HomeMy WebLinkAboutItem 19 - Award a Construction Contract for the Industrial Street Repair Project Public Works Agency
www.santa-ana.org/pw
Item # 19
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
April 21, 2026
TOPIC: Award a Construction Contract to All American Asphalt for the Construction of
the Industrial Street Repair Project for Susan Street, Garry Avenue, Carriage Drive, Yale
Street, Moore Avenue, and Shannon Street
AGENDA TITLE
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project for Susan Street, Garry Avenue, Carriage Drive, Yale
Street, Moore Avenue, and Shannon Street (Projects No. 24-6701, 25-6701, 26-6701)
(Non-General Fund)
RECOMMENDED ACTION
1. Approve the Project Cost Analysis for a total estimated construction delivery cost
of $5,799,849, which includes $4,639,879 for the construction contract, $695,982
for contract administration, inspection, and testing, and $463,988 for
unanticipated or unforeseen work.
2. Award a construction contract to All American Asphalt, the lowest responsible
bidder, in accordance with the base bid in the amount of $4,639,879, subject to
change orders, for construction of the Industrial Street Repair Program Project
(No. 24-6701, 25-6701, 26-6701), for a term beginning April 21, 2026 and
authorize the City Manager to execute the contract.
3. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER-2026-1 will be filed for Project No. 24-6701, 26-
6701. Categorical Exemption Environmental Review No. ER-2026-2 will be filed
for Project No. 26-6701.
GOVERNMENT CODE §84308 APPLIES: No
DISCUSSION
The Public Works Agency (PWA) is responsible for managing the City’s roads and
transportation network which is comprised of arterial, residential, alley, and industrial
streets. These segments of industrial streets include Susan Street from Alton Avenue to
Segerstrom Avenue; Garry Avenue from Harbor Boulevard to Yale Street; Carriage
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project
April 21, 2026
Page 2
5
6
9
6
Drive from Harbor Boulevard to Yale Street; Yale Street from Garry Avenue to
Segerstrom Avenue; Moore Avenue from cul-de-sac to Shannon Street; and Shannon
Street from Moore Avenue to Garry Avenue (Exhibit 1). The segments were identified
as requiring reconstruction and rehabilitation and were approved in the Capital
Improvement Project (CIP) for Fiscal Year 24/25 and 25/26. The scope of work includes
excavation, grading, removal and replacement of asphalt concrete pavement, curb and
gutter, drive approaches, sidewalk, curb ramps, cross gutter, traffic signal modifications,
installation of biofiltration systems, signing, and striping. Once completed, these
improvements will improve the overall pavement condition, ride quality, and enhance
the visual appearance of the street. Pedestrian facility improvements will also comply
with the Americans with Disabilities Act (ADA) standards.
Project Advertisement and Contractor Procurement
To provide an opportunity for local vendors to submit bids, the City notified a total of 82
regional vendors via PlanetBids, many of which are Santa Ana based. Furthermore,
staff specifically reached out to Santa Ana vendors to encourage their participation in
bids. A total of five bids were received. No bids were received from Santa Ana
contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on February 13, 2026. The project was also advertised in PlanetBids from
February 12, 2026 to March 5, 2026. Bids were received electronically via PlanetBids
on March 5, 2026. No bid protest was submitted by any of the bidders during the bid
protest period.
A copy of construction plans, contracts, specifications, and all related reference
materials (such as The Greenbook) are available for public review at the City’s Public
Works Agency, Central Files office located in City Hall.
Bid Results Summary
RANK BIDDER’S NAME LOCATION BASE BID
1 All American Asphalt Corona, CA $4,639,879
2 R.J. Noble Company Orange, CA $4,682,605
3 Onyx Paving Company, Inc.Yorba Linda, CA $4,906,000
4 Hardy & Harper, Inc.Lake Forest, CA $5,110,000
5 Excel Paving Co Long Beach, CA $5,448,986
Five responsive bids were received. All American Asphalt submitted the lowest
responsive base bid in the amount of $4,639,879 (Exhibit 2). Based on the bid analysis
and a contractor’s reference check, staff recommends awarding the construction
contract to All American Asphalt (Exhibit 3).
