RECOMMENDED ACTION
Award a contract to Joud Construction Company, Inc. the lowest responsible bidder, in
accordance with the bid quantity prices in the amount of $91,170 for construction of the
Santa Ana Regional Transportation Center Improvements.
2. Approve a funding analysis with a total estimated construction cost of $118,519.
DISCUSSION
The Santa Ana Regional Transportation Center (SARTC) is the focal point of transportation in
Orange County with an overall estimated weekday visitor count of 2,995 a day. Built in 1985,
the SARTC's Spanish-style architecture is complemented by an outdoor courtyard and viewing
decks adjacent to the train platforms. Due to age, weather, and high usage the balusters of
the staircase and viewing deck along the south end of the courtyard have become deteriorated
and are in need of replacement.
Work includes the removal and replacement of the pre-cast concrete caps, bases, and
balustrades, forged steel handrails, and warning striping on stair treads. All work will bring the
stairway and deck balustrades in compliance with the 2010 California Building Code and
Americans with Disabilities Act guidelines.
Bids were opened on July 23, 2012. A summary of the bid invitations mailed, the bids received
and the bid results are as follows:
23B-1
Contract Award for
SARTC Improvements
August 20, 2012
Page 2
Contractors requesting bidding documents
Santa Ana contractors receiving notices:
Total bids received:
Bids received from Santa Ana contractors:
3
13
1
0
NAME OF RESPONSIVE BIDDER
1. Joud Construction Company, Inc
CITY BASE BID AMOUNT
Corona $91,170
The Engineer's estimate was $85,313. This was a rebid of the project originally opened May
30, 2012 which was withdrawn due to insufficient advertising. The original bid opening resulted
in six bids with the lowest bid being $98,700.
With this rebid, bid notices were mailed out to the same contractors as before. Only one bid
was received and it is deemed responsive; therefore it is recommended that the City award the
contract to the sole bidder, Joud Construction Company, Inc. in the amount of $91,170.
ENVIRONMENTAL IMPACT
Environmental Review #ER-2012-48 has been completed and a Notice of Exemption has been
filed pursuant to the California Environmental Quality Act.
FISCAL IMPACT
The funding analysis shows a total estimated construction cost of $118,519 for the project
(Exhibit 2). Funds are available in the Depot enterprise (accounting unit 06717650-66200).
APPROVED AS TO FUNDS AND ACCOUNTS:
Raul Godi ez II
Executive Pi rector
Public WoRh s Agency
RG/KW
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
Exhibits: 1. Project Location Map
2. Funding Analysis
23B-2
,l
LEGEND
PROJECT LOCATION
EXHIBIT 1
SANTA ANA CITY COUNC I L T I TLE l CONTRACT AWARD FOR
P^ AGENDA SANTA ANA REGIONAL TRANSPORTATION
uDATE: CENTER EXTERIOR IMPROVEMENTS
PWLIC MSnWEWY August 20, 2012 (PROJECT NO. 126063)
23B-3
w
3RD ST z
Exhibit 2
FUNDING ANALYSIS
PROJECT NOS. 126063
SANTA ANA REGIONAL TRANSPORTATION CENTER IMPROVEMENTS
Construction Contract $ 91,170
Contract Administration $6,837
Inspection and Testing $6,837
Contingencies $ 13,675
TOTAL ESTIMATED CONSTRUCTION COSTS $118,519
23B-4