HomeMy WebLinkAbout23A - PROJ - FAIRVIEW TRIANGLE HABITAT RESTORATIONREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: CLERK OF COUNCIL USE ONLY: OCTOBER 3, 2011 TITLE: APPROVED CONTRACT AWARD FOR FAIRVIEW ? As Recommended TRIANGLE HABITAT RESTORATION o ?rAmended ? Ordinance on 15f Reading (GRANT FUNDED) (PROJECT NO. ? Ordinance on 2"d Reading 086028) E] Implementing Resolution ? Set Public Hearing For CONTINUED TO - t FILE NUMBER CITY MANAGER RECOMMENDED ACTION Award a contract to ACE CD, Inc., the lowest responsible bidder, in accordance with unit bid prices for the base bid in the estimated amount of $93,207.50 for construction of the Fairview Triangle Habitat Restoration. 2. Approve a funding analysis with a total estimated construction cost of $123,780. DISCUSSION The Fairview Triangle is a triangular-shaped undeveloped dirt lot along the Santa Ana River Recreational Trail and Fairview Avenue, south of 17th Street (Exhibit 1). The Santa Ana River Vision Plan, which was adopted by City Council on August 7, 2006, identified this property as an area of opportunity in that it could be developed into a trail-side rest area for pedestrians and cyclists. The proposed project includes decomposed granite paths, benches, a bike rack, drought- tolerant landscaping, and an irrigation system using reclaimed water. The improvements will provide a space for trail users to rest as well as view the existing habitat area. The Notice Inviting Bids was advertised on August 17 and 18, 2011, and bids were opened on September 7, 2011. A summary of the bid invitations mailed, the bids received, and the bid results follows. Santa Ana Contractors receiving notices: 19 Contractors requesting bidding documents: 26 Bids received: 10 Bids received from Santa Ana Contractors: 0 23A-1 Contract Award For Fairview Triangle Habitat Restoration October 3, 2011 Page 2 While the City made outreach efforts to Santa Ana contractors regarding the notice inviting bids, no contractors from Santa Ana submitted bids. A survey was taken from randomly selected Santa Ana contractors who chose not to bid. The results indicated that they either were not capable of performing this type of work, were unable to obtain insurance because the project was too large, or they worked as a subcontractor to certain prime contractors. The bids received are as follows. NAME OF RESPONSIVE BIDDER CITY BASE BID AMOUNT 1. ACE CD, Inc. Glendora $93,207.50 2. Moalej Builders Sherman Oaks $101,752.60 3. Fleming Environmental, Inc. Fullerton $104,065.55 4. Native Landscaping, Inc. Escondido $109,365.00 5. STL Landscape, Inc. Los Angeles $116,000.00 6. HYM Engineering, Inc. Buena Park $125,860.00 7. Ted Enterprises, Inc. San Clemente $139,750.00 8. Aramexx Const. Chino $148,295.00 9. Unique Performance Const. Inc. Costa Mesa $166,645.00 10. Atom Engineering Const. Hemet $177,398.00 A total of 10 bids were received and all were responsive. The lowest bid was submitted by ACE CD, Inc., for $93,207.50, which is below the Engineer's estimate of $105,500. ENVIRONMENTAL IMPACT Environmental Review #ER-2006-166 has been completed and a Notice of Exemption has been filed pursuant to the California Environmental Quality Act. In addition, a Certificate of Categorical Exclusion has been prepared in accordance with the National Environmental Quality Act. 23A-2 Contract Award For Fairview Triangle Habitat Restoration October 3, 2011 Page 3 FISCAL IMPACT The funding analysis shows a total estimated construction cost of $123,780 for the project (Exhibit 2). Funds are available in the National Recreation Trails Fund Act (accounting unit 17213240-66220) and the Park Acquisition and Development Fund (accounting unit 31113260- 66220). F Raul Godinez gIll Executive Director Public Works Agency APPROVED AS TO FUNDS AND ACCOUNTS: Francisco Gutierrez Executive Director Finance & Management Services Agency Gerardo Mouet Executive Direct r Parks, Recreation, and Community Services Agency RGMA Exhibits: 1. Project Location Map 2. Funding Analysis 23A-3 23A-4 B ? LA VE TP G???E FP?y .. - :2 GaEEK - GpPO?N - ? I ? ? r- - - - SPNTPGO ?? 22 w?? Ir1 !J vp n YESTN INSTE EVENTEENT SEV TEENT X00 \ n??D?DDooo gtiq c CIV CENTE Da, U?O??00?00 .rui= ??I ? ANTP ? o ?? FIRST a III ???O?000? I O LL ..??llu r FIRST nCFAODEN L EE= I-' oa ?? ncFaooEN EOI NGER r - E I n ? o.,,.o o a X Y ?a EOINGER E e ?E WARNER (II ?u V u L_J YPRNER u ? ?i ??n a Q?a P=P cer. g s (?P $E RSTR IIr OYER 2 c 5 a ¢ ? ? ?+' hp c¢uelrt ? NR[RRTRUH = ? o a ??? ? rt ??. NP ARTR R '?? $UNFLOWE ?S P \\9N ?? SUNFLOWER S Q> DI T \Rti'Y FAIRVIEW TRIANGLE EXHIBIT 1 SANTA ANA CITY AGENDAOUNCII p PROJECT 0&-am ¦ H ¦ VVu DATE: FAHVEW TIPIMCtiE HABITAT FESI )RATIM PUBLIC KRKS AOENCI SEPTEMBER 7, 2011 0%ok A MM NTS \Rwy r1?N oRANC 3 ? o z o , 1 23A-6 FUNDING ANALYSIS PROJECT NO. 08-6028 FAIRVIEW TRIANGLE HABITAT RESTORATION Construction Contract $93,207 Contract Administration $2,432 Inspection and Testing $6,000 Survey Staking $3,500 Contingencies $18,641 TOTAL ESTIMATED CONSTRUCTION COSTS 123 780 Exhibit 2 23A-7 23A-8