CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
? Ordinance on 15` Reading
? Ordinance on 2nd Reading
? Implementing Resolution
? Set Public Hearing For
CONTINUED TO
FILE NUMBER
Adopt a resolution supporting state funding for three projects in the City and authorizing the City to
submit the Bristol Street, First Street, and Memory Lane/Flower Street bike lane projects for funding
consideration under the Bicycle Transportation Account.
DISCUSSION
The State of California Department Transportation issued a call for Bicycle Transportation
Accounts (BTA) applications for Fiscal Year 2011-2012. BTA is a state funded program which
provides construction funds for projects that improve safety and convenience for bicycle
commuters.
In response to this call the City is requesting authorization to submit grant applications for three
projects: Bristol Street bike lane extension from McFadden Avenue to Edinger Avenue, First
Street bike lane from Harbor Boulevard to Newhope Avenue, and Memory Lane/Flower Street
from Bristol Street to Fisher Park. These projects involve new class II (on-street) bike lane
installations (Exhibit 2). The application deadline is March 18, 2011.
To be eligible for BTA grant funding the projects need to be listed in the City's Bikeway Master
Plan and approved by Orange County Transportation Authority (OCTA). The Memory
Lane/Flower Street bike lane is currently not on the City's Bikeway Master Plan or approved by
OCTA. However, the update of the Santa Ana Bikeway Master Plan to include Memory
Lane/Flower Street bike lane is scheduled for adoption by City Council on March 21, 2011
following the environmental review process. City staff is coordinating with OCTA staff to pursue
OCTA approval for the Bicycle Transportation Plan that includes the Memory Lane/Flower Street
bike lane so that it will be eligible for BTA funding. The adoption by City Council of the Bikeway
Master Plan and approval by OCTA of the Bicycle Transportation Plan may follow the funding
application deadline according to the program guidelines.
55D-1
Authorization to Submit BTA
Project Applications
March 7, 2011
Page 2 of 2
ENVIRONMENTAL IMPACT
Per Section 15061(b)(3) of the Environmental Quality Act, this action is exempt from further
review as there is no potential for any environmental impact.
FISCAL IMPACT
For the Bristol Street and First Street bike lane projects the City will need to provide 10 percent
matching funds and the Bicycle Transportation Account will provide 90 percent of the funding for
any project that is approved for funding. The City's 10% match for those projects receiving BTA
grant funds will be budgeted in a future Capital Improvement Program.
APPROVED AS TO FUNDS AND ACCOUNTS:
Raul Go ez II Francisco Gutierrez
Executive Director Executive Director 0
Public Works Agency Finance & Management Services Agency
RG/ZK
Exhibit 1: Resolution
Exhibit 2: Location Map
Exhibit 3: Project Cost
55D-2
Iss2/19/11
RESOLUTION NO. 2011-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA AUTHORIZING THE SUBMISSION OF
PROJECTS FOR FUNDING UNDER THE BICYCLE
TRANSPORTATION ACCOUNT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines and
declares as follows:
A. The California Department of Transportation is responsible for administering
the Bicycle Transportation Account (BTA) which provides state funds for city
and county projects to improve safety and convenience for bicycle
commuters.
B. To be eligible for BTA funding, the City of Santa Ana is required to adopt a
bicycle transportation plan that meets the requirements of the California
Transportation Act (California Streets and Highways Code Section 891.2)
and is approved by the regional transportation authority.
C. On May 22, 2009, the Orange County Transportation Authority (OCTA)
adopted its OCTA Commuter Bikeways Strategic Plan (CBSP) which is
consistent with the Santa Ana bicycle transportation plan.
D. Projects funded through the Bicycle Transportation Account, require that the
applicant furnish funding for ten percent (10%) of the total cost of
constructing the proposed bikeways and related facilities.
Section 2. The City Council of the City of Santa Ana authorizes the Executive Director
of the Public Works Agency to submit an application for Bicycle Transportation Account
funding for three Class II bike lane projects including:
• Bristol Street bike lane extension from McFadden Avenue to Edinger Avenue
• First Street bike lane from Harbor Boulevard to Newhope Avenue
• Memory Lane/Flower Street from Bristol Street to Fisher Park
Section 3. The City Council of the City of Santa Ana certifies that, if selected, the City
will provide the required ten percent matching funds, and will have sufficient funds to
operate and maintain the project(s).
Resolution 2011-xxx
Page 1 of 2
55D-3
Section 4. The City Council of the City of Santa Ana authorizes the City Manager and/or
the Executive Director of the Public Works Agency to execute and submit all documents
and take any actions necessary, for and on behalf of the City of Santa Ana, for the
purpose of obtaining financial assistance from the State of California, Department of
Transportation, under the Bicycle Transportation Account.
Section 5. This Resolution shall take effect immediately upon its adoption by the City
Council, and the Clerk of the Council shall attest to and certify the vote adopting this
Resolution.
ADOPTED this day of
Councilmembers
Miguel A. Pulido
Mayor
APPROVED AS TO FORM:
Joseph Straka, Interim City Attorney
By:
Laura S. Sheedy
Assistant City Attorney
AYES:
NOES: Councilmembers
ABSTAIN: Councilmembers
NOT PRESENT: Councilmembers
2011.
CERTIFICATE OF PUBLICATION AND ORIGINALITY
I, MARIA D. HUIZAR, Clerk of the Council, do hereby attest to and certify the attached
Resolution No. 2011-XXX to be the original resolution adopted by the City Council of the
City of Santa Ana on
Date:
Clerk of the Council
City of Santa Ana
Resolution No. 2011-xxx
Page 2 of 2
55D-4
Bristol Street
McFadden Avenue
to Edinger Avenue
SANTA ANA ity Council RESOLUTION AND AUTHORIZATION FOR BTA
Pi WA Agenda Date APPLICATIONS FOR BRISTOL STREET, FIRST
% STREET, AND MEMORY LANE/FLOWER STREET
PUBLIC WORKS AGENCY March 7, 2011
BIT 2
55D-6
Bicycle Transportation Account
On-Street Bike Lane Projects Recommended for Grant Application
FY 2011-2012
Location Project Cost
Bristol Street From McFadden Avenue to
Edinger Avenue $72,000
First Street from Newhope Avenue to
Harbor Boulevard $143,000
Memory Lane/Flower Street from Bristol
Street to Fisher Park $236,000
Total $451,000