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project
April 21, 2026
Page 3
5
6
9
6
All American Asphalt has previously performed work as a prime contractor in the City of
Santa Ana within the past five years, including Main Street Rehabilitation, Grand
Avenue Rehabilitation, and Local Street Preventative Maintenance. The contractor
satisfactorily completed these projects and staff recommends awarding the construction
contract to All American Asphalt for the construction of the Project.
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes a budget allocation for construction administration,
inspection, and testing. Construction administration and inspection may be performed
by either staff or consultants and includes construction management, inspection of the
Contractor’s work to ensure contract compliance, workmanship and quality, materials
testing, and implementation of the labor requirements.
Any of the allocated construction administration funds not spent are considered project
savings and are returned to the respective fund balance upon close out of the project.
As indicated in the Cost Analysis and as summarized in the table below, the estimated
total construction delivery cost of the project is $5,799,849.
Project Item Total
Construction Contract Bid Amount $4,639,879
Construction Administration[RR1] $371,190
Inspection[RR2] $231,994
Testing $92,798
Unanticipated and Unforeseen Work $463,988
TOTAL ESTIMATED CONSTRUCTION DELIVERY
COST $5,799,849
Project Schedule and Contract Time
The project is estimated to be completed in October 2026 barring unforeseeable
conditions such as rain, natural disasters, or other delays beyond the control of the City
and of the Contractor. The contract time for this project is 75 working days, as specified
in the bid documents. Working days are counted in accordance with the City’s Standard
Specifications, which exclude weekends, City-observed holidays, and inclement
weather days that prevent work.
The contractor was required to submit a construction schedule as part of their bid to
expedite delivery of the project. The projected completion dates based on the submitted
schedule is October 2026, which is within the allotted 75 working days. If the contractor
fails to deliver on time, they will be assessed a penalty of $7,000 per calendar day as
specified in the bid documents.
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project
April 21, 2026
Page 4
5
6
9
6
Project Milestones
Milestone Estimated
Completion
Notes
Administrative Startup April 2026 Contract execution, bonds,
insurance
Material Procurement May 2026 Procurement may take place
concurrently with construction
Contractor Mobilization May 2026 Start of construction activities
Project Completion October 2026 Based on 75 working days
Project Phasing
The contractor will be constructing this project in a singular phase, fulfilling the scope of
work as outlined in the contract documents. The contractor is responsible for
determining the scheduling and sequencing of activities based on their proposed means
and methods.
Public Outreach
The project scope will impact nearby businesses and residences. To ensure timely and
effective communication, the following notification measures will be implemented prior
to the start of construction:
Electronic message signs will be installed two weeks in advance of construction
activities to provide early notice of the project’s start date,
A project information sign will be posted at the construction site, including contact
information for public inquiries,
Residents and businesses within 1,000 feet of the project limits will receive door
hanger or mailed notifications at least two weeks before construction begins,
A second round of notification will be issued 48 hours prior to the start of
construction to residents and business adjacent to the limits of work, and
The City will also disseminate information through its official website and social
media platforms to keep the public informed of construction activities, including
any lane closures.
The Contractor is required to issue construction notices to adjacent residents and
businesses at least two weeks before construction begins. Additionally, the contractor is
required to install signage at the project site indicating project details and contact
information.
ENVIRONMENTAL IMPACT
Pursuant to the California Environmental Quality Act (CEQA), the recommended actions
are exempt from further review pursuant to Section 15301(b) of the CEQA Guidelines
for projects consisting of repair/maintenance of existing public facilities. The proposed
project continues to meet these parameters of the CEQA Guidelines and Categorical
Exemption Environmental Review No. ER-2026-1 will be filed for Project No. 24-
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project
April 21, 2026
Page 5
5
6
9
6
6701, 26-6701. Categorical Exemption Environmental Review No. ER-2026-2 will be
filed for Project No. 26-6701 (Exhibit 4)
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
projects is $5,799,849. All funds are available for expenditure in Fiscal Year 2025-26.
