CITY COUNCIL MEETING DATE:
DECEMBER 5, 2011
TITLE:
APPROPRIATION ADJUSTMENT FOR
BRISTOL STREET BIKE LANE EXTENSION
_ ? L-
2?CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
0 Ordinance on 'I?` Reading
? Ordinance on 2"d Reading
0 Implementing Resolution
(] Set Public Hearing For
CONTINUED TO
FILE NUMBER
Approve an appropriation adjustment accepting funds in the amount of $64,800 into the Select
Street Construction Revenue Run for Federal Grants (accounting unit 05917002-52026) and
appropriating $64,800 to the Select Street Construction Expense Fund for Improvements Other
Than Buildings (accounting unit 05917660-66220) for the Bristol Street bike lane extension.
DISCUSSION
On March 7, 2011 the City Council authorized the applications for project funding through the
Bicycle Transportation Account (BTA) administered by the California Department of
Transportation (Caltrans) and authorized the Executive Director of the Public Works Agency to
execute needed documents to obtain the grant funding. BTA funds are designated for bicycle
related improvement projects to better integrate transportation facilities into the surrounding
community. One of the BTA applications submitted was for the implementation of class II (on-
street) bike lanes on Bristol Street from McFadden Avenue to Edinger Avenue.
On September 14, 2011 Caltrans notified the City of the BTA grant award for the Bristol Street
bike lanes from McFadden Avenue to Edinger Avenue. Subsequently, on October 1 7, 201 1 ,
Caltrans and the City entered into an agreement authorizing BTA funding up to $64,800 for this
project. City staff expects to advertise this project in early 2012.
Bristol Street class II (on-street) bike lanes are identified in the Santa Ana Bikeway Master Plan.
Currently, Bristol Street between First Street and McFadden Avenue is the only section of Bristol
Street that has existing class II (on-street) bike lanes. This project will extend the existing class II
bike lanes along Bristol Street from McFadden Avenue up to Edinger Avenue to better serve the
needs of the bicycling community.
20B-1
Appropriation Adjustment for
Bristol Street Bike Lane Extension
December 5, 2011
Page 2
FISCAL IMPACT
Upon approval of the appropriation adjustment, funds will be available in the Transportation
Enhancement Fund (accounting unit 05917660-66220) for this project.
(((??? LlV?- ? _
ill r? Raul Godinez II
`? Executive Director
Public Works Agency
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez ??
Executive Director
Finance & Management Services Agency
RG/SA
Exhibit : Appropriation Adjustment