HomeMy WebLinkAbout19D - RFP - PRE-PRELIMINARY ENGINEERINGREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
AP RI L 18, 2011
TITLE:
AUTHORIZATION TO REQUEST
PROPOSALS FOR PRE-
PRELIMINARY ENGINEERING
ANALYSIS FOR THE SANTA ANA
GARDEN GROVE FIXED GUIDEWAY
(PROJECT 092505)
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
? Ordinance on 1" Reading
? Ordinance on 2nd Reading
? Implementing Resolution
? Set Public Hearing For_
CONTINUED TO
FILE NUMBER
Authorize the Public Works Agency to issue a Request for Proposals (RFP) to qualified consulting
firms to prepare Pre-Preliminary Engineering project deliverables required by the Federal Transit
Administration.
DISCUSSION
On March 7, 2011, Council authorized staff to execute a cooperative agreement with the Orange
County Transportation Authority (OCTA), in an amount not to exceed $5,541,700 for Pre-
Preliminary Engineering (Pre-PE) and Preliminary Engineering (PE) activities for the Santa Ana-
Garden Grove Fixed Guideway Project. The cooperative agreement with OCTA defined the roles
and responsibilities related to funding and project delivery between OCTA and Santa Ana for Pre-
PE and PE activities consistent with Measure M2 as well as federal guidelines and requirements.
Prior to entry into the PE phase, there are certain project development activities that need to be
completed to satisfy Federal Transit Administration (FTA) requirements. Such activities include
items such as project and fleet management plans and a detailed FTA ridership analysis for the
purpose of ridership modeling. Such tasks were not included as part of the Go Local Step Two
grant awards and scope of work.
Therefore, in order to complete these necessary tasks, staff is requesting authorization to solicit
proposals from qualified consulting firms to prepare Pre-PE project deliverables in an amount not to
exceed $529,360. For your information, key RFP dates are shown below:
RFP Issued: April 22, 2011
Pre-Proposal Meeting: Week of May 2, 2011
Proposal Due Date: May 20, 2011
Interview Date: Week of June 6, 2011
Contract Award: July 5, 2011
19D-1
Pre-Preliminary Engineering RFP
April 18, 2011
Page 2
It should be noted that unless extended by contract amendment, the Pre-PE contract will terminate
on February 1, 2012. Further, all FTA funding is passed through OCTA since they are the grant
recipient. OCTA will provide oversight for the project to ensure that the federal procurement
process is followed and that all documents prepared by the consultant(s) are in compliance with
FTA New Starts and Small Starts funding criteria.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
FISCAL IMPACT
On November 22, 2010, the OCTA Board allocated funding in the amount of $661,700 for the
Pre-PE analysis with a required 10% local match of $66,170. Funds for the local match are
available in Measure M Street Construction (accounting unit 03217660-66220, project 092505).
APPROVED AS TO FUNDS AND ACCOUNTS:
Raul Godinez II Francisco Gutierrez
Executive Director Executive Director
Public Works Agency Finance & Management Services Agency
RG:RB
Exhibit 1: RFP Scope of Work
1901-2
REQUEST FOR PROPOSAL
SANTA ANA-GARDEN GROVE FIXED GUIDEWAY PROJECT
PRE-PRELIMINARY ENGINEERING ANALYSIS
Key RFP Dates
RFP Issued:
Pre-Proposal Meeting
Proposal Due Date:
Interview Date:
Contract Award:
April 22, 2011
Week of May 2, 2011
May 20, 2011
Week of June 6, 2011
July 5, 2011
CITY OF SANTA ANA
PUBLIC WORKS AGENCY
20 CIVIC CENTER PLAZA
SANTA ANA, CALIFORNIA 92702
Issued by:
Dave Biondolillo
City of Santa Ana
Exhibit 1 1r6b_ pe of Work
IV. SCOPE OF WORK
Task 1 - New Starts Templates and Application
A significant amount of work in support of the project has recently been prepared
through the Conceptual Engineering/Alternatives Analysis/Draft Environmental Analysis
effort. At project kick-off, City of Santa Ana staff will provide Consultant with copies of
the documents that provide information relevant to the Pre-PE scope of work. For
efficiency and consistency, Consultant shall draw from those materials to the maximum
extent feasible to prepare and assemble all documents and data needed for an FTA
Section 5309 (New Starts/Small Starts/Urban Circulator) application, including:
A. Project Description
B. Standard Cost Categories (SCC) Annualized Cost Worksheets
C. Land Use Supporting Information
D. Project Financial Plan & Supporting Information
E. "Making the Case" Document
Task 1 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft Project Description,
SCC Annualized Cost Worksheets, Land Use Supporting Information, Project
Financial Plan & Supporting Information, and "Making the Case" Document
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final Project Description,
SCC Annualized Cost Worksheets, Land Use Supporting Information, Project
Financial Plan & Supporting Information, and "Making the Case" Document
Task 2 - Project Management Plan (PMP)
As a condition of Federal assistance, a grant applicant for a major capital investment
project must prepare a Project Management Plan (PMP) consistent with 49 USC 5327
(Project Management Oversight) and 49 CFR 633 (Project Management Oversight
Rule). The grant applicant must submit the PMP in time for FTA to review the
applicant's plan in conjunction with its New Starts/Small Starts grant application. The
196-4
PMP is a dynamic document for managing engineering, design, construction and start-
up of a project. The PMP must provide sufficient detail to demonstrate the grant
applicant's technical capability to carry out the project.