Any remaining balances not expended at the end of the fiscal year will be presented to
City Council for approval of carryovers into Fiscal Year 2026-2027 (Exhibit 5).
The proposed contract authorizes staff a maximum of 10% in construction contract
change orders for unanticipated and unforeseen work. Staff will return to City Council
for authorization and appropriation of additional funding if necessary.
Fiscal
Year
Accounting
Unit –
Account No.
(Project No.)
Fund
Description
Accounting Unit,
Account
Description
Amount
CURRENT BUDGET
2025-26
05917664-
66220
(24-6701)
Select Street
Construction
Vehicle Impact
Fee Program,
Improvements
Other than
Buildings
$2,165,346
2025-26
05917664-
66220
(25-6701)
Select Street
Construction
Vehicle Impact
Fee Program,
Improvements
Other than
Buildings
$2,203,680
2025-26
05917664-
66220
(26-6701)
Select Street
Construction
Vehicle Impact
Fee Program,
Improvements
Other than
Buildings
$1,430,823
TOTAL $5,799,849
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Environmental Determination
5. Capital Improvement Project Worksheet
Award a Construction Contract to All American Asphalt for the Construction of the
Industrial Street Repair Project
April 21, 2026
Page 6
5
6
9
6
Submitted By: Rodolfo Rosas, P.E., Acting Executive Director, Public Works Agency
Approved By: Alvaro Nuñez, City Manager
PWA
SANTA ANA
PUBLIC WORKS AGENCY
Project No. 24-6701, 25-6701, 26-6701:
Industrial Street Repair Program
Exhibit 1
LEGEND:
24-6701
- 24-6701 (SUSAN ST.)
- 25-6701 (YALE ST., CARRIAGE DR., AND GARRY AVE.)
- 26-6701 (SHANNON ST., AND MOORE AVE.)
25-6701
26-6701
ADDENDUM No. ONE
CITY OF SANTA ANA Project 24-670l
PROPOSAL Project 25-6701
PROJECT NO. 24-670l: INDUSTRIAL STREET REPAIR-susAN ST Project 26-670l
PROJECT NO. 25-6701 : INDUSTRIAL STREET REPAR -YALE ST, CARRY AVE, AND CARRIAGE DR
PROJECT NO. 26-6701 : INDUSTRIAL STREET REPAIR -SHAt`INON ST AND MOORE AVE
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
BASE BID:
PROJECT NO. 24-6701: INDUSTRIAL STRBET REPAIR -SUSAN STREET FROM RAILROAD
TRACKS T0 SEGERSTROM AVENUE
PROJECT No. 25-67oi : INDusTRIAL STREET REPAR -yALn STREET, GARRv AVENUE, AND
CARRIAGE DRIVE
PROJECT NO. 26-6701: INDUSTRIAL STREET REPAIR -SHANNON STREET AND MO0RE AVENUE
Item Description Qty Unit Unit Price Amount
1 Unclassified Excavation 9,290 CY S S
2 AC Pavement 13,340 TN S S
3 Cold Mill (2")10,000 SF S S
4 Asphalt Rubber Hot Mix (ARHM)3,700 TN S S
5 PCC Sidewalk (4")2,700 SF S S
6 PCC Driveway Approach 13,800 SF S S
(Commercial = 8")
7 PCC Curb Ramp I,700 SF S S
8 PCC Curb and Gutter (Type A-2-8)3,700 LF S S
9 PCC Cross-Gutter (Local Street)5,700 SF S S
10
Local Drainage Depression 8 SF S S
P-I of p-19
70.00
145.00
0.40
155.00
17.00
10.00
60.00
20.00
35.00
650,300.00
1,934,300.00
4,000.00
573,500.00
8.00 21,600.00
234,600.00
17,000.00
222,000.00
114,000.00
280.00
ADDENDUM No. ONE
CITY OF SANTA ANA Project 24-670l
PROPOSAL Project 25-6701
PROJECT NO. 24-6701: INDUSTRIAL STREET REPAIR _ susAN ST Project 26-6701
