HomeMy WebLinkAbout2004-02•
RESOLUTION NO. 2004-02
Koo/1 /13/04
A RESOLUTION OF THE ZONING ADMINISTRATOR OF
THE CITY OF SANTA ANA APPROVING TENTATIVE
PARCEL MAP NO. 2003-07 AS CONDITIONED FOR THE
PROPERTY LOCATED AT 325 WEST PINE STREET
(COUNTY MAP NO. 2002-248)
BE IT RESOLVED BY THE ZONING ADMINISTRATOR OF THE CITY OF
SANTA ANA AS FOLLOWS:
Section 1. The Zoning Administrator of the City of Santa Ana hereby finds,
determines and declares as follows:
A. The Applicant is requesting approval of a tentative parcel map to subdivide
a 0.33-acre parcel into two lots to facilitate the construction of two new
single-family residences at 325 West Pine Street.
B. Tentative Parcel Map No. 2003-07 came before the Zoning Administrator
of the City of Santa Ana for a public hearing on January 21, 2004.
C. The Zoning Administrator determines that the following findings have been
established:
1. The proposed project, as conditioned, and its design and
improvements are consistent with the Low Density Residential land
use designation of the General Plan and are otherwise consistent
with all other elements of the General Plan and any applicable
specific plans.
The proposed subdivision creates two conforming lots
consistent with the Low Density Residential designation
provisions and the Specific Development No. 40 zoning
district. Each lot has been designed to accommodate one
single-family residence.
2. The proposed project, as conditioned, conforms to all applicable
requirements of the zoning and subdivision codes as well as other
applicable City ordinances.
The proposed subdivision conforms to the minimum lot size
and street frontage requirements, as well as meets the letter
and intent of the State of California Subdivision Map Act
provisions and the Specific Development No. 40 zoning
Resolution No. 2004--02
Page 1 of 4
district. Each lot will maintain a minimum of 50 feet of street
frontage and 6,000 square feet of lot area.
3. The project site is physically suitable for the type and density of the
proposed project.
The project site is a corner lot that contains frontage on two
streets, allowing adequate frontage for each parcel. Both
proposed residential lots meet the minimum frontage and
required lot size of one dwelling unit per 6,000 square feet of
lot area. There are no physical constraints on the site to
preclude development. The parcels will aid in the
implementation of quality infill single-family residential
development.
4. The design and improvements of the proposed project will not
cause substantial environmental damage or substantially and
avoidably injure fish and wildlife or their habitat.
There are no wetlands or unusual flora or fauna on or around
the project site. No development surrounding this site will be
affected by this proposal.
•
5. The design or improvements of the proposed project will not cause
serious public health problems.
The proposed infill development is residential and will be in
compliance with the Specific Development No. 40 zoning
district provisions for single-family residential development
and building code requirements.
6. The design or improvements of the proposed project will not conflict
with easements necessary for public access through or use of the
property within the proposed project.
There is an ingress and egress easement on the
northeastern portion of the lot, however, the proposed
project will not conflict with the easement and will not affect
the use or development of this site.
•
Section 2. In accordance with the California Environmental Quality Act, the
proposed project is exempt from further review. Categorical Exemption Environmental
Review No. 2003-13 will be filed for this project.
Section 3. The Zoning Administrator of the City of Santa Ana after conducting
the public hearing hereby approves Tentative Parcel Map No. 2003-07 as conditioned in
Exhibit "A" attached hereto and incorporated herein.
Resolution No. 2004--02
Page 2 of 4
ADOPTED this 21St day of January,2004.
•
Kenneth Adams
Zoning Administrator
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
By:~ :~ ~_
Kylee O.
Deputy Cir Attorney
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, MARTHA RAMIREZ, Clerk of the Zoning Administrator, do hereby attest to and certify
the attached Resolution No. 2004-02 to be the original resolution adopted by the Zoning
• Administrator of the City of Santa Ana on January 21, 2004.
Date: D ~ G'°-%I ~
Cle of the Zoning Administr r
City of Santa Ana
C7
Resolution No. 2004--02
Page 3 of 4
• Conditions of Approval for Tentative Parcel Map No. 2003-07
Tentative Parcel .Map No. 2003-07 (County Map No. 2002-248) is approved subject to
compliance, to the reasonable satisfaction of the Planning Manager, with all applicable
sections of the Santa Ana Municipal Code, the California Administrative Code, the Uniform
Fire Code, the Uniform Building Code and all other applicable regulations.
The applicant. must comply in full with each and every condition listed below rip ~or to
exercising the rights conferred by this tentative parcel map.
A. Planning Division
1. The Final Map is required to be recorded within two years of the date of
approval for the tentative map by the City Council.
2. Two copies of the recorded Final Map need to be submitted to the Planning
Division and Public Works Agency within 10 days of recordation.
3. All development within the area of the map is subject to development and
permit fees in effect at the time of permit issuance.
4. All development within the area of the map is subject to all design and
• development standards in effect at the time of permit issuance.
5. The tentative map, final map, and all improvements required to be made or
installed by the subdivider will be in accordance with the design standards
and specifications of the Santa Ana Municipal Code and the requirement of
the State Subdivision Map Act.
6. Prior to issuance of permits beyond one single-family residence, a new grant
deed must be recorded to create two legal building sites.
7. All proposed site improvements must comp{y with Development Review
Committee comments dated February 14, 2003 for Site Plan Review DP No.
03-02.
8. The ingress and egress easement recorded November 8, 1988, as
Instrument No. 88-570294 for the northerly 3-feet of the easterly 26-feet
and 6-inches of lot six, must be maintained. (Modified by the Zoning
Administrator on January 7. 2004.)
Exhibit "A"