Consultant shall develop a draft PMP that addresses the following items:
A. Adequate recipient staff organization with well-defined reporting relationships,
statements of functional responsibilities, job descriptions, and job qualifications;
B. Budget that covers the project management organization, appropriate
consultants, property acquisition, utility relocation, systems demonstrations staff,
audits, and miscellaneous payments the recipient may be prepared to justify;
C. Construction schedule for the project:
D. Document control procedure and recordkeeping system
E. Change order procedure that includes a documented, systematic approach to
handling of construction change orders;
F. Organizations structures, management skills, and staffing levels required
throughout the construction phase,
G. Quality control and quality assurance functions, procedures, and responsibilities
for construction, system installation, and integration of system components;
H. Material testing policies and procedures;
1. Internal plan implementation and reporting requirements;
J. Criteria and procedures for testing the operational system or its major
components;
K. Periodic updates of the plan, especially related to project budget and project
schedule, financing, ridership estimates, and the status of local efforts to
enhance ridership where ridership estimates partly depend on the success of
those efforts;
L. The recipient's commitment to submit a project budget and project schedule to
the Secretary of Transportation each month; and
For purposes of this task, Consultant shall assume that items b and c, Budget and
Construction Schedule, would be the same regardless of which agency chooses to
implement the project.
10
1901-5
It is assumed that a final decision regarding project ownership and management may be
reached before completion of Pre-PE. If that is the case, Consultant shall prepare a final
PMP focused on the single, approved scenario.
The final PMP shall include a plan for managing later stages of the project. Consistent
with FTA guidance, such plan shall be laid out in general terms with a description of
how and when the details will be developed. Nonetheless, the grant application
prepared by Consultant shall demonstrate that the plan will be developed and
implemented as necessary to stay ahead of the implementation of the project.
Task 2 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft PMP
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final PMP
Task 3 - Safety & Security Management Plan (SSMP)
Consultant shall prepare a SSMP which fully complies with 49 CFR 633 and is prepared
in accordance with FTA's Circular C 5800.1. Sections of the SSMP shall include:
A. Management Commitment and Philosophy
B. Integration of Safety and Security into Project Development Process
C. Assignment of Safety and Security Responsibilities
D. Safety and Security Analysis
E. Development of Safety and Security Design Criteria
F. Process for Ensuring Qualified Operations and Maintenance Personnel
G. Safety and Security Verification Process
H. Construction Safety and Security
1. Requirements for 49 CFR Part 659, Fixed Guideway Systems; State Safety
Oversight
J. Federal Railroad Administration (FRA) Coordination Plan (if necessary)
K. Department of Homeland Security (DHS) Coordination Plan
Task 3 Deliverables.-
196-6
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft SSMP
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final SSMP
Task 4 - Fleet Management Plan, Draft (FMP)
Consistent with the requirements set forth in FTA's Circular 9030.1D, Consultant shall
develop a draft FMP that proposes how the Santa Ana-Garden Grove fixed guideway
system will be properly planned for and managed. The FMP shall be substantially
consistent with the adopted Record of Decision (if applicable) and sufficiently complete
in detail and analysis to readily demonstrate the project's ability to maintain and/or
improve service levels, operating costs, and the reliability and quality of service for a
minimum of 10 years following project construction.