PROJECT NO. 25-6701 : INDUSTRIAL STREET REPAR -YALE ST, CARRY AVE, AND CARRIAGE DR
PROJECT NO. 26-6701 : INDUSTRIAL STREET REPAIR -SHANNON ST AND MOORE AVE
Item Description Qty Unit Unit Price Amount
[1
Furnish and Install New Water 62 EA S S
Valve Frame and Cover
12
Adjust Sewer and Drainage 24 EA S S
Manhole to Finished Grade
13 No. #6 Pull Box 8 EA S S
14 Adjust Monitoring Well*2 EA S S
]5
Furnish and Install Traffic Loops 4 EA S S
Type F
16
Furnish and Install Traffic Loops 6 EA S S
Type E
17
Furnish and Install Traffic Loop
1 EA S S
Type Q
18
Furnish and Install Detector Lead
150 LF S S
Cable
19 Install 2" PVC Conduit 20 LF S S
20 Truncated Dome Installation 1 EA S S
21 Parkway Culvert Type "A"5 EA S S
22 Parkway Culvert Type "8"12 EA S S
23 Traffic Signal Modifications I LS S S
24 Additional Potholing (As Needed)*6 EA S S
25
Furnish and Install MWS-L-4-2l-
I EA
S S
V-UG by Contech or Approved
Equal
26
Furnish and Install MWS-L-4-17-
I EA
S S
V-UG by Contech or Approved
Equal
27 Furnish and Install MWS-L-4-8-V-
1 EA S S
UG by Contech or Approved Equal
28 Root Shave*4 EA S S
29 Signing and Striping I LS S S
30 Railroad: UPRR Permit I LS $4,400 $4,400
P-2 of P-19
1,100.00
2,000.00
1,000.0
1,100.00
700.00
550.00
700.00
10.00
100.00
1500.00 1500.00
8,200.00 41,000.00
1,500.00 18,000.00
8,000.00 8,000.00
650.00 3,900.00
700.00 2,800.00
180,000.00 180,000.00
68,200.00
48,000.00
8,000.00
2,200.00
2,800.00
3,300.00
700.00
1,500.00
2,000.00
85,000.00 85,000.00
100,000.00 100,000.00
154,999.00154,999.00
ADDENDUM No. ONE
CITY OF SANTA ANA Project 24-670l
PROPOSAL Project 25-670 I
PROJECTNO. 24-670l: INDUSTRIAL STREET REPAIR_ SusAN ST Project 26-6701
PROJECT NO. 25-6701 : INDUSTRIAL STREET REPAR -YALE ST, GARRY AVE, AND CARRIAGE DR
PROJECT NO. 26-6701 : INDUSTRIAL STREET REPAIR -SHANNON ST AND MOORE AVE
Item Description Qty Unit Unit Price Amount
31 Railroad: UPRR Flagging* ' **60 DAY Sl,500 $90,000
32 Construction Sign 3 EA S S
33 Construction Permit 1 LS S 17,200 $ 17,200
34 Stomi Water Pollution Prevention
I LS S S
Plan (SWPPP) - Risk Level I
35 Irrigation and Landscape
I LS S S
Construction at 3400 W. Carry St.
TOTAL BASE BID S
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add-alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the 25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
** Contractor shall coordinate with the City if additional days are required for the project.
i This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number /751 working days after the commencement date stated in the Notice to
Pproceed. Upon issuance of the Notice to Proceed, Contractor shall immediately place order for
long-lead time items (Filterra Units pending pothole approval, and Union Pacific Railroad Permit).
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $7,000 per calendar day.
Name ofFirm AII American Asphalt
Signature of BIDDER
Title Edward J Carlson, Vice President
(If an individual, so state. If a firm or co-partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of president, Secretary, Treasurer and Manager, thereof.)
