, 2026Public Works Agency
Priority Projects Updates 19Slide March 17, 2026Public Works Agency
Priority Projects Updates Pole removal –Installation of electrical and –Currently Ongoing: •Completion: December 2026•Total Investment: $40.2 Million•Undergrounding overhead electrical
and communications utilities–New water and storm drains improvements–Wider sidewalks, parkways, and a raised landscape median–Widening from two to three lanes with protected bike lanes–Scope:
•First Approved: May 1991•Wards 4, 5 & 6 20Slide March 17, 2026Public Works Agency
Priority Projects Updates 21Slide March 17, 2026Public Works Agency
Priority Projects Updates Interior plumbing and framing–: Currently Ongoing•Completion: December 2026•Total Investment: $3.9 Million•New site landscaping, walkways–Restore historic architectural
building features–Interior: new lobby, open community area, classrooms, & restrooms–#4Rehabilitation and adaptive reuse of the historic Santa Ana Fire Station –SCOPE: •First Approved:
March 2023•Ward 2Cypress Center Restoration 22Slide March 17, 2026Public Works Agency
Priority Projects Updates Phase 2 Bids received–Pole removal–Telecom undergrounding –Irrigation & Landscaping–Roadway paving & opening lanes–Currently Ongoing: •Completion: November
2027•Total Investment: $38.9 Million•Undergrounding overhead electrical and communications utilities–New water and storm drains improvements–Wider sidewalks, parkways, and a raised
landscape median–Widening from two to three lanes with protected bike lanes–Scope: ••Ward 6Warner Widening 23Slide March 17, 2026Public Works Agency
Priority Projects Updates Thank you 24Slide March 17, 2026Public Works Agency