A. The FMP shall plan for and discuss the overall management of the entire fleet of
vehicles and related support functions and equipment, addressing all the
reasonably foreseeable factors that are relevant to the determination of
equipment needs in light of demand for service. It should address in detail the
composition of the fleet, operating conditions, maintenance, facilities, peak
vehicle demand, and spare ratio;
B. The FMP shall discuss in detail:
a. Requirements for peak and spare vehicles including schedule spares,
maintenance spares, parts spares,
b. Requirements for support functions such as heavy maintenance, capital
and operating parts inventory and information technology,
c. Strategies for acquiring new vehicles or overhauling existing equipment
and the tradeoffs between them,
d. Strategies for maintenance and operations including reducing spare
vehicles, and
e. Strategies for reducing operating costs and increasing service reliability.
12
19D-7
C. The FMP shall include operating and financial data such as current estimates of
vehicle operating costs, reliability and life expectancy, for decision-making and
performance review.
D. The FMP shall be formatted and calculated in conformance with FTA Circular
9030.1 D, specifically with respect to:
a. Definition of terms,
b. Description of existing system and expansion plans, both project and non-
project related,
c. Justification of the demand for revenue vehicles and operating spare ratio,
d. Process for reconciling demand versus supply to determine if additional
vehicles will be needed, overhauled, procured or other changes in
maintenance practices, inventory, information technology, capital
investment will be implemented instead;
e. Preventive maintenance schedule for the procured/overhauled rail car
fleet;
f. Grantee's reliability program, past performance and plans to improve
reliability including profile monitoring and support of maintenance, failure
rates and rail cars out-of-service, and train failure definitions and actions;
E. The FMP shall discuss the selection and specification of vehicle equipment and
systems and how the specifications matched the appropriate technology with the
planned transit applications for the best performance at the lowest cost.
F. The FMP shall ensure that the project's estimates of costs, service levels, quality,
or reliability are mechanically correct and complete, consistent with the grantee-
defined methodologies and free of any material inaccuracies or incomplete data.
G. The FMP shall discuss the project's forecasts and schedule, to be consistent with
the plan scope and project scope adopted in the Record of Decision (if
applicable) and the proposed Revenue Operations Date and shall free of any
material inaccuracies or incomplete data.
Task 4 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft FMP
13
19D-8
Task 5 - Quality Management Plan (QMP)
Consultant shall prepare a QMP that is consistent with the requirements presented in
FTA's Quality Assurance and Quality Control Guidelines (February 2002).
Task 5 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft QMP
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final QMP
Task 6 - Real Estate Acquisition Management Plan (RAMP)
Consultant shall prepare a RMP which fully complies with 49 CFR Part 24 and is based
upon FTA's "Model for Development of a Real Estate Management Plan".
Task 6 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft RAMP
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final RAMP
Task 7 - Investment Grade Ridership Forecasts
Consultant shall review the ridership forecasts developed during the Conceptual
Engineering phase and, if necessary, perform additional work to provide defensible
travel demand forecasts for the following years, taking into account typical "ramp up"
effects of new transportation modes:
A. Opening Day (2015)
B. Interim (2025)
C. Long-Term (2035)
The resulting forecasts shall based upon OCTAM, but shall include refinements
necessary to accurately forecast system ridership. Consultant shall secure OCTA
14
19D-9
concurrence on any proposed refinements to OCTAM and, if necessary, develop travel
surveys and analyze travel forecasting uncertainties to support the proposed approach
to developing Santa Ana-Garden Grove fixed guideway system ridership forecasts. The
final report shall detail any post-processing or "off-model" work that was completed and
include ridership forecast for Task 8, FTA Summit Analysis.
Task 7 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft ridership forecasts
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final ridership forecasts
Task 8 - FTA Summit Analysis
Using the FTA Summit software, Consultant shall determine Transportation System
User Benefits for reduced the set of "Build" and "No Build" alternatives selected for the
Santa Ana-Garden Grove fixed guideway project. This information shall be presented in
a report that includes:
A. Thematic Maps for each of the Build Alternatives versus the Baseline Alternative
B. Production & Attraction Maps for Each Trip Purpose & Period
C. Daily Totals
Additional inputs and outputs from Summit, such as trip length frequency reports and
row and column sum outputs, shall also be provided.
Task 8 Deliverables:
1. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the draft Thematic Maps for
Each of the Build Alternatives versus Baseline, Production & Attraction Maps
for Each Trip Purpose & Period, and Daily Totals
2. One electronic version (on CD in Microsoft Office Word 2007 or Microsoft
Office Excel 2007 format) and 12 hard copies of the final Thematic Maps for
Each of the Build Alternatives versus Baseline, Production & Attraction Maps
for Each Trip Purpose & Period, and Daily Totals
15
19D-10