P-3 of P-19
4800.00
10,000.00 10,000.00
1600.00
10,000.00 10,000.00
4,639,879.00
CITY 0F SANTA ANA
PROPOSAL
pRoiECT NO. 24rd7O I : INDusTRIAL STREET REPAIR -susAN sT
PROJECT NO. 25J570l : INDUSTRIAL STREET REPAR -YALE ST, GARRY AVE, AND CARRIAGE DR
pRoiECT NO. 26rd7O I : INDusTRIAL STREET REPAIR -SHANNON sT AND MOORE AVE
BIDDER' S STATEMENT
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Cconstruction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council
with her signature and official seal noting hereon the action of approval of the Council, signed by
the Public Works Agency Executive Director or his/her duly authorized agent, and signed by the
City Attorney, denoting his approval of the form of this document, and its execution, and when it
or an exact copy of it has been either delivered to BIDDER or deposited with the United States
Postal Service properly addressed to the BIDDER with the correct postage affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinetly agreed that the proof of damages
actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond
substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation under
the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also cerdfies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of pegivry that the foregoing is true and correct.
NameofFim AllAmerican As
Signatureof8IDDER
Title Edward J Carlson, Vice President
(If an individual, so state. If a firm or co-partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-4 of P-I 9
CITY 0F SANTA ANA
CONSTRUCTION CONTRACT
pRoiECT 24rd7o I , 25rd7o I , 26rd7o I
INDUSTRIAL STREET REPAIR PROGRAM
This CONSTRUCTION CONTRACT is made and entered into this 21 day of April, 2026 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California thereinafter `CITY), and All American Asphalt
(JiereinaftertoNTRACTOR')..
WITNISSETH:
TThe CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
I. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, Industrial Street Repair Program Onereinafter referred to as the"WORK OF IMPROVEMENT") identified in and in accordance with the Contract Documents
prepared by the City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bidproposal
• BidBond
• Contract Form
• Contract Bonds
• General provisions
• Special provisions
• Technical provisions and project plans
• Community workforce Agreement
• Appendices
ln case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed Four Million Six Hundred Thirty Nine
Thousand Eight Hundred Seventy Nine Dollars and No Cents (sO,639,879.00), as set forth and
identified in the itemized BID PROPOSAL uploaded by the Contractor to PlanetBids, which is
attached hereto and incorporated herein as Exhibit "A".
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
Page I of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMIINT within the time specified in
the Time for Completion of Improvements and Liquidated Damages section of the BID PROPOSAL
(Exhibit "8') including commencing construction within the timefrane therein specified after
issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law,
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Work force Agreement
(CWA), a pre-hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at : httD : //www. santa-an a.oralowa/doc urn ents/C WA. Ddf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work Performance Bond), and one in the amount of one Hundred Percent ( 100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond anount shall be the greater ofTen Thousand Dollars (S 10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of one Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers thereinafter collectively referred to as "Indemnitees|,
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attomey's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of subcontractors provided by this section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other lndemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
JENNIFER L. HALL
City Clerk
APPROVED AS TO FORM:
SONIA R. CARVALHO
C ity Attorney
RECOMMENDED FOR APPROVAL:
RODOLFO ROSAS, P.E.
Acting Executive Director
Public Works Agency
CITY OF SANTA ANA
ALVARO NUNEZ
City Manager
CONTRACTOR:
All American Asphalt
By: Edwa J Carlson
TITLE: Vice President
Page 3 of 3
Rodolfo Rosas Digitally signed by Rodolfo Rosas
DN: cn=Rodolfo Rosas,
email=rrosas@santa-ana.org, c=US
Date: 2026.04.07 13:56:32 -07'00'
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT civlL CODE § iieo
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached. and not the t"thfulness. accuTacv. or validitv of`that document
State of Caljfornia
County of Riverside
on March 31st,2026 before me,Kimberlv Deiro. Notarv Public
H®re Insert name and Trdo of (ho officer
pruri ally rmoa red ES;]p|[#arlson
KIMBERLY DEIR0
Notary Public - Califomla
ii'y;iid';cJJhty- . E
Commisslon # 2491436
My Comm. Expires May 27, 2028
who proved to me on the basis of satisfactory evidence to be the
person(6) whose name(e,) is/ace subscribed to the within instrument
and acknowledged to me that he/chc,thc`,' executed the same in
his/iic:i/:I:Sir authorized capacity(ie6), and that by his/r:crAhe!r
signature(6) on the instrument the person(6), or the entity upon behalf
of which the person(e) acted, executed the jnstrument.
