CONTRACT CHANGE ORDER NO. 2:
DYER ROAD AND GRAND AVENUE
INTERSECTION WIDENING
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
? Ordinance on 1s` Reading
? Ordinance on 2nd Reading
? Implementing Resolution
? Set Public Hearing For_
CONTINUED TO
FILE NUMBER
Approve Change Order No. 2 for Dyer Road and Grand Avenue Intersection Widening for an
estimated cost of $75,000.
DISCUSSION
Last summer, two water mains broke occurred: one on Grand Avenue north of Dyer Road and
the other near the Dyer Road/Hotel Terrace intersection. Gushing water caused extensive
damage to the pavement, median island and sidewalk. The water mains were repaired promptly
by the City crew and the pavement and sidewalk were temporarily patched.
A permanent repair is required. If the repair were to be done by a maintenance contractor, the
cost would exceed $150,000. However, since the damaged areas are in proximity to the Dyer
Road/Grand Intersection project, All American Asphalt (the contractor for the project) is able to
perform the repair work at a lower cost based on unit bid prices. A change order is required to
reconstruct the permanent pavement, median island, and sidewalk at the affected areas
(Exhibits 1 and 2). The contractor shall be paid according to the contract unit prices and the
actual quantity of work.
FISCAL IMPACT
The cost for the change order is estimated at $100,000. Funds are available in the Water
System Maintenance Fund (accounting unit 06017641-62300).
23B-1
Contract Change Order No. 2:
Dyer Road and Grand Avenue
Intersection Widening
April 18, 2011
Page 2
t
Raul Godinez II
Executive Director
Public Works Agency
RG/MG
Exhibit 1: Change Order No. 2
Exhibit 2: Change Order Analysis
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
23B-2
CITY OF SANTA ANA
PUBLIC WORKS AGENCY
CONTRACT CHANGE ORDER
Project Numbers 09-1751: DYER ROAD AND GRANn AVFNI 1F
INTERSECTION WIDENING
Change Order Number 2
To ALL American Asahalt
Contractor
You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and
specifications on this contract.
NOTE; THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER.
Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.
Change requested by
PUBLIC WORKS AGENCY
REVISE THE FOLLOWING BID ITEMS OF THE CONTRACT
Remove existing and construct AC Pavement, sidewalks, PCC retaining curb and pattern stamped
concrete on Grand Avenue north of Dyer Road and Dyer Road/Hotel Terrace intersection per
PCO #3.
Line
Estimated Unit
Item # Line Item Unit Quantity Price
2 Unclassified Excavation CY 2800 $33
3 AC Pavement TN 4300 $72
5 PCC Retaining Curb 131-A LF 260 $36
7 PCC Sidewalk (4") SF 7500 $4
10 Patterned Stamped Concrete SF 1100 $7
12 Furnish and Install Water EA 5 $730
Valve Box Frame and Cover
21 Adjust OCSD Manhole Frame EA 4 $1,050
and Cover to Grade
P 3? 3
Exhibit 1
CITY OF SANTA ANA
PUBLIC WORKS AGENCY
CONTRACT CHANGE ORDER
Project Number 09-1751; DYER ROAD AND GRAND AVENUE Change Order Number 2
INTERSECTION WIDENING
To ALL American Asphalt Contractor
You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and
specifications on this contract.
NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER.
Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.
Change requested by
PUBLIC WORKS AGENCY
The compensation both time and cost set forth in this final change order comprises the total
compensation due the Contractor, all Subcontractors, and all Suppliers for all work performed per
this change order, including impact on unchanged work. By signing this final change order, the
Contractor acknowledges and agrees on behalf of himself, all Subcontractors, and all Suppliers,
that the stipulated compensation includes payment for all work contained in this final change order,
plus all payment for interruption of schedules, extended field overhead, home office overhead,
profit, delay, and all impact, ripple effect or cumulative impact on all other work under this Contract.
The signing of this final change order constitutes full mutual accord and satisfaction for all changes
and work performed on this project, and that the time and cost paid per this final change order
constitutes the total equitable adjustments owed the Contractor, all Subcontractors, and all
Suppliers for all work performed on this project. The Contractor on behalf of himself, all
Subcontractors, and all Suppliers agrees to waive all rights, without exception or reservation of any
whatsoever to file any further claim related to this project.
ESTIMATED
TOTAL COST THIS CHANGE ORDER: DECREASE $ - - - - - INCREASE $ 100,000
By reason of this order the CONTRACT TIME completion will be adjusted as follows None.
We the undersigned contractor have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all service necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted, Date Contractor ALL American Asphalt
By Title
Approval recommended by
PUBLIC WORKS AGENCY EXECUTIVE DIRECTOR
Approved by
CITY MANAGER
Date
Date
23??4 2
CHANGE ORDER ANALYSIS
DYER ROAD AND GRAND AVENUE INTERSECTION WIDENING
CHANGE ORDER NO. 2
Change Order Number: 2
Project Description: Dyer Road and Grand Avenue Intersection Widening
Contractor: All American Asphalt
PO Box 2229
Corona CA 92878-2229
Original Contract Cost: $721,180
Amount of this
Change Order: $100,000 13.9 percent
Previously approved
Change Order: 72,118 10.0 percent
Total Change Orders: $172,118 23.9 percent