I certify under PENALTY OF PERJURY under the laus of the State of
California that the forgoing paragraph is true and correct.
OPTIONAL
Though trle information below is not required by law, it may prove valuable to person relying on the document
and could prevent fraudulent removal and reattachment Of this form to another document.
Description of Attached Document
Title or Type of Docilment
Document Date:
Construction Contract - City of Santa Ana
April 21st, 2026
Signer(e,) Other Than Named Above:
Number of Pages:
Capacity(lee) claimed by Signer(®)
Slgner's Name: Edward J. Carlson
I Individual
x corporate officer -Title(6): Vice president
lJ Other:
Signer's Name.N/A
i] Individual
t] Corporate Officer - Title(s):
Bid Result
Bidder Details
VendorName A\lAmerican Asphalt
Address 400 E. Sixth s[ree[
Corona, California 92879
United States
Respondee
Respondee Title
phor'e
Email
Vendor Type
Licerise #
Maurice Ramirez
Project Manager
951 -736-7600
krystall.padil\a@allamericanasphal[.com
CADIFi
267073
Bid Detail
Bld Format Electronic
Submitted 03/05/20261:55 PM (PST)
Delivery Method
BId Responsive
Bid status Submitted
Confirmation # 470410
Respondee Comment
Buyer Comment
Attachments
FI'e Title File Name
Industrial street Repair program-City of santa Industrial s[ree[ Repair program-City of santa
Ana cc>mpleted bid proposalpdF
ownership AFFidavi[.pdf
Bid Bond Guaranty.pdF
Non-Couusion AFFjclavit.pdf
And comp`eted bid proposal.pdf
Ownership AFFidavit.pdF
Bid Bond Guaranty.pdf
Non-Co`lusion AFFidavi[.pdF
I,\) 1u' ,
-r' ,,,,, €c ,i, ,i < ,zl,
Exhlblt A
File Type
General Forms
ownership AFfidavit (Notary Public) -REQ Orlginal
Hard CoF>y Submittal in Addition
Bid Bond Guaranty (Notary Public) -REQ Original
Hard Copy Si/bmittal in Addition
Non-Col`usior\ Affidavit (Notary Public) -REQ
Origina\ Hard Copy Submittal in Addition
Line Items
Discount Terms NO Discoiir`[
't..in:t=.=typ.
114 |lpe 'fro
2
i
e
9
10
1,
12
1,
1,
§
1,
17
1e
1,
ae
Z1
22
2,
2,
Z5
i,
27
2,
2,
sO
3'
)2
ae
W
as
At.th Nde
iE
)7
ae
I ton Eberith
unE`rssm.II tx.".tlon
^C P"mud
C®u' Mu' CI
AspA.It kylb.r I.ct M]x (utNM)
Ct S-U' (,1
PCC I>rwhp/ ^ppror{I. (Co-I..rcl.` I r)
p{c cud fan`p
pcc cult ..I c.tt.r |1)n>. A.Z.)
p« cross{uEter a.ck StrE.a
I.c.I thaln.a. beor.iil.n
nmlsli n. Ingt.ll Mw vet" v.I- nm. .nd conr
^ch.st Sou. ..I Dr.h.i. ..Inh®t. to rfebhed Gall.
N® tt pvu hex
^¢vct .... itorf.. .bir
nl7`tsh ..I ln.t*l Tnm Lap Typ. F
For-l]I` ..I last-II ThfBc I-®pf 1`ni. E
tt.ml.I end fo[t.u "M< l®.P type a
tmlch .nd lest.II I~r I..I C-bl.
I .si.u 2- "c coedt
".rated Eb-. JFBt.llatk.a
P.rtry C`,tut T)p>. -A.
p.rfupr c.tvert T)q}. --
tt.mc sl)nel hedihatlo..
A.dltl.hut a.thouhg t^! N..I.I) .
Fvml5h on. fo!t.lI MWS++Zlry-uC bar Contrd e. ^pprord Equl
Fvmlch un. I"t.ll MWS++17JV-UC bir Co.trd e. ^pprrd E|u..
ftlm]ch .nll lo!t.u Nts+1+`H/e by co.I.ch .r ^ppro-I E.v.I
Red shM.
sfroing .nd strtying
frollro.4: UptR A..ml(
toLLro.I: uP.I fl.I.ln.. . ~
c.m]tlv<fro son
C®nsm.cthm P-lE
Stem V.e.. P®ue€l.o one`..-B.Ii .I.. 6wMO - kbk I.`r.( 1
I ht).d.a .rd lmd.cp. Co..tn.cElo. k 1.cO W. a.mr !t.
A.bdsk Nctes p.. p... pi] Of sp«Ibe.tlom
IrgM QTY unu!"c. LJn.Tot.I A}..po"Conm.o.
*cOJ'„ae
cv .an Sroco S.so4ooae ves
" 1...0 S1.leo $1 ,.... oo.oo Yes
Sf 10000 cO
" ,7cO S,9SJ,O
s[ 2ro so
ev i..oo Si7Jx)
5r i7oo SioJxi
L, \,®0 S&OJ,®
SF S]cO S20®O
S, 1 S3SJ,®
E^ .2 si.icoco S.e,zOOcO vt.
E^ Z. $2.OcOcO S.|cOO.cO Y.!
E^ . Si.coaco S.¢oooo v.s
E^ z Si.ioo.a® s22o®co v.s
E^ . Srcoco S2.ooae Yes
E^ 6 S5saioo s3pco®o y«
E^ . $7aaio® $7ooco \n..
iT .so S.ace Si jocoo vei
lT 20 §100.00 Szroooco Y.l
EA 1 Siecoco Sisoouio y.i
E^ . S.r20aco S.1cOO.00 Y.s
E^ 12 Si+Oaco Silooo.OO y.I
is i simco s.ooeoo `fro
E^ . S.!o`oo S3,.coeo ves
u ` S`i+imo® S.u.in.so V-
IA 1 Sicomoco Siooo®aeo vls
EA t s&!rmco sos,OcO.cO y..
EA . S70aoo Szr.O.OO Y..
is 1 Si.a.Oa®ixi Sicoooooo v.i
ls 1 S+.OO.00 a++O®OO Y.s
DAY co Sisco.Oo S.a/moo `nes
E^ 3 Si+O®cO s.pcaoo yti
Ls i si7;zoai}o Si7xpOcO y(s
Ls 1 Siojroco Siocoam `nis
Ls i Sio/aeoo S.OOcoixi yd
SL'ce
M^ a sacs sa,Oe yti
Th. .-rdty fo. tlli. .I. lE- lf f lie.in for Old c.mp]rb®. o.tiL Thlf bld toI. f A.lL -oE I. .*|.ct he th. ts*- Ill.lt as .t.e.I
I-SeeEha 7-.. Of I.e !drd]rd sprdfl-tl..s. T...ttiul.moun( for tl`Is lton rd e. dhatl. b9/ Ll.. ac.u.l qu..dty.rs.4,.nd N^ a Saco Scoo vti
th. ^apor rei~ a.. givt to hocr.rs. er .car .... tl.. qurty/ or thls lha .corchgty.
Line Item Subtotals
eld Lil,® 't®us
Altorl.k Mo(..
SOA.9,.79cO
sOJ„
g'6,,.e79.00
EXHIBIT 8
ADDENDUM No. ONE
CITY OF SANTA ANA Project 24-670l
PROPOSAL Project 25-670 I
PROJEC`T NO. 24{70l: lNDUSTRIAL STREET REPAIR -SuSAN ST Project 26-670l
PROJEC`T NO. 256701 : lN'DUSTRIAL STREET R£PAR -YALE ST. CARRY AYE. AND CARRIAGE DR
PROJECT NO. 26-6701 : INDUSTRIAL STREET REPAIR -SHANNON ST AND MO0RE AVE
]'em bes.ri|ition Qty Uni(Unit Price Amount
31 Railroad: UPRR Flagging* . **60 DAY S I .500 $90.000
32 Construction Sign 3 EA $ 16oo.oo $ 4800.00
33 Construction Permit 1 LS S I 7,200 S I 7.200
34 Storm Water Pollution Prevention
I LS S S
Plan (SWPPP) -Risk Level I 10,000.0 10,000.00
35 Irrigation and Landscape
I LS S S
Construction at 3400 W. Carry St.10,000.00 10,000.00
TOTAL BASE BID $4,639,879.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid. and any` all. or none of the add-alternate bid items (if any).
* The quantity for this bid item is sho\^/n for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
** Contractor shall coordinate with the City if.additional days are required for the prcject.
i This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES
TThe undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number (75` working days after the commencemem date stated in the Notice to
Proceed. upon issuance of the Notice to Proceed, Contractor shall immediately place order for
long-lead time items (Filtema Units pending pothole approval. and Union Pacific Railroad Permit).
The liquidated damages amount. in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications. shall be $7.000 per calendar day.
Name ofFirm AM American Asphalt
Signature of BIDDER z4ZZ
Title Edward J Carlson. Vice President
([f an individual. so state. ]f a firm or co-partnership` state the firm name and give the names of
all individual co-partners composing the firm. ]f a corporation. state legal name of colporation.
and names of President. Secretary. Treasurer and Manager, thereof.)
P-3 of` P-19
TO BE FILED
TO BE FILED
CITY OF SANTA ANA FY 23/24CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT TITLE:PROJECT DESCRIPTION:PROJECT NEED:
Industrial Street Repair Program This project entails the rehabilitation of existing roadway pavement
for industrial streets. The project will include the removal and
replacement of existing asphalt streets. Various replacement
pavement strategies will be investigated to determine the most cost
effective and maintainable treatment. Minor concrete repair to
severely damaged or missing curbs, gutters, sidewalks, and
wheelchair ramps will also be included.
The interior roadway of non-residential street has been identified as
priority by the City's Pavement Management System. The pavement is
deteriorating due to weather, age, and heavy usage.PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP
PROJECT COSTS
Construction
FY 23/24
2,166,480
240,720
FY 24/25
2,166,480
240,720
FY 25/26
2,166,480
240,720
FY 26/27
2,166,480
240,720
FY 27/28
2,166,480
240,720
FY 28/29
2,166,480
240,720
FY 29/30
2,166,480
240,720Engineering
TOTAL 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200
SOURCE OF FUNDS FY 23/24
-
FY 24/25
-
FY 25/26
-
FY 26/27
-
FY 27/28
-
FY 28/29
-
FY 29/30
-
PAVMNT ACCELRTD REPAIR
IM
2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200
REFUSE MAINTENANCE -------
TOTAL 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200 2,407,200
AGENCY:DIVISION:CONTACT:
Public Works CIP Engineering Jason Gabriel, Principal Civil Engineer
26
CITY OF SANTA ANA FY 25/26CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT TITLE:PROJECT DESCRIPTION:PROJECT NEED:
Industrial Street Repair Program This project entails the rehabilitation of existing roadway pavement
for industrial streets. The project will include the removal and
replacement of existing asphalt streets. Various replacement
pavement strategies will be investigated to determine the most cost
effective and maintainable treatment. Minor concrete repair to
severely damaged or missing curbs, gutters, sidewalks, and
wheelchair ramps will also be included.
The interior roadway of non-residential street has been identified as
priority by the City's Pavement Management System. The pavement is
deteriorating due to weather, age, and heavy usage.PROJECT CATEGORY:
Street Improvements
Local Street Resurfacing
LOCATION MAP
PROJECT COSTS
Construction
FY 25/26
2,710,000
147,801
FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Engineering
TOTAL 2,857,801
SOURCE OF FUNDS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
GENERAL FUND
OTHER
250,000 -
-
-
-
-
-
-
-
-
-
-
-
2,607,801 -
TOTAL 2,857,801 -----
AGENCY:DIVISION:CONTACT:
Public Works CIP Engineering Jason Gabriel, Principal Civil Engineer
Ϯ ϵ 5HWXUQꢀ7Rꢀ7DEOHꢀRIꢀ&RQWHQWV